Force Main Renewal - Golf Course

Share Force Main Renewal - Golf Course on Facebook Share Force Main Renewal - Golf Course on Twitter Share Force Main Renewal - Golf Course on Linkedin Email Force Main Renewal - Golf Course link

PROJECT NUMBER R-000035-013A

LOCATION Along Pine Bend Dr. to Laurel Trail Dr. and Lake Kingwood Trail just south of Kingwood Drive

COUNCIL DISTRICT E

BUDGET $1,862,260

TYPE Wastewater

START Summer 2020

COMPLETION Fall 2022

DETAILS The project will replace an existing force main to provide reliability and maintenance capabilities for the golf course lift station.


MAP

project map



What is the purpose of this project?
This project will replace an existing force main to provide reliability and maintenance capabilities to the golf course lift station.
How long is the project going to take to complete?
8 months (242 calendar days). Work is scheduled to begin Summer and anticipated to be completed in Fall. The project schedule depends upon weather conditions.


Have More Questions? Click here for more answers.


PROJECT NUMBER R-000035-013A

LOCATION Along Pine Bend Dr. to Laurel Trail Dr. and Lake Kingwood Trail just south of Kingwood Drive

COUNCIL DISTRICT E

BUDGET $1,862,260

TYPE Wastewater

START Summer 2020

COMPLETION Fall 2022

DETAILS The project will replace an existing force main to provide reliability and maintenance capabilities for the golf course lift station.


MAP

project map



What is the purpose of this project?
This project will replace an existing force main to provide reliability and maintenance capabilities to the golf course lift station.
How long is the project going to take to complete?
8 months (242 calendar days). Work is scheduled to begin Summer and anticipated to be completed in Fall. The project schedule depends upon weather conditions.


Have More Questions? Click here for more answers.