Park Ten Wastewater Treatment Plant

Share Park Ten Wastewater Treatment Plant on Facebook Share Park Ten Wastewater Treatment Plant on Twitter Share Park Ten Wastewater Treatment Plant on Linkedin Email Park Ten Wastewater Treatment Plant link

Project Overview

Council District: A & G

Project Number: R-000536-0019

Estimated Budget: $39,980,681

Start: Spring 2024

Completion: Fall 2025



Project Impact Area


Community Feedback

Have questions or feedback about this project? Email us at engage@houstontx.gov or call 311.

Project Overview

Council District: A & G

Project Number: R-000536-0019

Estimated Budget: $39,980,681

Start: Spring 2024

Completion: Fall 2025



Project Impact Area


Community Feedback

Have questions or feedback about this project? Email us at engage@houstontx.gov or call 311.

  • Latest News

    Share Latest News on Facebook Share Latest News on Twitter Share Latest News on Linkedin Email Latest News link

    TRAFFIC NOTIFICATION - Park Ten Project

    What:

    The dedicated right-turn lane will be closed to help improve traffic flow and safety.

    Where:

    The Intersection of Memorial Drive and N. Eldridge Parkway

    When:

    Starting on August 4th, it will remain in effect until construction activities at N. Eldridge are completed.

    Why:

    This closure is part of an ongoing effort to improve traffic flow and safety.

    Additional signage will be installed to enhance traffic control throughout the construction period.

    Who to Contact:

    Please call 311 or email us at engage@houstontx.gov


    • Traffic control measures, including signage, cones, and flaggers, will be in place to guide vehicles safely through the construction zone.
    • Proceed with caution and reduce speed when driving near work areas.
    • Yield to workers and construction vehicles.
    • Stay alert for lane shifts and changing traffic patterns.
    • Follow all posted signs and signals to ensure your safety and the safety of our crews.


  • Latest News

    Share Latest News on Facebook Share Latest News on Twitter Share Latest News on Linkedin Email Latest News link

    Our wastewater project has experienced some delays due to unexpected obstacles encountered during tunneling, along with weather-related challenges. As with any major construction effort, unforeseen issues can arise—but we’re working hard to keep things moving forward and the new completion date is now Fall 2025.

    We truly appreciate your patience and understanding as we navigate these hurdles and remain committed to completing the project as efficiently and safely as possible.


  • Latest News

    Share Latest News on Facebook Share Latest News on Twitter Share Latest News on Linkedin Email Latest News link

    Park Row

    Crews continue to make steady progress on concrete, curb, and median restoration, along with completing manhole installations and removing construction shafts. This work is essential to advancing the project and will continue through the current phase.


    North Eldridge (South of I-10)

    Construction activity remains ongoing near I-10, with work progressing on multiple underground shafts. Preparations are underway for tunnel operations, and hand tunneling is expected to begin soon in the area.


    Lift Station Improvements

    Electrical work has been completed, and pavement restoration is in progress as we move toward wrapping up this portion of the project.

    We appreciate your continued support as this important work advances. Stay tuned for future updates.


  • Latest News

    Share Latest News on Facebook Share Latest News on Twitter Share Latest News on Linkedin Email Latest News link

    Park Row:
    Crews are making steady progress with concrete, curb, and median restoration, along with finishing manhole installations and shaft backfill/removal. These activities are essential to advancing this phase of the project and will continue in the coming weeks.

    North Eldridge (South of I-10):
    Construction remains active near I-10 with continued work on multiple shafts. Preparations are underway for upcoming tunnel operations, expected to begin soon. While there is currently no active construction at the Memorial and Eldridge intersection, hand tunneling in that area is scheduled to start shortly.

    Lift Station Improvements:
    All electrical work has been completed, and pavement restoration is in progress to return the area to its final condition.

  • Latest News

    Share Latest News on Facebook Share Latest News on Twitter Share Latest News on Linkedin Email Latest News link

    Park Row Area:

    Pavement restoration has been completed around Shaft 5 to Shaft 7 at Stations 20+64 and 29+78.

    The hand tunnel between Shaft 12 at Station 51+44 and the existing shaft across Park Row is ongoing.

    Work on Shaft 6 at Station 25+03 has been completed.

    Installation at Shaft 1 at Station 2+05 near the wastewater treatment plant is currently underway.

    The only remaining shaft installation along Park Row will be Shaft 12 at Station 51+44.

    North Eldridge Area:

    The shaft at the intersection of Memorial Drive and North Eldridge Parkway has been completed, and the traffic control measures remain unchanged.

    Shaft 12 has been completed. The tunneling subcontractor is mobilizing for tunnel preparation between Shaft 12 and Shaft 18.

Page last updated: 12 Aug 2025, 09:57 AM