South Lockwood - Subproject 1

Share South Lockwood - Subproject 1 on Facebook Share South Lockwood - Subproject 1 on Twitter Share South Lockwood - Subproject 1 on Linkedin Email South Lockwood - Subproject 1 link

PROJECT NUMBER N-100027-0001

LOCATION Refer to map

COUNCIL DISTRICT H

BUDGET $9,698,748

TYPE Street

START Winter 2024

COMPLETION Summer 2025

DETAILS This project provides for the construction of concrete driveways, medians, sidewalks, bicycle facilities, storm water, water lines, wastewater, street lighting, traffic signals, and necessary underground utilities, and upgrading the necessary intersections, improvement of drainage and upgrade of the existing roadway to Major Thoroughfare & Freeway Plan (MTFP) standards. The contract time for the subproject is 540 calendar days.


MAP


General Project Information

What is the purpose of this project?
This project is designed to improve mobility, drainage, and safety along South Lockwood.


Have More Questions? Click here for more answers.

PROJECT NUMBER N-100027-0001

LOCATION Refer to map

COUNCIL DISTRICT H

BUDGET $9,698,748

TYPE Street

START Winter 2024

COMPLETION Summer 2025

DETAILS This project provides for the construction of concrete driveways, medians, sidewalks, bicycle facilities, storm water, water lines, wastewater, street lighting, traffic signals, and necessary underground utilities, and upgrading the necessary intersections, improvement of drainage and upgrade of the existing roadway to Major Thoroughfare & Freeway Plan (MTFP) standards. The contract time for the subproject is 540 calendar days.


MAP


General Project Information

What is the purpose of this project?
This project is designed to improve mobility, drainage, and safety along South Lockwood.


Have More Questions? Click here for more answers.

  • Latest News

    Share Latest News on Facebook Share Latest News on Twitter Share Latest News on Linkedin Email Latest News link
    Exciting progress is underway on Lockwood Drive and Navigation Boulevard! Major activities are moving forward right on track, keeping the project firmly on schedule for completion by Summer 2025.
  • Latest News

    Share Latest News on Facebook Share Latest News on Twitter Share Latest News on Linkedin Email Latest News link

    We’re excited to share the latest progress on this important project!


    Work along Lockwood Drive and Navigation Boulevard is moving full steam ahead and right on schedule. We’re proud to report that the project is still on track for completion by Summer 2025.


    Thank you for your patience and support as we continue working hard to enhance your community. Stay tuned—more updates are coming soon!

  • Latest News

    Share Latest News on Facebook Share Latest News on Twitter Share Latest News on Linkedin Email Latest News link

    We’re pleased to share the latest developments:


    Current Progress:
    Currently, two-way traffic is in place on the southbound side of Lockwood Drive and the westbound side of Navigation Boulevard, while construction continues on the northbound side of Lockwood and the eastbound side of Navigation Boulevard.


    Thank you for your continued patience and support. We will keep you updated as we move forward!


  • Latest News

    Share Latest News on Facebook Share Latest News on Twitter Share Latest News on Linkedin Email Latest News link

    We’re excited to share the latest updates on South Lockwood - Subproject 1!


    WHAT

    Traffic Lane Changes from the northbound lanes of Lockwood Drive.

    WHEN

    September 30th, 2024.

    WHY Stormwater System Installation and Paving
    UPDATE The contractor is currently working at the intersection of Navigation and South Lockwood. On Monday, September 30, 2024, traffic will be shifted to begin construction on the northbound lanes of Lockwood Drive. This adjustment will direct traffic into the southbound lanes, while still providing access to two Metro Bus Stop Stations:


    • Lockwood Dr & Crites St
    • Lockwood Dr & Navigation Blvd (SW Corner) (previously located near Suburban St & Lockwood Dr)












    Thank you for your continued support! We’ll keep you informed as the project moves toward completion. To stay connected, subscribe to the project page for updates.

  • Latest News

    Share Latest News on Facebook Share Latest News on Twitter Share Latest News on Linkedin Email Latest News link

    The project is 12% complete and currently on schedule. The contractor is currently working on the southbound side of Lockwood Dr. We are in the final stages of completing the stormwater lines on the southbound side and have also begun the process of laying down the concrete pavement. Our objective is to finish the southbound side of Lockwood Dr by the end of Spring 2024. Currently, the northbound side of Lockwood Dr accommodates two-way traffic, while the southbound side remains closed.


  • Latest News

    Share Latest News on Facebook Share Latest News on Twitter Share Latest News on Linkedin Email Latest News link

    Project is at 100% design completion and construction contract award is anticipated for Fall 2023

Page last updated: 13 Jan 2025, 11:41 AM