Park Ten Wastewater Treatment Plant (WWTP) Abandonment and Flow Diversion to Turkey Creek WWTP

Share Park Ten Wastewater Treatment Plant (WWTP) Abandonment and Flow Diversion to Turkey Creek WWTP on Facebook Share Park Ten Wastewater Treatment Plant (WWTP) Abandonment and Flow Diversion to Turkey Creek WWTP on Twitter Share Park Ten Wastewater Treatment Plant (WWTP) Abandonment and Flow Diversion to Turkey Creek WWTP on Linkedin Email Park Ten Wastewater Treatment Plant (WWTP) Abandonment and Flow Diversion to Turkey Creek WWTP link

PROJECT NUMBER R-000536-0019

LOCATION Refer to Project Map

COUNCIL DISTRICT A & G

BUDGET $39,980,681

TYPE Wastewater

START Spring 2024

COMPLETION Spring 2025

DETAILS The project provides for the installation of a gravity sanitary sewer and sanitary force main. The scope also includes the abandonment of the Park Ten WWTP and improvements to the North Eldridge Lift Station and Park Row Regional Lift Station.


MAP



General Project Information

What is the purpose of this project?
1) The purpose of this project is to decommission Park Ten Wastewater Treatment Plant (WWTP) and instead convey flow to a newly installed sanitary system east of Highway 6.
2) Convey flow from an existing stub-out near the intersection of Park Row & North Eldridge to an existing manhole at the intersection of Memorial & Eldridge.

How long is this project going to take to complete?
The project schedule was placed on hold, please see updates below for further information.

The City will post a new schedule once available.



PROJECT NUMBER R-000536-0019

LOCATION Refer to Project Map

COUNCIL DISTRICT A & G

BUDGET $39,980,681

TYPE Wastewater

START Spring 2024

COMPLETION Spring 2025

DETAILS The project provides for the installation of a gravity sanitary sewer and sanitary force main. The scope also includes the abandonment of the Park Ten WWTP and improvements to the North Eldridge Lift Station and Park Row Regional Lift Station.


MAP



General Project Information

What is the purpose of this project?
1) The purpose of this project is to decommission Park Ten Wastewater Treatment Plant (WWTP) and instead convey flow to a newly installed sanitary system east of Highway 6.
2) Convey flow from an existing stub-out near the intersection of Park Row & North Eldridge to an existing manhole at the intersection of Memorial & Eldridge.

How long is this project going to take to complete?
The project schedule was placed on hold, please see updates below for further information.

The City will post a new schedule once available.



  • Latest News

    Share Latest News on Facebook Share Latest News on Twitter Share Latest News on Linkedin Email Latest News link

    Great news...we are on track to resume construction in June 2024! We will provide an updated phasing map and other relevant project materials once available. Houston Public Works will host a virtual community meeting prior to construction. Stay tuned!

  • Latest News

    Share Latest News on Facebook Share Latest News on Twitter Share Latest News on Linkedin Email Latest News link

    Project is approximately 60% complete. Construction is currently temporarily suspended and will resume work in June 2024.

  • Latest News

    Share Latest News on Facebook Share Latest News on Twitter Share Latest News on Linkedin Email Latest News link

    Construction is set to resume in Spring of 2024, with completion expected in Spring 2025. We will provide an update on any changes to the construction schedule.

  • Traffic Update

    Share Traffic Update on Facebook Share Traffic Update on Twitter Share Traffic Update on Linkedin Email Traffic Update link

    Traffic adjustments have been made during rush hours to ease congestion. Safety measures will keep existing traffic control in place around the construction area.

  • Latest News

    Share Latest News on Facebook Share Latest News on Twitter Share Latest News on Linkedin Email Latest News link

    We would like to provide you with a comprehensive update on the Park Ten project, outlining the recent developments and the anticipated timeline moving forward.

    • Original Timeline and Setback: The initial target completion timeline for the Park Ten project was set for Fall 2023. Unfortunately, in September 2023, the project encountered an unforeseen challenge as the contracted construction company declared bankruptcy. Consequently, construction activities were immediately halted.
    • City's Response and Contractor Replacement Process: In response to this setback, the City of Houston took decisive action by terminating the contract. Subsequently, the City of Houston engaged the Surety company to identify a suitable replacement contractor. We are pleased to inform you that the Surety company has diligently evaluated bids from potential contractors and is currently in the final stages of selecting the most qualified candidate. The commencement of work is anticipated within the next few months, contingent upon the execution of the new contract.
    • Construction Evaluation and Prioritization: Upon the appointment of the new contractor, there will be a thorough assessment of high traffic areas to strategically reduce the impact on the surrounding community before resuming construction. This meticulous evaluation aims to streamline the construction process and minimize disruptions to the area.
    • Revised Project Completion Timeline: As a result of these developments, we now project the completion of the Park Ten project to be in Spring 2025. We understand the significance of adhering to timelines and are committed to delivering a successful project while keeping the community's best interests in mind.
    • Temporary Measures for Public Safety: During this interim period, lane closures and traffic control measures will remain in place to mitigate potential risks to public safety associated with open shafts. We appreciate the community's cooperation and understanding as we prioritize safety throughout the project's duration.


    We are dedicated to maintaining transparency and open communication throughout this process. Should you have any further inquiries or require additional information, please visit EngageHouston.org and register to the project page for updates and to voice your concerns.

    Thank you for your continued support and understanding.

  • Latest News

    Share Latest News on Facebook Share Latest News on Twitter Share Latest News on Linkedin Email Latest News link

    The original contractor for this project filed for bankruptcy in September 2023, and was subsequently unable to continue the contract work. Therefore, the City terminated their contract and requested to find a replacement contractor to finish the remaining work. We are currently in the process of finding a new contractor. Once selected, the new contractor will resume the work. In the interim, to maintain public safety at the site, the streets need to remain blocked due to testing and open shafts. We will provide an update on the timeline as information becomes available. Please subscribe to this project page to receive updates as they become available.

    The streets that are currently restricted (traffic control in place) either have open tunnel shafts or other pending testing that needs to be completed before the traffic control can be removed from these areas. The traffic control on these streets needs to stay in place for public safety. Once the new contractor resumes work, they will prioritize these areas to open the partially blocked streets.

  • Latest News

    Share Latest News on Facebook Share Latest News on Twitter Share Latest News on Linkedin Email Latest News link

    We appreciate your interest and concern regarding the project's progress. Here's an update on the current status and timelines:

    • Scheduled Completion and Timelines:

    The scheduled completion date for the project is has changed. We are diligently working to evaluate options and find replacement contractors. Rest assured, we will provide updates on the project's progress and timelines as soon as they become available.

    • Opening of IH-10 Northbound and Southbound:

    All work related to the project has been placed on hold, including any changes to traffic control measures. Therefore, there will be no alterations to the existing traffic control until work resumes. We will keep you informed of any changes in this regard.

    • Completion of South Side of IH-10:

    Completing the project on the south side of IH-10 by the end of December 2023 is not achievable due to the project being on hold. As with the other aspects of the project, we will update you on the revised timeline once construction activities resume.

  • Latest News

    Share Latest News on Facebook Share Latest News on Twitter Share Latest News on Linkedin Email Latest News link

    Project is approximately 40% completed in place with over 5,000 linear feet of wastewater pipe installed.