Richmond Plaza (South) Improvements

Share Richmond Plaza (South) Improvements on Facebook Share Richmond Plaza (South) Improvements on Twitter Share Richmond Plaza (South) Improvements on Linkedin Email Richmond Plaza (South) Improvements link

PROJECT NUMBER M-410023-0001

LOCATION Refer to map

COUNCIL DISTRICT J

BUDGET $18,953,794

TYPE Drainage

START Winter 2023

COMPLETION Fall 2024

DETAILS Design and construction of stormwater drainage and paving improvements, and necessary utility upgrades.


MAP

Project Map


General Project Information

What is the purpose of this project?
The purpose of the project is to construct storm drainage improvements that address and reduce the risk of structural flooding in the area by improving street conveyance and sheet flow and providing detention, as needed, for mitigation.


Have More Questions? Click here for more answers.

PROJECT NUMBER M-410023-0001

LOCATION Refer to map

COUNCIL DISTRICT J

BUDGET $18,953,794

TYPE Drainage

START Winter 2023

COMPLETION Fall 2024

DETAILS Design and construction of stormwater drainage and paving improvements, and necessary utility upgrades.


MAP

Project Map


General Project Information

What is the purpose of this project?
The purpose of the project is to construct storm drainage improvements that address and reduce the risk of structural flooding in the area by improving street conveyance and sheet flow and providing detention, as needed, for mitigation.


Have More Questions? Click here for more answers.

  • Latest News

    Share Latest News on Facebook Share Latest News on Twitter Share Latest News on Linkedin Email Latest News link

    The contractor is scheduled to begin work on Evergreen Street (between Chimney Rock and Mapleridge) in August 2024, with an expected completion in September 2024. Please note that the timeline may be adjusted due to weather conditions. Residents will receive notifications a few days prior to the start of work on their street. The contractor will ensure continuous communication throughout the project and provide access as needed. The project is on track for completion in Fall 2024.

  • Latest News

    Share Latest News on Facebook Share Latest News on Twitter Share Latest News on Linkedin Email Latest News link

    The project has been partially completed and is facing a delay of around three weeks due to utility conflicts on Evergreen Street. This road is crucial for this project as all the side streets rely on it. The contractor is presently focusing on storm improvements along Evergreen Street from Alder Dr to Chimney Rock Rd. They have already completed the sanitary and water improvements. Once this section is completed, the next phase of work will begin on Alder Drive. from Evergreen Street. to Bissonnet Road. We are confident there will be no issues in completing the project on time.


  • Latest News

    Share Latest News on Facebook Share Latest News on Twitter Share Latest News on Linkedin Email Latest News link

    The project is approximately 5% completed in place. Construction activities currently include the installation of wastewater and water lines on Evergreen between Alder and Chimney Rock.


Page last updated: 21 Aug 2024, 04:40 PM