Park Ten Wastewater Treatment Plant
Project Overview
Project Number: R-000536-0019
Estimated Budget: $39,980,681
Start: Spring 2024
Completion: Summer 2026
Project Impact Area
Community Feedback
Have questions or feedback about this project? Email us at engage@houstontx.gov or call 311.
Project Overview
Project Number: R-000536-0019
Estimated Budget: $39,980,681
Start: Spring 2024
Completion: Summer 2026
Project Impact Area
Community Feedback
Have questions or feedback about this project? Email us at engage@houstontx.gov or call 311.
-
Latest News
Share Latest News on Facebook Share Latest News on X (formerly Twitter) Share Latest News on Linkedin Email Latest News linkPark Row:
Crews are making steady progress with concrete, curb, and median restoration, along with finishing manhole installations and shaft backfill/removal. These activities are essential to advancing this phase of the project and will continue in the coming weeks.North Eldridge (South of I-10):
Construction remains active near I-10 with continued work on multiple shafts. Preparations are underway for upcoming tunnel operations, expected to begin soon. While there is currently no active construction at the Memorial and Eldridge intersection, hand tunneling in that area is scheduled to start shortly.Lift Station Improvements:
All electrical work has been completed, and pavement restoration is in progress to return the area to its final condition.Park Row:
Crews are making steady progress with concrete, curb, and median restoration, along with finishing manhole installations and shaft backfill/removal. These activities are essential to advancing this phase of the project and will continue in the coming weeks.North Eldridge (South of I-10):
Construction remains active near I-10 with continued work on multiple shafts. Preparations are underway for upcoming tunnel operations, expected to begin soon. While there is currently no active construction at the Memorial and Eldridge intersection, hand tunneling in that area is scheduled to start shortly.Lift Station Improvements:
All electrical work has been completed, and pavement restoration is in progress to return the area to its final condition. -
Latest News
Share Latest News on Facebook Share Latest News on X (formerly Twitter) Share Latest News on Linkedin Email Latest News linkPark Row Area:
Pavement restoration has been completed around Shaft 5 to Shaft 7 at Stations 20+64 and 29+78.
The hand tunnel between Shaft 12 at Station 51+44 and the existing shaft across Park Row is ongoing.
Work on Shaft 6 at Station 25+03 has been completed.
Installation at Shaft 1 at Station 2+05 near the wastewater treatment plant is currently underway.
The only remaining shaft installation along Park Row will be Shaft 12 at Station 51+44.
North Eldridge Area:
The shaft at the intersection of Memorial Drive and North Eldridge Parkway has been completed, and the traffic control measures remain unchanged.
Shaft 12 has been completed. The tunneling subcontractor is mobilizing for tunnel preparation between Shaft 12 and Shaft 18.
Park Row Area:
Pavement restoration has been completed around Shaft 5 to Shaft 7 at Stations 20+64 and 29+78.
The hand tunnel between Shaft 12 at Station 51+44 and the existing shaft across Park Row is ongoing.
Work on Shaft 6 at Station 25+03 has been completed.
Installation at Shaft 1 at Station 2+05 near the wastewater treatment plant is currently underway.
The only remaining shaft installation along Park Row will be Shaft 12 at Station 51+44.
North Eldridge Area:
The shaft at the intersection of Memorial Drive and North Eldridge Parkway has been completed, and the traffic control measures remain unchanged.
Shaft 12 has been completed. The tunneling subcontractor is mobilizing for tunnel preparation between Shaft 12 and Shaft 18.
Follow Project
Project Timeline
-
Design
Park Ten Wastewater Treatment Plant has finished this stage -
Construction
Park Ten Wastewater Treatment Plant is currently at this stage -
Complete
this is an upcoming stage for Park Ten Wastewater Treatment Plant