Garden Oaks and Shepherd Park (West)

Share on Facebook Share on Twitter Share on Linkedin Email this link

PROJECT NUMBER M-410017-0001

LOCATION Refer to Project Map

COUNCIL DISTRICT C

BUDGET $23,692,336

TYPE Drainage

START Summer 2021

COMPLETION Spring 2024

DETAILS Construction of stormwater drainage and paving improvements and necessary utility upgrades.


MAP

project map


General Project Information


What is the purpose of this project?
The purpose of the project is to construct storm drainage improvements that address and reduce the risk of structural flooding in the area by improving street conveyance and sheet flow and providing detention, as needed, for mitigation. The benefitted area of the project includes the Garden Oaks and Shepherd Park Plaza subdivisions.


How long is this project going to take to complete?

28 months (835 calendar days). Work is scheduled to begin on Monday, August 30, 2021 and anticipated to be completed on Fall 2023. The project schedule depends upon weather conditions


Have More Questions? Click here for more answers

PROJECT NUMBER M-410017-0001

LOCATION Refer to Project Map

COUNCIL DISTRICT C

BUDGET $23,692,336

TYPE Drainage

START Summer 2021

COMPLETION Spring 2024

DETAILS Construction of stormwater drainage and paving improvements and necessary utility upgrades.


MAP

project map


General Project Information


What is the purpose of this project?
The purpose of the project is to construct storm drainage improvements that address and reduce the risk of structural flooding in the area by improving street conveyance and sheet flow and providing detention, as needed, for mitigation. The benefitted area of the project includes the Garden Oaks and Shepherd Park Plaza subdivisions.


How long is this project going to take to complete?

28 months (835 calendar days). Work is scheduled to begin on Monday, August 30, 2021 and anticipated to be completed on Fall 2023. The project schedule depends upon weather conditions


Have More Questions? Click here for more answers

  • April 2023 Update

    Share on Facebook Share on Twitter Share on Linkedin Email this link

    Project is currently 60% completed in place. Restoration is 100% completed for Wakefield, Fisher, Rosepoint. The contractor is regrading ditches along Golf Drive.

  • January 2023 Update

    Share on Facebook Share on Twitter Share on Linkedin Email this link
    Underground construction up to W43rd has been completed.


Page last updated: 12 Mar 2024, 03:18 PM