Missouri Kansas Texas Trail Spur Connector
Share on Facebook
Share on Twitter
Share on Linkedin
Email this link
PROJECT NUMBER N-320420-030A
LOCATION Refer to project map
COUNCIL DISTRICT C
BUDGET $1,179,480
TYPE Paving
START Winter 2021
COMPLETION Spring 2022
DETAILS This project consist of construction of a hike and bike trail. This trail connection is one of the last critical pieces needed for the White Oak Bayou/ MKT Hike and Bike system.
MAP
What is the purpose of this project? It will provide the link from MKT Hike and Bike Trail to Stude Park, connecting a dead end under Studemont Street. | |
How long is the project going to take to complete? 5.5 months (157 calendar days). Work is scheduled to begin Winter 2021 and anticipated to be completed on Spring 2022. The project schedule depends upon weather conditions. |