72-Inch Water Line from Crawford to Mt. Vernon

Share 72-Inch Water Line from Crawford to Mt. Vernon on Facebook Share 72-Inch Water Line from Crawford to Mt. Vernon on Twitter Share 72-Inch Water Line from Crawford to Mt. Vernon on Linkedin Email 72-Inch Water Line from Crawford to Mt. Vernon link

PROJECT NUMBER S-000900-0134

LOCATION 72-Inch Water Line from Crawford to Mt. Vernon

COUNCIL DISTRICT C & D

BUDGET $48.8 Million

TYPE Water Line

START Summer 2022

COMPLETION Summer 2024

DETAILS The project provides for the following upgrades: waterlines, sanitary and storm systems, and new concrete pavements.


MAP

project map


General Project Information

What is the purpose of this project?
The 72-Inch water transmission main will carry potable water to the City’s Southwest Pump Station to increase the overall capacity in the region's drinking water.

How long is this project going to take to complete?
24 months (730 calendar days). Work is scheduled to begin in early Summer 2022 and is anticipated to be completed in Summer 2024. The project schedule depends upon weather conditions.

Have More Questions? Click here for more answers

PROJECT NUMBER S-000900-0134

LOCATION 72-Inch Water Line from Crawford to Mt. Vernon

COUNCIL DISTRICT C & D

BUDGET $48.8 Million

TYPE Water Line

START Summer 2022

COMPLETION Summer 2024

DETAILS The project provides for the following upgrades: waterlines, sanitary and storm systems, and new concrete pavements.


MAP

project map


General Project Information

What is the purpose of this project?
The 72-Inch water transmission main will carry potable water to the City’s Southwest Pump Station to increase the overall capacity in the region's drinking water.

How long is this project going to take to complete?
24 months (730 calendar days). Work is scheduled to begin in early Summer 2022 and is anticipated to be completed in Summer 2024. The project schedule depends upon weather conditions.

Have More Questions? Click here for more answers

  • Latest News

    Share Latest News on Facebook Share Latest News on Twitter Share Latest News on Linkedin Email Latest News link

    The project has underground utilities installed throughout. The contractor is currently backfilling the shafts along Holman Street before repaving the entire stretch. Simultaneously, they are paving Tuam Street. The reconstruction of Holman and Tuam Street is a priority. The contractor is progressing according to schedule, and the completion date is Summer 2024.

  • Latest News

    Share Latest News on Facebook Share Latest News on Twitter Share Latest News on Linkedin Email Latest News link

    All four locations: Kipling, Hawthorne, Garrott, and Emerson have completed their underground work, paving for pavement, sidewalks, and driveways, as well as landscaping and sod installation, with a 100% completion rate.


    Audubon:

    Underground – 100% Complete

    Paving (Pavement/Sidewalks/Driveways) - 100% Complete

    Landscaping/Sod – 85% Complete – Anticipated Completion March 2024


    Holman:

    Underground – 50% Complete – Anticipated Completion September 2024

    Paving (Pavement/Sidewalks/Driveways) - 0% Complete - Anticipated Completion October 2024

    Landscaping/Sod – 0% Complete – Anticipates Completion October 2024


    Fannin:

    Underground – 80% Complete - Anticipated Completion September 2024

    Paving (Pavement/Sidewalks/Driveways) – 80% Complete - Anticipated Completion October 2024

    Landscaping/Sod – 30% Complete - Anticipates Completion October 2024


    Tuam:

    Underground – 60% Complete (Large Diameter Water Line) – Anticipated Completion August 2024

    Paving (Pavement/Sidewalks/Driveways) - 15% Complete – Anticipated Completion September 2024

    Landscaping/Sod – 0% Complete – Anticipated Completion September 2024

Page last updated: 25 Mar 2024, 11:28 AM