South Lockwood Paving and Drainage - Subproject 1

Share South Lockwood Paving and Drainage - Subproject 1 on Facebook Share South Lockwood Paving and Drainage - Subproject 1 on Twitter Share South Lockwood Paving and Drainage - Subproject 1 on Linkedin Email South Lockwood Paving and Drainage - Subproject 1 link

PROJECT NUMBER N-100027-0001-4

LOCATION South Lockwood from North of Crites Street to Suburban Street

COUNCIL DISTRICT H

BUDGET $9,698,748

TYPE Paving and Drainage

START Winter 2024

COMPLETION Summer 2025

DETAILS This project provides for the construction of concrete driveways, medians, sidewalks, bicycle facilities, storm water, water lines, sanitary sewer, street lighting, traffic signals, and necessary underground utilities, and upgrading the necessary intersections, improvement of drainage and upgrade of the existing roadway to Major Thoroughfare & Freeway Plan (MTFP) standards. The contract time for the subproject is 540 calendar days.


MAP



General Project Information

What is the purpose of this project?
This project is designed to improve mobility, drainage, and safety along South Lockwood.


How long is this project going to take to complete?
To be determined. Please subscribe to this project to receive the most up-to-date information.


Have More Questions? Click here for more answers

PROJECT NUMBER N-100027-0001-4

LOCATION South Lockwood from North of Crites Street to Suburban Street

COUNCIL DISTRICT H

BUDGET $9,698,748

TYPE Paving and Drainage

START Winter 2024

COMPLETION Summer 2025

DETAILS This project provides for the construction of concrete driveways, medians, sidewalks, bicycle facilities, storm water, water lines, sanitary sewer, street lighting, traffic signals, and necessary underground utilities, and upgrading the necessary intersections, improvement of drainage and upgrade of the existing roadway to Major Thoroughfare & Freeway Plan (MTFP) standards. The contract time for the subproject is 540 calendar days.


MAP



General Project Information

What is the purpose of this project?
This project is designed to improve mobility, drainage, and safety along South Lockwood.


How long is this project going to take to complete?
To be determined. Please subscribe to this project to receive the most up-to-date information.


Have More Questions? Click here for more answers

Is there anything you want us to know?

loader image
Didn't receive confirmation?
Seems like you are already registered, please provide the password. Forgot your password? Create a new one now.
  • Share Will table top crossings be provided at the intersections with the Harrisburg Hike/Bike Trail, Brady Street Xwalk, and the crossings at the roundabout at Canal/Lockwood? These are really good for ped/bike safety and flashing signage telling drivers to stop for peds would be incredible. on Facebook Share Will table top crossings be provided at the intersections with the Harrisburg Hike/Bike Trail, Brady Street Xwalk, and the crossings at the roundabout at Canal/Lockwood? These are really good for ped/bike safety and flashing signage telling drivers to stop for peds would be incredible. on Twitter Share Will table top crossings be provided at the intersections with the Harrisburg Hike/Bike Trail, Brady Street Xwalk, and the crossings at the roundabout at Canal/Lockwood? These are really good for ped/bike safety and flashing signage telling drivers to stop for peds would be incredible. on Linkedin Email Will table top crossings be provided at the intersections with the Harrisburg Hike/Bike Trail, Brady Street Xwalk, and the crossings at the roundabout at Canal/Lockwood? These are really good for ped/bike safety and flashing signage telling drivers to stop for peds would be incredible. link

    Will table top crossings be provided at the intersections with the Harrisburg Hike/Bike Trail, Brady Street Xwalk, and the crossings at the roundabout at Canal/Lockwood? These are really good for ped/bike safety and flashing signage telling drivers to stop for peds would be incredible.

    EastEndAaron asked over 1 year ago

    Howdy Neighbor!  This portion of the project is currently under hold and we will consider the table top options when the project gets going. Thank you!

Page last updated: 03 May 2024, 12:35 PM