Park Ten Wastewater Treatment Plant
PROJECT NUMBER R-000536-0019
LOCATION Refer to map
BUDGET $39,980,681
TYPE Wastewater
START Spring 2024
COMPLETION Summer 2025
DETAILS The project provides for the installation of a gravity wastewater lines and force main. The scope also includes the abandonment of the Park Ten WWTP and improvements to the North Eldridge Lift Station and Park Row Regional Lift Station.
MAP
General Project Information
What is the purpose of this project? 1) The purpose of this project is to decommission Park Ten Wastewater Treatment Plant (WWTP) and instead convey flow to a newly installed wastewater line east of Highway 6. 2) Convey flow from an existing stub-out near the intersection of Park Row & North Eldridge to an existing manhole at the intersection of Memorial & Eldridge. |
Have More Questions? Click here for more answers.
PROJECT NUMBER R-000536-0019
LOCATION Refer to map
BUDGET $39,980,681
TYPE Wastewater
START Spring 2024
COMPLETION Summer 2025
DETAILS The project provides for the installation of a gravity wastewater lines and force main. The scope also includes the abandonment of the Park Ten WWTP and improvements to the North Eldridge Lift Station and Park Row Regional Lift Station.
MAP
General Project Information
What is the purpose of this project? 1) The purpose of this project is to decommission Park Ten Wastewater Treatment Plant (WWTP) and instead convey flow to a newly installed wastewater line east of Highway 6. 2) Convey flow from an existing stub-out near the intersection of Park Row & North Eldridge to an existing manhole at the intersection of Memorial & Eldridge. |
Have More Questions? Click here for more answers.
-
Latest News
Share Latest News on Facebook Share Latest News on Twitter Share Latest News on Linkedin Email Latest News linkWHAT
Right Turn Lane Closure on North Eldridge Parkway (Southbound) at the intersection of Memorial Drive.
WHEN
April 25, 2025 - May 26, 2025
WHY
Wastewater infrastructure work.
UPDATE The right lane will be closed to accommodate the wastewater project.
-
Latest News
Share Latest News on Facebook Share Latest News on Twitter Share Latest News on Linkedin Email Latest News linkWe are committed to delivering a project done right the first time, and part of that commitment involves redoing pressure testing in this area. While this process may take some time, and you may not see much activity on the surface, rest assured that important work is happening underground.
Your patience and understanding mean the world to us as we work toward ensuring a reliable and long-lasting solution. If you have any questions or need updates, please don’t hesitate to reach out to us at engage@houstontx.gov.
Thank you for your cooperation as we work diligently to bring this project to completion!
-
Latest News
Share Latest News on Facebook Share Latest News on Twitter Share Latest News on Linkedin Email Latest News linkWe’re thrilled to share the latest updates on this important project, along with a newly updated document highlighting the shaft locations and station details!
Park Row Area
Tunneling completed:
- Shaft 11 to Shaft 10 at stations 48+12 and 43+32.
Ongoing progress:
- Installation of Shaft 4 at station 15+62.
- Hand tunneling from Shaft 1 to the existing tie-in at station 2+05.
- The contractor is relocating to Shaft 5 to begin tunneling operations at station 20+64.
North Eldridge Area (South of I-10)
- Fall 2024 – Winter 2025: Shaft installations scheduled at Stations 12+78 and 18+04 along North Eldridge Parkway.
- Winter 2025 – Spring 2025: Shaft installation will begin at Station 4+87, followed by tunneling to connect Stations 12+78 and 4+87.
- Spring 2025 – Summer 2025: Tunneling operations will take place at Station 25+71.
Lift Station Improvements
Electrical installations are actively underway and progressing smoothly.
Thank you for your continued patience and support as we push forward with this vital work. Stay tuned—more updates are coming soon as we bring this project closer to completion!
-
Latest News
Share Latest News on Facebook Share Latest News on Twitter Share Latest News on Linkedin Email Latest News linkWe’re excited to share the latest developments:
Park Row:
- We have successfully installed 450 linear feet of pipe.
- Tunneling operations from Highway 6 to Park Ten will continue around the clock until November 1, 2024.
- We are preparing to remove the current traffic control devices once the lines have been tested and approved.
North Eldridge (South of I-10):
- The contractor is currently maintaining the traffic control plan. Signage is being reviewed to ensure clear traffic flow, and adjustments will be made as necessary.
Lift Station:
- We are currently performing electrical work.
