South Lockwood Paving and Drainage - Subproject 1

Share South Lockwood Paving and Drainage - Subproject 1 on Facebook Share South Lockwood Paving and Drainage - Subproject 1 on Twitter Share South Lockwood Paving and Drainage - Subproject 1 on Linkedin Email South Lockwood Paving and Drainage - Subproject 1 link

PROJECT NUMBER N-100027-0001-4

LOCATION South Lockwood from North of Crites Street to Suburban Street

COUNCIL DISTRICT H

BUDGET $9,698,748

TYPE Paving and Drainage

START Winter 2024

COMPLETION Summer 2025

DETAILS This project provides for the construction of concrete driveways, medians, sidewalks, bicycle facilities, storm water, water lines, sanitary sewer, street lighting, traffic signals, and necessary underground utilities, and upgrading the necessary intersections, improvement of drainage and upgrade of the existing roadway to Major Thoroughfare & Freeway Plan (MTFP) standards. The contract time for the subproject is 540 calendar days.


MAP



General Project Information

What is the purpose of this project?
This project is designed to improve mobility, drainage, and safety along South Lockwood.


How long is this project going to take to complete?
To be determined. Please subscribe to this project to receive the most up-to-date information.


Have More Questions? Click here for more answers

PROJECT NUMBER N-100027-0001-4

LOCATION South Lockwood from North of Crites Street to Suburban Street

COUNCIL DISTRICT H

BUDGET $9,698,748

TYPE Paving and Drainage

START Winter 2024

COMPLETION Summer 2025

DETAILS This project provides for the construction of concrete driveways, medians, sidewalks, bicycle facilities, storm water, water lines, sanitary sewer, street lighting, traffic signals, and necessary underground utilities, and upgrading the necessary intersections, improvement of drainage and upgrade of the existing roadway to Major Thoroughfare & Freeway Plan (MTFP) standards. The contract time for the subproject is 540 calendar days.


MAP



General Project Information

What is the purpose of this project?
This project is designed to improve mobility, drainage, and safety along South Lockwood.


How long is this project going to take to complete?
To be determined. Please subscribe to this project to receive the most up-to-date information.


Have More Questions? Click here for more answers

Frequently Asked Questions

GENERAL PROJECT INFORMATION

Q What is the purpose of this project?
A The purpose of this project is to improve the paving and drainage along Lockwood Drive.


Q What is going to be replaced/installed in this project?
A Improved storm sewer, water lines, sanitary sewer lines, roadway pavement, bike lanes, sidewalks, and shared-use paths will be installed as part of the project. In addition, the traffic signal at the intersection of Lockwood and Navigation will be replaced.


Q How long is this project going to take to complete?
A The project will be complete in Spring 2025.


SIDEWALKS, TREES & LIGHTING

Q Will there be Street Light Poles installed?
A Yes, there will be 39 new street lights installed as part of the project.


Q What trees are being removed?
A The Tree Protection Plan identifies the trees to be removed, which includes the removal of diseased or dying trees. The City of Houston identifies trees that can be preserved on a case-by-case basis.


Q What are my options if I do not want to construct a sidewalk with my project?

A Because all construction on this project is being completed along City of Houston major thoroughfares, sidewalks are required to be installed based on the City of Houston's standards.



CONSTRUCTION

Q At some point, will my utilities be affected? 
A There will be no interruption to utility service as part of the project, as the contractor will be providing temporary service connections during construction. Please note that the contractor will provide notice 72 hours in advance if utilities are interrupted.


Q Will this project cause traffic/mobility issues (lane closures, increase of trucks in the area, etc.)?
A Because the pavement along Lockwood and Navigation will be replaced, some lanes will be closed as part of the Traffic Control Plan. At least one lane of traffic will be maintained in each direction at all times during construction.


Q Are they going to dig up the front area or just the street?
A This is a complete reconstruction project, and all areas within the public ROW will be under construction.

Q When will my services be transferred to the new line?

A Service transfers will vary and will be based on contractor's schedule of testing and transferring.


CONTACT INFORMATION

NON-EMERGENCY NEEDS
Dial 311 - Mention to the operator the following 3 things along with your issue:
- Project number: N-100027-0001-4
- South Lockwood Paving and Drainage - Subproject 1
- Refer the questions/comments to Capital Projects

EMERGENCY NEEDS
Contact Contractor or the 24-hour contact provided by the contractor.

Contractor
Total Contracting Limited

Maher Matta -Project Manager 713.501.3771


Houston Public Works
Jessika Carey – Project Manager 832.395.2385

Jesus Serrano-Marrero - Senior Inspector 281.627.0550


HELPFUL LINKS

PROJECT SPECIFIC CONCERNS
Buildforward@houstontx.gov

GENERAL CONCERNS
3-1-1 or 713.837.0311
www.houston311.org