Reconstruction of Holmes Road

Share Reconstruction of Holmes Road on Facebook Share Reconstruction of Holmes Road on Twitter Share Reconstruction of Holmes Road on Linkedin Email Reconstruction of Holmes Road link

PROJECT NUMBER N-000590-0001

LOCATION Refer to map

COUNCIL DISTRICT K

BUDGET $22,257,934

TYPE Street

START Fall 2019

COMPLETION Spring 2024

DETAILS Reconstructing Holmes Road from Kirby Drive to Main from 2-lane asphalt to 4-lane concrete pavement with storm sewer improvement: Install 4,000 linear feet of sanitary sewers from Kirby Drive to Buffalo Speedway.


MAP


General Project Information

What is the purpose of this project?
Improve Holmes Road and install sanitary sewer for future capacity needs.

How long is the project going to take?
Work began in Fall 2019 and is anticipated to be completed in Spring 2024. The project schedule depends upon weather conditions.

Have More Questions? Click here for more answers.

PROJECT NUMBER N-000590-0001

LOCATION Refer to map

COUNCIL DISTRICT K

BUDGET $22,257,934

TYPE Street

START Fall 2019

COMPLETION Spring 2024

DETAILS Reconstructing Holmes Road from Kirby Drive to Main from 2-lane asphalt to 4-lane concrete pavement with storm sewer improvement: Install 4,000 linear feet of sanitary sewers from Kirby Drive to Buffalo Speedway.


MAP


General Project Information

What is the purpose of this project?
Improve Holmes Road and install sanitary sewer for future capacity needs.

How long is the project going to take?
Work began in Fall 2019 and is anticipated to be completed in Spring 2024. The project schedule depends upon weather conditions.

Have More Questions? Click here for more answers.

Frequently Asked Questions

GENERAL PROJECT INFORMATION

Q: What is the purpose of this project?
A: The Project will replace and widen a street that has deteriorated beyond economical repair and normal maintenance. It will improve traffic circulation, mobility, and drainage in the service area. These improvements will upgrade the existing roadway to MTFP standards. This also allows additional sewer collection system capacity to be constructed.


Q: What is going to be replaced/installed in this project?
A: Will replace a 2-lane asphalt road with a 4-lane concrete thoroughfare from Kirby Drive to Holmes Road with storm drains and ditches and Construct ~4,000 LF of Sewer Collection System.


Q: How long is this project going to take to complete?
A: Original Duration was 500 days with delays and construction issues the project will be substantially complete by January 2024.


SIDEWALKS, TREES & LIGHTING

Q: Will there be Street Light Poles installed?
A: Yes, streetlights have been installed by CenterPoint.


Q: What trees are being removed?
A: The Tree Protection Plan identifies the trees to be removed, including removing diseased or dying trees. The City of Houston identifies trees that can be preserved on a case-by-case basis.


CONSTRUCTION

Q: At some point, will my utilities be affected?
A: No.




Q: Will this project cause traffic/mobility issues (lane closures, increase of trucks in the area, etc.)?
A: Yes, Road Closures on Holmes Rodd from Kirby Drive to the Buffalo Speedway Connector.




Q: Are they going to dig up the front area or just the street?
A: The front area will be reconstructed as well as the street.



Q: When will my services be transferred to the new line? 

A: This is a commercial area, mostly undeveloped.



CONTACT INFORMATION

NON-EMERGENCY NEEDS
Dial 311 - Mention to the operator the following 3 things along with your issue:
- Project number: N-000590-0001-4
- Reconstruction of Holmes Road
- Refer the questions/comments to Capital Projects

EMERGENCY NEEDS
Contact Contractor or the 24-hour contact provided by the contractor.

Contractor
Reytec Construction Resources, Inc.
Roberto Sanchez – 281-850-4890                                                                                                                                                                                                                                                                                               Carl Mitchell - 281-415-2198 

Houston Public Works
Fernando Gallegos – Inspector 713.817.5283
Melissa Jefferson – Project Manager 832.395.2217


HELPFUL LINKS

PROJECT SPECIFIC CONCERNS
Buildforward@houstontx.gov

GENERAL CONCERNS
3-1-1 or 713.837.0311
www.houston311.org

You need to be signed in to comment in this Guest Book. Click here to Sign In or Register to get involved
Page last updated: 08 Apr 2024, 09:32 AM