Park Ten Wastewater Treatment Plant (WWTP) Abandonment and Flow Diversion to Turkey Creek WWTP

Share on Facebook Share on Twitter Share on Linkedin Email this link

PROJECT NUMBER R-000536-0019

LOCATION Refer to Project Map

COUNCIL DISTRICT A & G

BUDGET $39,980,681

TYPE Wastewater

START Spring 2022

COMPLETION To Be Determined

DETAILS The project provides for the installation of a gravity sanitary sewer and sanitary force main. The scope also includes the abandonment of the Park Ten WWTP and improvements to the North Eldridge Lift Station and Park Row Regional Lift Station.


MAP



General Project Information

What is the purpose of this project?
1) The purpose of this project is to decommission Park Ten Wastewater Treatment Plant (WWTP) and instead convey flow to a newly installed sanitary system east of Highway 6.
2) Convey flow from an existing stub-out near the intersection of Park Row & North Eldridge to an existing manhole at the intersection of Memorial & Eldridge.

How long is this project going to take to complete?
18 months (540 calendar days). Work is scheduled to begin in Spring 2022 and is anticipated to be completed in Fall 2023. The project schedule depends upon weather conditions.


Have More Questions? Click here for more answers


PROJECT NUMBER R-000536-0019

LOCATION Refer to Project Map

COUNCIL DISTRICT A & G

BUDGET $39,980,681

TYPE Wastewater

START Spring 2022

COMPLETION To Be Determined

DETAILS The project provides for the installation of a gravity sanitary sewer and sanitary force main. The scope also includes the abandonment of the Park Ten WWTP and improvements to the North Eldridge Lift Station and Park Row Regional Lift Station.


MAP



General Project Information

What is the purpose of this project?
1) The purpose of this project is to decommission Park Ten Wastewater Treatment Plant (WWTP) and instead convey flow to a newly installed sanitary system east of Highway 6.
2) Convey flow from an existing stub-out near the intersection of Park Row & North Eldridge to an existing manhole at the intersection of Memorial & Eldridge.

How long is this project going to take to complete?
18 months (540 calendar days). Work is scheduled to begin in Spring 2022 and is anticipated to be completed in Fall 2023. The project schedule depends upon weather conditions.


Have More Questions? Click here for more answers


  • April 2023 Update

    Share on Facebook Share on Twitter Share on Linkedin Email this link

    Project is approximately 40% completed in place with over 5,000 linear feet of wastewater pipe installed.