Park Ten Wastewater Treatment Plant
PROJECT NUMBER R-000536-0019
LOCATION Refer to map
BUDGET $39,980,681
TYPE Wastewater
START Spring 2024
COMPLETION Summer 2025
DETAILS The project provides for the installation of a gravity wastewater lines and force main. The scope also includes the abandonment of the Park Ten WWTP and improvements to the North Eldridge Lift Station and Park Row Regional Lift Station.
MAP
General Project Information
What is the purpose of this project? 1) The purpose of this project is to decommission Park Ten Wastewater Treatment Plant (WWTP) and instead convey flow to a newly installed wastewater line east of Highway 6. 2) Convey flow from an existing stub-out near the intersection of Park Row & North Eldridge to an existing manhole at the intersection of Memorial & Eldridge. |
Have More Questions? Click here for more answers.
PROJECT NUMBER R-000536-0019
LOCATION Refer to map
BUDGET $39,980,681
TYPE Wastewater
START Spring 2024
COMPLETION Summer 2025
DETAILS The project provides for the installation of a gravity wastewater lines and force main. The scope also includes the abandonment of the Park Ten WWTP and improvements to the North Eldridge Lift Station and Park Row Regional Lift Station.
MAP
General Project Information
What is the purpose of this project? 1) The purpose of this project is to decommission Park Ten Wastewater Treatment Plant (WWTP) and instead convey flow to a newly installed wastewater line east of Highway 6. 2) Convey flow from an existing stub-out near the intersection of Park Row & North Eldridge to an existing manhole at the intersection of Memorial & Eldridge. |
Have More Questions? Click here for more answers.
-
Latest News
Share Latest News on Facebook Share Latest News on Twitter Share Latest News on Linkedin Email Latest News linkWHAT
The right-turn lane traveling Southbound on Eldridge will open at the intersection of Eldridge and Memorial temporarily until November 2024.
WHEN
This week
WHY
The traffic control mitigation plan has been updated
CONTACT
311 or 713-837-0311 reference Project No. R-000536-0019
Reytec- Scott Walker- Superintendent 254.749.4530
-
Latest News
Share Latest News on Facebook Share Latest News on Twitter Share Latest News on Linkedin Email Latest News linkExciting Project Updates!
- The contractor successfully installed the approved Traffic Control Plan.
- Low concrete barriers will be installed to ensure safety in the area.
- Work along N. Eldridge will continue until Spring 2025.
- To ease traffic impacts, traffic signs, flagmen/uniformed officers, and adjustments to traffic signal timings may be implemented.
- The site will be fully restored as soon as the work is completed.
Stay tuned for more updates as we move forward with this exciting project!
-
Latest News
Share Latest News on Facebook Share Latest News on Twitter Share Latest News on Linkedin Email Latest News linkA contractor has been selected and will start assessing the project area prior to mobilization. Look forward to seeing the following:
- Moving equipment
- Moving pipe and other materials to the site
- Dewatering shafts
- Performing critical locates for the water line relocation along Eldridge
- Fence maintenance to mitigate safety concerns
-
Latest News
Share Latest News on Facebook Share Latest News on Twitter Share Latest News on Linkedin Email Latest News linkGreat news...we are on track to resume construction in June 2024! We will provide an updated phasing map and other relevant project materials once available. Houston Public Works will host a virtual community meeting prior to construction. Stay tuned!
-
Latest News
Share Latest News on Facebook Share Latest News on Twitter Share Latest News on Linkedin Email Latest News linkProject is approximately 60% complete. Construction is currently temporarily suspended and will resume work in June 2024.
-
Latest News
Share Latest News on Facebook Share Latest News on Twitter Share Latest News on Linkedin Email Latest News linkConstruction is set to resume in Spring of 2024, with completion expected in Spring 2025. We will provide an update on any changes to the construction schedule.
-
Traffic Update
Share Traffic Update on Facebook Share Traffic Update on Twitter Share Traffic Update on Linkedin Email Traffic Update linkTraffic adjustments have been made during rush hours to ease congestion. Safety measures will keep existing traffic control in place around the construction area.
-
Latest News
Share Latest News on Facebook Share Latest News on Twitter Share Latest News on Linkedin Email Latest News linkWe would like to provide you with a comprehensive update on the Park Ten project, outlining the recent developments and the anticipated timeline moving forward.
- Original Timeline and Setback: The initial target completion timeline for the Park Ten project was set for Fall 2023. Unfortunately, in September 2023, the project encountered an unforeseen challenge as the contracted construction company declared bankruptcy. Consequently, construction activities were immediately halted.
- City's Response and Contractor Replacement Process: In response to this setback, the City of Houston took decisive action by terminating the contract. Subsequently, the City of Houston engaged the Surety company to identify a suitable replacement contractor. We are pleased to inform you that the Surety company has diligently evaluated bids from potential contractors and is currently in the final stages of selecting the most qualified candidate. The commencement of work is anticipated within the next few months, contingent upon the execution of the new contract.
- Construction Evaluation and Prioritization: Upon the appointment of the new contractor, there will be a thorough assessment of high traffic areas to strategically reduce the impact on the surrounding community before resuming construction. This meticulous evaluation aims to streamline the construction process and minimize disruptions to the area.
- Revised Project Completion Timeline: As a result of these developments, we now project the completion of the Park Ten project to be in Spring 2025. We understand the significance of adhering to timelines and are committed to delivering a successful project while keeping the community's best interests in mind.
- Temporary Measures for Public Safety: During this interim period, lane closures and traffic control measures will remain in place to mitigate potential risks to public safety associated with open shafts. We appreciate the community's cooperation and understanding as we prioritize safety throughout the project's duration.
We are dedicated to maintaining transparency and open communication throughout this process. Should you have any further inquiries or require additional information, please visit EngageHouston.org and register to the project page for updates and to voice your concerns.
Thank you for your continued support and understanding.
-
Latest News
Share Latest News on Facebook Share Latest News on Twitter Share Latest News on Linkedin Email Latest News linkThe original contractor for this project filed for bankruptcy in September 2023, and was subsequently unable to continue the contract work. Therefore, the City terminated their contract and requested to find a replacement contractor to finish the remaining work. We are currently in the process of finding a new contractor. Once selected, the new contractor will resume the work. In the interim, to maintain public safety at the site, the streets need to remain blocked due to testing and open shafts. We will provide an update on the timeline as information becomes available. Please subscribe to this project page to receive updates as they become available.
The streets that are currently restricted (traffic control in place) either have open tunnel shafts or other pending testing that needs to be completed before the traffic control can be removed from these areas. The traffic control on these streets needs to stay in place for public safety. Once the new contractor resumes work, they will prioritize these areas to open the partially blocked streets.
-
Latest News
Share Latest News on Facebook Share Latest News on Twitter Share Latest News on Linkedin Email Latest News linkWe appreciate your interest and concern regarding the project's progress. Here's an update on the current status and timelines:
- Scheduled Completion and Timelines:
The scheduled completion date for the project is has changed. We are diligently working to evaluate options and find replacement contractors. Rest assured, we will provide updates on the project's progress and timelines as soon as they become available.
- Opening of IH-10 Northbound and Southbound:
All work related to the project has been placed on hold, including any changes to traffic control measures. Therefore, there will be no alterations to the existing traffic control until work resumes. We will keep you informed of any changes in this regard.
- Completion of South Side of IH-10:
Completing the project on the south side of IH-10 by the end of December 2023 is not achievable due to the project being on hold. As with the other aspects of the project, we will update you on the revised timeline once construction activities resume.