Missouri Kansas Texas Trail Spur Connector

Share on Facebook Share on Twitter Share on Linkedin Email this link

PROJECT NUMBER N-320420-030A

LOCATION Refer to project map

COUNCIL DISTRICT C

BUDGET $1,179,480

TYPE Paving

START Winter 2021

COMPLETION Spring 2022

DETAILS This project consist of construction of a hike and bike trail. This trail connection is one of the last critical pieces needed for the White Oak Bayou/ MKT Hike and Bike system.


MAPProject Map




What is the purpose of this project?

It will provide the link from MKT Hike and Bike Trail to Stude Park, connecting a dead end under Studemont Street.

How long is the project going to take to complete?
5.5 months (157 calendar days). Work is scheduled to begin Winter 2021 and anticipated to be completed on Spring 2022. The project schedule depends upon weather conditions.



Have More Questions? Click here for more answers


PROJECT NUMBER N-320420-030A

LOCATION Refer to project map

COUNCIL DISTRICT C

BUDGET $1,179,480

TYPE Paving

START Winter 2021

COMPLETION Spring 2022

DETAILS This project consist of construction of a hike and bike trail. This trail connection is one of the last critical pieces needed for the White Oak Bayou/ MKT Hike and Bike system.


MAPProject Map




What is the purpose of this project?

It will provide the link from MKT Hike and Bike Trail to Stude Park, connecting a dead end under Studemont Street.

How long is the project going to take to complete?
5.5 months (157 calendar days). Work is scheduled to begin Winter 2021 and anticipated to be completed on Spring 2022. The project schedule depends upon weather conditions.



Have More Questions? Click here for more answers


Is there anything you want us to know?

You need to be signed in to add your question.

  • Share on Facebook Share on Twitter Share on Linkedin Email this link

    It appears that there is still much work to be done until this section of trail is finished. Can we please get an update on the expected completion date of this project?

    ChrisH. asked almost 2 years ago

    Teamwork Construction Services (Contractor) is forecasted to complete work on the MKT Trail Spur Connector mid-July.

  • Share on Facebook Share on Twitter Share on Linkedin Email this link

    I see there is now visible progress on this project. Is completion still expected this quarter?

    markwmsn asked almost 2 years ago

    Thank you for your question. The project is moving in full force. We expect completion in mid-July 2022 due to unforeseeable site conditions.

  • Share on Facebook Share on Twitter Share on Linkedin Email this link

    Hello, can you provide an update since it doesn’t look like there’s been any progress?

    Joeyjoe asked about 2 years ago

    The contractor had some delays with permits and the construction activities for this project commenced last week. Thank you.

  • Share on Facebook Share on Twitter Share on Linkedin Email this link

    It doesn't look like much progress has been made since early November, are there delays in the schedule that have come up?

    Twisterhunt asked over 2 years ago

    Thank you for your inquiry. The contractor was previously working on pre-construction deliverables. This week they began to mobilize to the area to begin the construction. You should begin to see work begin soon.

  • Share on Facebook Share on Twitter Share on Linkedin Email this link

    Will future work on the MKT bridge over White Oak Bayou impact use of the new trail connector when it's completed?

    Hindesky asked over 2 years ago

    Thank you for your question. Houston Park Board will shift their construction access to the other side (west side) of the trail to avoid a conflict with the new spur connector trail once completed.

  • Share on Facebook Share on Twitter Share on Linkedin Email this link

    I was wondering about the status of this Project. I live close by and cannot see any activity. Please advise. Thanks/Jorgen

    Jorgen asked over 2 years ago

    Thank you for your inquiry. The contract for this project was awarded to the contractor in September 2021 and construction is expected to begin November 2021.