Thank you for your continued support and patience as we progress with these developments!
-
Latest News
Share Latest News on Facebook Share Latest News on Twitter Share Latest News on Linkedin Email Latest News linkWe would like to share the latest progress of the Park Ten wastewater Project (Revised)
Park Row:
- Testing is ongoing from Memorial Brook to North Eldridge. Once testing is approved, traffic control will be removed and the roadway will be open.
-
The City of Houston has approved the 24 Hour work schedule for the tunneling operations from Highway 6 to Park Ten. This schedule will begin October 1, 2024 through October 21, 2024 including Saturdays and Sundays. The Contractor work schedule is required to adhere to the City of Houston Code of Ordinances, Section 30-5 Maximum Permissible Sound Levels. This work plan will allow the Contractor to align with the planned schedule.
North Eldridge (South of I-10)
The contractor is currently maintaining the traffic control plan. The signage is being reviewed to ensure clear traffic flow, and adjustments will be made as necessary.
Lift Station
We’re making strides with ongoing electrical work, and all piping and pumps have been installed. Testing is set to take place in December.
Thank you for your continued support and patience as we move forward with the developments of this project!
-
Latest News
Share Latest News on Facebook Share Latest News on Twitter Share Latest News on Linkedin Email Latest News linkWe are currently developing a traffic control plan for the area near North Eldridge Parkway and Memorial Drive. While intermittent work may be visible at the surface, please note that most activities will occur in phases, minimizing disruptions whenever possible. Stay tuned for further updates as the project progresses.
We’d like to share an update on the progress of the Park Ten Wastewater project as of this month:
Park Row Shaft/Tunneling:
- We’ve successfully installed 100 linear feet of pipe!
- Tunneling operations is in progress and on schedule.
North Eldridge/Memorial Lift Station:
- The walls are complete, and we’re gearing up for the installation of the top slab.
- We’ve passed the electrical code inspection, and work is continuing smoothly.
Thank you for your ongoing support and patience as we make progress on this important project!
-
Latest News
Share Latest News on Facebook Share Latest News on Twitter Share Latest News on Linkedin Email Latest News linkHello from the Engage Houston Team,
We have recently updated the Park Ten Project page with the latest developments and details:
1. Park Row Tunneling: Soon, we will begin tunneling work in Park Row. While this work will be happening below the surface and might not be visible, please rest assured that significant progress will be made once it starts.
2. Eldridge and Memorial: We are collaborating with our engineers to minimize traffic disruptions when construction begins on Eldridge near Memorial. We are committed to reducing the impact on your daily commute.
3. N. Eldridge: Construction is also taking place at the N. Eldridge Lift Station next to the library.
We understand that some citizens might feel concerned about the pace or visibility of the work. Please know that we are working diligently to ensure all projects are completed as efficiently as possible. This project is mostly tunneling work; therefore the workers may not be visible at all times.
Thank you for your patience and understanding. If you have any further questions or concerns, feel free to reach out. Your involvement and support means a lot to us, and we want to make sure you have the latest information readily available.
Thank you for staying connected with us!
Best regards,
The Engage Houston Team
-
Latest News
Share Latest News on Facebook Share Latest News on Twitter Share Latest News on Linkedin Email Latest News linkGreat news! The southbound and northbound lanes are now open. Please note that one of the southbound driveways is closed as we work on the paving markings while continuing to implement the traffic control plan.
-
Latest News
Share Latest News on Facebook Share Latest News on Twitter Share Latest News on Linkedin Email Latest News linkWHAT
The right-turn lane traveling Southbound on Eldridge will open at the intersection of Eldridge and Memorial temporarily until November 2024.
WHEN
This week
WHY
The traffic control mitigation plan has been updated
CONTACT
311 or 713-837-0311 reference Project No. R-000536-0019
Reytec- Scott Walker- Superintendent 254.749.4530
-
Latest News
Share Latest News on Facebook Share Latest News on Twitter Share Latest News on Linkedin Email Latest News linkExciting Project Updates!
- The contractor successfully installed the approved Traffic Control Plan.
- Low concrete barriers will be installed to ensure safety in the area.
- Work along N. Eldridge will continue.
- To ease traffic impacts, traffic signs, flagmen/uniformed officers, and adjustments to traffic signal timings may be implemented.
- The site will be fully restored as soon as the work is completed.
Stay tuned for more updates as we move forward with this exciting project!