Hempstead No. 1 Area Lift Stations

Share Hempstead No. 1 Area Lift Stations on Facebook Share Hempstead No. 1 Area Lift Stations on Twitter Share Hempstead No. 1 Area Lift Stations on Linkedin Email Hempstead No. 1 Area Lift Stations link

PROJECT NUMBER R-000035-0025

LOCATION Refer to map

COUNCIL DISTRICT A

BUDGET $9,285,189

TYPE Wastewater

START Spring 2024

COMPLETION Winter 2026

DETAILS The project will consist of installing approximately 5,500 linear feet of force main wastewater line.


MAP


General Project Information


What is the purpose of this project?
This project is part of the City's Capital Improvement Plan (CIP) for wastewater facilities.




Have More Questions? Click here for more answers.

PROJECT NUMBER R-000035-0025

LOCATION Refer to map

COUNCIL DISTRICT A

BUDGET $9,285,189

TYPE Wastewater

START Spring 2024

COMPLETION Winter 2026

DETAILS The project will consist of installing approximately 5,500 linear feet of force main wastewater line.


MAP


General Project Information


What is the purpose of this project?
This project is part of the City's Capital Improvement Plan (CIP) for wastewater facilities.




Have More Questions? Click here for more answers.

Frequently Asked Questions

GENERAL PROJECT INFORMATION

Q: What is the purpose of this project?
A: The benefits of the project include upgraded sanitary sewers and force mains.


Q: What is going to be replaced/installed in this project?
A: Work of tThe project primarily consists of installation of approximately 5500-linear feet of force main.


Q: How long is this project going to take to complete?
A: (597 calendar days). Work is scheduled to begin in Spring 2024 and anticipated to be completed in Winter 2026. The project schedule will depend on weather conditions.


SIDEWALKS, TREES & LIGHTING

Q: Will there be Street Light Poles installed?
A: No, street light poles will not be installed.


Q: What trees are being removed?
A: No.


CONSTRUCTION

Q: At some point, will my utilities be affected?
A: No utilities should be impacted, but unforeseen issues may arise due to the nature of underground work.




Q: Will this project cause traffic/mobility issues (lane closures, increase of trucks in the area, etc.)?
A: Yes. Partial lane closures along the construction path as provided in the exhibits.




Q: Are they going to dig up the front area or just the street?
A: Roadsides and certain driveways along the construction route will be dug.


Q: When will my services be transferred to the new line? 

A: Upon substantial completion of the work.

CONTACT INFORMATION

NON-EMERGENCY NEEDS
Dial 311 - Mention to the operator the following 3 things along with your issue:
- Project number: R-000035-0025
- Force Main Renewal/Replacement of Hempstead No.1 (WCID #28) Lift Stations
- Refer the questions/comments to Capital Projects

EMERGENCY NEEDS
Contact Contractor or the 24-hour contact provided by the contractor.

Contractor
Resicom Inc.
Michelle Turner – 713.666.0775                                                                                                                                                                               

Houston Public Works
Mack Nosrat – Inspector 832.395.5852
Jack Cortez – Project Manager 713.299.7072


HELPFUL LINKS

PROJECT SPECIFIC CONCERNS
Engage@houstontx.gov

GENERAL CONCERNS
3-1-1 or 713.837.0311
www.houston311.org