West Alabama Paving and Drainage
PROJECT NUMBER N-000751-0001
LOCATION Buffalo Speedway to Weslayan
COUNCIL DISTRICT C
BUDGET $14,567,455
TYPE Paving and Drainage
START Winter 2022
COMPLETION Winter 2024
DETAILS Construction of concrete paving with storm drainage, bike lanes, curbs, sidewalks, driveways, street lighting, and necessary underground utilities. Replace asphalt and concrete pavement sections and base material depending on the street condition. New pavement markings will be implemented at various levels depending on the extent of roadway surface rehabilitation.
MAP
General Project Information
What is the purpose of this project? This project is designed to improve safety and mobility along West Alabama from Buffalo Speedway to Weslayan. | |
Have More Questions? Click here for more answers
PROJECT NUMBER N-000751-0001
LOCATION Buffalo Speedway to Weslayan
COUNCIL DISTRICT C
BUDGET $14,567,455
TYPE Paving and Drainage
START Winter 2022
COMPLETION Winter 2024
DETAILS Construction of concrete paving with storm drainage, bike lanes, curbs, sidewalks, driveways, street lighting, and necessary underground utilities. Replace asphalt and concrete pavement sections and base material depending on the street condition. New pavement markings will be implemented at various levels depending on the extent of roadway surface rehabilitation.
MAP
General Project Information
What is the purpose of this project? This project is designed to improve safety and mobility along West Alabama from Buffalo Speedway to Weslayan. | |
Have More Questions? Click here for more answers
Is there anything you want us to know?
-
Share Beautiful project completions thus far. What is the status of Kipling Street? on Facebook Share Beautiful project completions thus far. What is the status of Kipling Street? on Twitter Share Beautiful project completions thus far. What is the status of Kipling Street? on Linkedin Email Beautiful project completions thus far. What is the status of Kipling Street? link
Beautiful project completions thus far. What is the status of Kipling Street?
rebenson asked 4 months agoThank you for your question! Regarding Kipling (Saint to Edloe) and Joanel (W Alabama to Westheimer), work had started back in November (cleaning/maintaining ditches/culverts and concrete culverts extension). We had some difficulties on the TCP approval due to some narrow sections of Joanel, but as the holiday season has now ended, the contractor should proceed soon.
-
Share I just want to pass on a compliment about your contractors and superintendents on the West Alabama project. They seem to be making good progress and have really been good communicators throughout the process. I’ve had several meetings and conversations with them, and they’ve been extremely professional and courteous. I think several of the other neighbors would agree. on Facebook Share I just want to pass on a compliment about your contractors and superintendents on the West Alabama project. They seem to be making good progress and have really been good communicators throughout the process. I’ve had several meetings and conversations with them, and they’ve been extremely professional and courteous. I think several of the other neighbors would agree. on Twitter Share I just want to pass on a compliment about your contractors and superintendents on the West Alabama project. They seem to be making good progress and have really been good communicators throughout the process. I’ve had several meetings and conversations with them, and they’ve been extremely professional and courteous. I think several of the other neighbors would agree. on Linkedin Email I just want to pass on a compliment about your contractors and superintendents on the West Alabama project. They seem to be making good progress and have really been good communicators throughout the process. I’ve had several meetings and conversations with them, and they’ve been extremely professional and courteous. I think several of the other neighbors would agree. link
I just want to pass on a compliment about your contractors and superintendents on the West Alabama project. They seem to be making good progress and have really been good communicators throughout the process. I’ve had several meetings and conversations with them, and they’ve been extremely professional and courteous. I think several of the other neighbors would agree.
10 months agoHowdy Neighbor! we appreciate the positive feedback.
