Crenshaw Road from South Shaver Street to Allen Genoa Road Reconstruction

Share Crenshaw Road from South Shaver Street to Allen Genoa Road Reconstruction on Facebook Share Crenshaw Road from South Shaver Street to Allen Genoa Road Reconstruction on Twitter Share Crenshaw Road from South Shaver Street to Allen Genoa Road Reconstruction on Linkedin Email Crenshaw Road from South Shaver Street to Allen Genoa Road Reconstruction link

PROJECT NUMBER N-100037-0001

LOCATION Crenshaw Road from South Shaver Street to Allen Genoa Road

COUNCIL DISTRICT E

BUDGET $1,000,000

TYPE Street

START Summer 2023

COMPLETION Summer 2023

DETAILS Click Here for more information


MAP

Project Map



General Project Information

How long is this project going to take to complete?
3 months (95 calendar days). Work is scheduled to begin in Summer 2023 and is anticipated to be completed in Summer 2023. The project schedule depends upon weather conditions.

Which government agency is performing the work?
Harris County Engineering Department.

Will this project improve drainage for the area?
The project is not designed to improve or correct drainage issues; it will preserve and prolong the life of the road base and provide for a smoother riding surface.


Have More Questions? Click here for more answers

PROJECT NUMBER N-100037-0001

LOCATION Crenshaw Road from South Shaver Street to Allen Genoa Road

COUNCIL DISTRICT E

BUDGET $1,000,000

TYPE Street

START Summer 2023

COMPLETION Summer 2023

DETAILS Click Here for more information


MAP

Project Map



General Project Information

How long is this project going to take to complete?
3 months (95 calendar days). Work is scheduled to begin in Summer 2023 and is anticipated to be completed in Summer 2023. The project schedule depends upon weather conditions.

Which government agency is performing the work?
Harris County Engineering Department.

Will this project improve drainage for the area?
The project is not designed to improve or correct drainage issues; it will preserve and prolong the life of the road base and provide for a smoother riding surface.


Have More Questions? Click here for more answers

  • August 2023 Update

    Share August 2023 Update on Facebook Share August 2023 Update on Twitter Share August 2023 Update on Linkedin Email August 2023 Update link

    All reinforced concrete pipe installation/replacement, milling, base repair, level up and surface, and concrete sidewalks had been completed. The contractor is working on driveways and will start clearing and mowing ditches. The project should be completed No Later than the end of next week. Thank you!