We anticipate that the remaining work will extend for another eight to ten weeks, putting the estimated completion timeframe around mid-June or Spring 2024. The delay primarily stems from the testing protocols required for the reinstalled sections of the pipeline. As per these testing guidelines, the Contractor must wait for a 30-day period before conducting the necessary inspections on the pipe. However, there is a silver lining as we anticipate the removal of traffic control measures along a short section of Bering (near San Felipe) by month's end.