Force Main Renewal - Golf Course

Share Force Main Renewal - Golf Course on Facebook Share Force Main Renewal - Golf Course on Twitter Share Force Main Renewal - Golf Course on Linkedin Email Force Main Renewal - Golf Course link

PROJECT NUMBER R-000035-013A

LOCATION Along Pine Bend Dr. to Laurel Trail Dr. and Lake Kingwood Trail just south of Kingwood Drive

COUNCIL DISTRICT E

BUDGET $1,862,260

TYPE Wastewater

START Summer 2020

COMPLETION Fall 2022

DETAILS The project will replace an existing force main to provide reliability and maintenance capabilities for the golf course lift station.


MAP

project map



What is the purpose of this project?
This project will replace an existing force main to provide reliability and maintenance capabilities to the golf course lift station.
How long is the project going to take to complete?
8 months (242 calendar days). Work is scheduled to begin Summer and anticipated to be completed in Fall. The project schedule depends upon weather conditions.


Have More Questions? Click here for more answers.


PROJECT NUMBER R-000035-013A

LOCATION Along Pine Bend Dr. to Laurel Trail Dr. and Lake Kingwood Trail just south of Kingwood Drive

COUNCIL DISTRICT E

BUDGET $1,862,260

TYPE Wastewater

START Summer 2020

COMPLETION Fall 2022

DETAILS The project will replace an existing force main to provide reliability and maintenance capabilities for the golf course lift station.


MAP

project map



What is the purpose of this project?
This project will replace an existing force main to provide reliability and maintenance capabilities to the golf course lift station.
How long is the project going to take to complete?
8 months (242 calendar days). Work is scheduled to begin Summer and anticipated to be completed in Fall. The project schedule depends upon weather conditions.


Have More Questions? Click here for more answers.


  • Restoration Update

    Share Restoration Update on Facebook Share Restoration Update on Twitter Share Restoration Update on Linkedin Email Restoration Update link
    • Restoration at Median complete
    • Restoration inside at the golf course complete
    • Restoration around the Intersection
      • Bushes and landscaping complete
      • Tree planting today

    Except one tree at the intersection, there is no pending construction activity in the project. Close-out of the project will be next week. Thanks to District E and the Golf Course residents.

  • Restoration Update

    Share Restoration Update on Facebook Share Restoration Update on Twitter Share Restoration Update on Linkedin Email Restoration Update link
    • Restoration at Median complete
      • Contractor may be onsite to water the Sod as needed over next two weeks.
    • Restoration around the Discharge Manhole/Intersection complete
      • Tree planting is scheduled for this Thursday.
    • Restoration inside at the golf course complete.
      • Watering of various areas may be occurring as needed.
  • Kingwood Drive and Lake Kingwood Trails Traffic Update

    Share Kingwood Drive and Lake Kingwood Trails Traffic Update on Facebook Share Kingwood Drive and Lake Kingwood Trails Traffic Update on Twitter Share Kingwood Drive and Lake Kingwood Trails Traffic Update on Linkedin Email Kingwood Drive and Lake Kingwood Trails Traffic Update link

    The intersection is fully open to traffic effective on 9/21/2021. Restoration is currently taking place and is anticipated to be complete in October. The restoration work has limited impact to residents and local traffic.

  • Kingwood Drive and Lake Kingwood Trails Traffic Update

    Share Kingwood Drive and Lake Kingwood Trails Traffic Update on Facebook Share Kingwood Drive and Lake Kingwood Trails Traffic Update on Twitter Share Kingwood Drive and Lake Kingwood Trails Traffic Update on Linkedin Email Kingwood Drive and Lake Kingwood Trails Traffic Update link

    The Final Pressure Test was successfully completed on Saturday. Great News! Due to TS Nicholas, Contractor will not perform contractual work on Monday and Tuesday. The crew will monitor the construction site and will respond to adjust traffic controls and bypass systems.

  • Kingwood Drive and Lake Kingwood Trails Traffic Update

    Share Kingwood Drive and Lake Kingwood Trails Traffic Update on Facebook Share Kingwood Drive and Lake Kingwood Trails Traffic Update on Twitter Share Kingwood Drive and Lake Kingwood Trails Traffic Update on Linkedin Email Kingwood Drive and Lake Kingwood Trails Traffic Update link

    The signal timing @ Kingwood Dr. and Lake Kingwood Trail has been restored to the pre-construction condition.

    Additional updates will be provided when available.

  • Kingwood Drive and Lake Kingwood Trails Traffic Update

    Share Kingwood Drive and Lake Kingwood Trails Traffic Update on Facebook Share Kingwood Drive and Lake Kingwood Trails Traffic Update on Twitter Share Kingwood Drive and Lake Kingwood Trails Traffic Update on Linkedin Email Kingwood Drive and Lake Kingwood Trails Traffic Update link

    The bypass ramp has been relocated about 75 feet south from the previous location. This solution has restored the lane configuration to the pre-existing condition and right turn lane is open for traffic. Transtar is scheduled to adjust signal timing for today.

    The Contractor is currently adjusting joint at one location(Golf Course area) and the next pressure test will be scheduled later this week.

  • Kingwood Drive and Lake Kingwood Trails Traffic Update

    Share Kingwood Drive and Lake Kingwood Trails Traffic Update on Facebook Share Kingwood Drive and Lake Kingwood Trails Traffic Update on Twitter Share Kingwood Drive and Lake Kingwood Trails Traffic Update on Linkedin Email Kingwood Drive and Lake Kingwood Trails Traffic Update link

    Contractor agreed to complete the pressure test, remove the bypass, and restore the site within 3-4 weeks.

    Contractor agreed to relocate the bypass ramp about 75 feet south from the current location by Tuesday Night, August 21, 2021. This interim solution will restore the northbound right turning lane.

    Contractor will submit a request for signal timing adjustment by August 18, 2021. Capital Projects will coordinate with Transtar to expedite this request.