-
Share Will Saint Street be re-paved? It’s in terrible condition. What can be done about the dangerous ditches on Kipling between Saint Street and Edloe? on Facebook Share Will Saint Street be re-paved? It’s in terrible condition. What can be done about the dangerous ditches on Kipling between Saint Street and Edloe? on Twitter Share Will Saint Street be re-paved? It’s in terrible condition. What can be done about the dangerous ditches on Kipling between Saint Street and Edloe? on Linkedin Email Will Saint Street be re-paved? It’s in terrible condition. What can be done about the dangerous ditches on Kipling between Saint Street and Edloe? link
Will Saint Street be re-paved? It’s in terrible condition. What can be done about the dangerous ditches on Kipling between Saint Street and Edloe?
Leah Stolar asked about 1 year agoHowdy Neighbor! The overlay of Timmons and Saint will start when reconstructing the northern half of the Timmons/West Alabama intersection and Saint/West Alabama intersection. Both scheduled for Spring 2023
-
Share When will the section of West Alabama between Timmons and Edloe Streets be completed? on Facebook Share When will the section of West Alabama between Timmons and Edloe Streets be completed? on Twitter Share When will the section of West Alabama between Timmons and Edloe Streets be completed? on Linkedin Email When will the section of West Alabama between Timmons and Edloe Streets be completed? link
When will the section of West Alabama between Timmons and Edloe Streets be completed?
JJohnston asked over 1 year agoHowdy Neighbor! The overlay of Timmons and Saint will start when reconstructing the northern half of the Timmons/West Alabama intersection and Saint/West Alabama intersection. Both scheduled for Spring 2023
-
Share Hello, are the detailed construction drawings available? Also, is there an updated project timeline that is available? Thank you on Facebook Share Hello, are the detailed construction drawings available? Also, is there an updated project timeline that is available? Thank you on Twitter Share Hello, are the detailed construction drawings available? Also, is there an updated project timeline that is available? Thank you on Linkedin Email Hello, are the detailed construction drawings available? Also, is there an updated project timeline that is available? Thank you link
Hello, are the detailed construction drawings available? Also, is there an updated project timeline that is available? Thank you
Gregg asked over 1 year agoHowdy Neighbor, thank you for submitting your question. You may visit the website at www.engagehouston.org to review all exhibits pertaining to the West Alabama project, in addition to the FAQ sheet that provides the project timeline. We also would encourage you to subscribe to the project page to receive automatic updates. Thank you.
-
Share Why are you taking traffic lane out when the residential and automobile traffic is increasing? on Facebook Share Why are you taking traffic lane out when the residential and automobile traffic is increasing? on Twitter Share Why are you taking traffic lane out when the residential and automobile traffic is increasing? on Linkedin Email Why are you taking traffic lane out when the residential and automobile traffic is increasing? link
Why are you taking traffic lane out when the residential and automobile traffic is increasing?
JJohnston asked about 2 years agoThank you for your question. Vehicular traffic may have increased but the current vehicular volume can be supported by one lane in each direction with a continuous center left-turn lane.
-
Share How do I get a copy of the traffic plan? on Facebook Share How do I get a copy of the traffic plan? on Twitter Share How do I get a copy of the traffic plan? on Linkedin Email How do I get a copy of the traffic plan? link
How do I get a copy of the traffic plan?
JJohnston asked about 2 years agoThank you for your question. The Traffic Control Plans are located on this project page under documents.
Follow Project
Project Phase
Videos & Recordings
Documents
- Virtual Community Meeting on November 30, 2021
- Meeting Materials
- Construction Materials
- Plans
-
Exhibits
- West Alabama Mill and Overlay Construction Phasing Map.pdf (803 KB) (pdf)
- Design Features Exhibit (5.95 MB) (pdf)
- Intersection Improvements (442 KB) (pdf)
- Existing vs. Proposed Design (407 KB) (pdf)
- Existing Typical Sections (731 KB) (pdf)
- Proposed Improvements Map (5.98 MB) (pdf)
- Proposed Typical Sections (425 KB) (pdf)
- Renderings (936 KB) (pdf)