Garden Oaks and Shepherd Park (West)
PROJECT NUMBER M-410017-0001
LOCATION Refer to Project Map
COUNCIL DISTRICT C
BUDGET $23,692,336
TYPE Drainage
START Summer 2021
COMPLETION Spring 2024
DETAILS Construction of stormwater drainage and paving improvements and necessary utility upgrades.
MAP
General Project Information
What is the purpose of this project? The purpose of the project is to construct storm drainage improvements that address and reduce the risk of structural flooding in the area by improving street conveyance and sheet flow and providing detention, as needed, for mitigation. The benefitted area of the project includes the Garden Oaks and Shepherd Park Plaza subdivisions. | |
How long is this project going to take to complete?28 months (835 calendar days). Work is scheduled to begin on Monday, August 30, 2021 and anticipated to be completed on Fall 2023. The project schedule depends upon weather conditions |
Have More Questions? Click here for more answers
PROJECT NUMBER M-410017-0001
LOCATION Refer to Project Map
COUNCIL DISTRICT C
BUDGET $23,692,336
TYPE Drainage
START Summer 2021
COMPLETION Spring 2024
DETAILS Construction of stormwater drainage and paving improvements and necessary utility upgrades.
MAP
General Project Information
What is the purpose of this project? The purpose of the project is to construct storm drainage improvements that address and reduce the risk of structural flooding in the area by improving street conveyance and sheet flow and providing detention, as needed, for mitigation. The benefitted area of the project includes the Garden Oaks and Shepherd Park Plaza subdivisions. | |
How long is this project going to take to complete?28 months (835 calendar days). Work is scheduled to begin on Monday, August 30, 2021 and anticipated to be completed on Fall 2023. The project schedule depends upon weather conditions |
Have More Questions? Click here for more answers
Is there anything you want us to know?
-
Share on Facebook Share on Twitter Share on Linkedin Email this link
How is access handled for houses on a culdesac/circle with only one entrace/exit route. Will we lose access, or have to park and walk to get to our house?
Cooldesac asked about 1 year agoHowdy Neighbor! Thank you for your questions! The contractor will have a flagger during construction at the entrance directing residents in and out of the cul-de-sac. Driveway access will be maintained during underground construction unless the contractor is preparing the street and/or pavement.
-
Share on Facebook Share on Twitter Share on Linkedin Email this link
Your Tree Inventory list shows that my Tree #504 is a PINE in FAIR condition. It is a 38-year old OAK tree-in GOOD condition. Will this change your Treatment/Mitigation for this tree?
dottigarciaChantilly asked about 1 year agoHowdy Neighbor! Thank you for your question! The work proposed should not affect the tree in subject. There will only be minor root trimming if the roots are in conflict with the sidewalk installation.
-
Share on Facebook Share on Twitter Share on Linkedin Email this link
Where can I find more details of the root shaving plans for trees that were marked as such? I have reviewed the Tree Protection Plan but it is not clear. Which arborist are you working with for trees that will be modified?
jared.mcallister asked about 1 year agoHowdy Neighbor! Thank you for your questions! For additional information regarding tree pruning, please refer to the project webpage and review the tree protection plan on sheet 22, detail number two. Also, please contact the contractor for more information on the arborist. This information can be found in the Frequently Asked Questions document also located on the project webpage.
-
Share on Facebook Share on Twitter Share on Linkedin Email this link
When will the final pavement work be completed in the intersection area of Fisher and Golf? All work has been completed in this area but the final blacktop has not yet been installed.
nathan.montgomery asked about 1 year agoHowdy Neighbor! Thank you for your question! Majority of the work in this area has been completed with the exception of the installation of the blacktop overlay. The contractor is also finalizing ditch work in that area. Once the work is completed, the contractor will begin the last overlay. The overlay process will be completed by the end of next month dependent on weather conditions and any unforeseen circumstances.
-
Share on Facebook Share on Twitter Share on Linkedin Email this link
Who is the concrete company installing the driveways etc in Garden Oaks by Golf?
Kris asked over 1 year agoTotal Contracting Limited is the contractor performing the major work in Garden Oaks. There are also private builders in the area working which is not related to our project.
-
Share on Facebook Share on Twitter Share on Linkedin Email this link
Hi It’s mentioned in another question about not being able to access driveways for 21 days. Does that mean we need to street park for 21 days outside our house or have to park outside of the construction zone? Thanks
Chamboard asked over 1 year agoHowdy Neighbor! Yes, it means you need to street park for about 21 days. Thanks
-
Share on Facebook Share on Twitter Share on Linkedin Email this link
When is an estimate for work to begin on Thornton Rd at Clift Haven, 77018?
Dchbbc asked over 1 year agoHowdy neighbor! Per the contractor, they plan on beginning there in Q2 of 2023 but that might change due to many factors related to construction.
-
Share on Facebook Share on Twitter Share on Linkedin Email this link
When will Fisher East be impacted ? In terms of project on time satus, ow is this project progressing?
jeremiah_wheeler asked over 1 year agoHowdy Neighbor! The construction team has plans to start working on the east side of Fisher in approximately 2 weeks.
-
Share on Facebook Share on Twitter Share on Linkedin Email this link
When will the construction reach Golf & Chamboard Ln and will we be able to get into our driveways during the disruption?
MikeChamboard asked almost 2 years agoThe construction will reach Golf and Chamboard in the 4th quarter of 2022. The residents will have access to the their driveways while contractor is installing underground work. Once the contractor begin to pour concrete for street and driveways, the residents will not have access to their driveways for 21 days. -
Share on Facebook Share on Twitter Share on Linkedin Email this link
When is construction expected to begin on Brian Haven?
Alh733 asked almost 2 years agoThank you for your question. The contractor stated that construction on Brian heaven is anticipated for the first quarter of 2023 (Jan-Mar).
Follow Project
Project Phase
Who's Listening?
Public Engagement Team
Email Us: | Engage@houstontx.gov |