Abandonment of Bering and San Felipe Lift Stations

Share on Facebook Share on Twitter Share on Linkedin Email this link

PROJECT NUMBER R-000536-0026

LOCATION Refer to project map

COUNCIL DISTRICT G

BUDGET $19,677,850

TYPE Wastewater

START Spring 2021

COMPLETION Spring 2024

DETAILS The project provides for the installation of new wastewater system lines and the abandonment of two lift stations. This project also provides the diversion of flow from the previous wastewater lines to the new wastewater lines.


MAP

project map



What is the purpose of this project?
The purpose of this project is to install a wastewater system ( ranging in size from *-inch to 18-inch) on Bering Drive, divert wastewater flows with 30-inch to 48-inch gravity lines on San Felipe Drive and Fountain View Drive, and decommission two Lift Stations.
How long is this project going to take to complete?
Approximately 25 months (765 calendar days). Work is scheduled to begin in Spring 2021 and is anticipated to be completed in Winter 2024. The project schedule depends upon weather conditions.


Have More Questions? Click here for more answers.

PROJECT NUMBER R-000536-0026

LOCATION Refer to project map

COUNCIL DISTRICT G

BUDGET $19,677,850

TYPE Wastewater

START Spring 2021

COMPLETION Spring 2024

DETAILS The project provides for the installation of new wastewater system lines and the abandonment of two lift stations. This project also provides the diversion of flow from the previous wastewater lines to the new wastewater lines.


MAP

project map



What is the purpose of this project?
The purpose of this project is to install a wastewater system ( ranging in size from *-inch to 18-inch) on Bering Drive, divert wastewater flows with 30-inch to 48-inch gravity lines on San Felipe Drive and Fountain View Drive, and decommission two Lift Stations.
How long is this project going to take to complete?
Approximately 25 months (765 calendar days). Work is scheduled to begin in Spring 2021 and is anticipated to be completed in Winter 2024. The project schedule depends upon weather conditions.


Have More Questions? Click here for more answers.

  • Latest News

    Share on Facebook Share on Twitter Share on Linkedin Email this link

    The Contractor for this project states: The work along San Felipe St. is complete. The work along Fountain View Drive is complete. The work along Bering Drive is expected to take another six to seven weeks with an estimated completion timeline of early April (Spring 2024). During this time, the newly installed piping system will undergo testing and constituents can expect to see traffic control measures removed near the intersection of Bering and San Felipe in the coming weeks.

  • Latest News

    Share on Facebook Share on Twitter Share on Linkedin Email this link

    The prime Contractor from Harper Brothers Construction continues to make adjustments to the wastewater system. Harper Brothers Construction added additional personnel to expedite the work. Additionally, the Contractor plans to complete the work by Fall 2023 and connect the new system by Winter 2024.

  • Latest News

    Share on Facebook Share on Twitter Share on Linkedin Email this link

    The project is currently 80% completed in place. The contractor has completed the installation of wastewater lines along Fountain View Drive, between Westheimer Road and San Felipe Street, along with site restoration. The contractor is currently completing the installation of the sanitary sewer lines along San Felipe Street and Bering Drive. The remaining work and restoration along San Felipe and Bering is anticipated to be completed by the end of June 2023.

  • Latest News

    Share on Facebook Share on Twitter Share on Linkedin Email this link

    The project completion time has been updated.

Page last updated: 16 Feb 2024, 04:57 PM