Reconstruction of Holmes Road

Share Reconstruction of Holmes Road on Facebook Share Reconstruction of Holmes Road on Twitter Share Reconstruction of Holmes Road on Linkedin Email Reconstruction of Holmes Road link

PROJECT NUMBER N-000590-0001

LOCATION Refer to map

COUNCIL DISTRICT K

BUDGET $22,257,934

TYPE Street

START Fall 2019

COMPLETION Spring 2024

DETAILS Reconstructing Holmes Road from Kirby Drive to Main from 2-lane asphalt to 4-lane concrete pavement with storm sewer improvement: Install 4,000 linear feet of sanitary sewers from Kirby Drive to Buffalo Speedway.


MAP


General Project Information

What is the purpose of this project?
Improve Holmes Road and install sanitary sewer for future capacity needs.

How long is the project going to take?
Work began in Fall 2019 and is anticipated to be completed in Spring 2024. The project schedule depends upon weather conditions.

Have More Questions? Click here for more answers.

PROJECT NUMBER N-000590-0001

LOCATION Refer to map

COUNCIL DISTRICT K

BUDGET $22,257,934

TYPE Street

START Fall 2019

COMPLETION Spring 2024

DETAILS Reconstructing Holmes Road from Kirby Drive to Main from 2-lane asphalt to 4-lane concrete pavement with storm sewer improvement: Install 4,000 linear feet of sanitary sewers from Kirby Drive to Buffalo Speedway.


MAP


General Project Information

What is the purpose of this project?
Improve Holmes Road and install sanitary sewer for future capacity needs.

How long is the project going to take?
Work began in Fall 2019 and is anticipated to be completed in Spring 2024. The project schedule depends upon weather conditions.

Have More Questions? Click here for more answers.

  • Latest News

    Share Latest News on Facebook Share Latest News on Twitter Share Latest News on Linkedin Email Latest News link

    The road is open! The City of Houston has completed the paving for the roadway project, and it is now open for use. Please note that some minor construction work may occur over the next few weeks as the construction company completes minor fixes. The final completion is Spring 2024.

  • Latest News

    Share Latest News on Facebook Share Latest News on Twitter Share Latest News on Linkedin Email Latest News link

    As of early February, Holmes Road is now open to traffic on all sides. The City of Houston is currently in the process of taking the necessary steps to formally close the project, which includes conducting final walkthroughs of the completed work and making various minor improvements. The project is expected to be fully completed by the end of this month (March).