Lift Station Renewal and Replacement- Macgregor Way North #3, Wheeler, Gilpin, West Orem, Quail View, and Hillcroft Lift Stations

Share on Facebook Share on Twitter Share on Linkedin Email this link

PROJECT NUMBER R-000267-0160

LOCATION Refer to Project Map

COUNCIL DISTRICT D, E & K

BUDGET $14,925,300

TYPE Wastewater

START Spring 2023

COMPLETION Spring 2024

DETAILS The project provides for the rehabilitation of six wastewater lift stations. The rehabilitation includes site work and improvements to various equipment.


MAP

Project MapGeneral Project Information

What is the purpose of this project?
The work for this project includes the rehabilitation of six (6) lift stations. The rehabilitation includes site work, pumps, piping, valves, supports, instrumentation, electrical, and various improvements. This project is needed for reliable and efficient collection of Wastewater throughout the City.

How long is this project going to take to complete?
17 months (510 calendar days). Work is scheduled to begin in Spring 2023 and is anticipated to be completed in Spring 2024. The project schedule depends upon weather conditions. Please see the phasing map for details
.

Have More Questions? Click here for more answers

PROJECT NUMBER R-000267-0160

LOCATION Refer to Project Map

COUNCIL DISTRICT D, E & K

BUDGET $14,925,300

TYPE Wastewater

START Spring 2023

COMPLETION Spring 2024

DETAILS The project provides for the rehabilitation of six wastewater lift stations. The rehabilitation includes site work and improvements to various equipment.


MAP

Project MapGeneral Project Information

What is the purpose of this project?
The work for this project includes the rehabilitation of six (6) lift stations. The rehabilitation includes site work, pumps, piping, valves, supports, instrumentation, electrical, and various improvements. This project is needed for reliable and efficient collection of Wastewater throughout the City.

How long is this project going to take to complete?
17 months (510 calendar days). Work is scheduled to begin in Spring 2023 and is anticipated to be completed in Spring 2024. The project schedule depends upon weather conditions. Please see the phasing map for details
.

Have More Questions? Click here for more answers

  • Latest News

    Share on Facebook Share on Twitter Share on Linkedin Email this link

    We are at 60% work completed and on track with the completion date of June 2024.