Kingwood Drive and Lake Kingwood Trails Traffic Update

Contractor agreed to complete the pressure test, remove the bypass, and restore the site within 3-4 weeks.

Contractor agreed to relocate the bypass ramp about 75 feet south from the current location by Tuesday Night, August 21, 2021. This interim solution will restore the northbound right turning lane.

Contractor will submit a request for signal timing adjustment by August 18, 2021. Capital Projects will coordinate with Transtar to expedite this request.