Park Ten Wastewater Treatment Plant

Share Park Ten Wastewater Treatment Plant on Facebook Share Park Ten Wastewater Treatment Plant on Twitter Share Park Ten Wastewater Treatment Plant on Linkedin Email Park Ten Wastewater Treatment Plant link

Project Overview

Council District: A & G

Project Number: R-000536-0019

Estimated Budget: $39,980,681

Start: Spring 2024

Completion: Winter 2026



Project Impact AreaProject Map


Community Feedback

Have questions or feedback about this project? Email us at engage@houstontx.gov or call 311.

Project Overview

Council District: A & G

Project Number: R-000536-0019

Estimated Budget: $39,980,681

Start: Spring 2024

Completion: Winter 2026



Project Impact AreaProject Map


Community Feedback

Have questions or feedback about this project? Email us at engage@houstontx.gov or call 311.

  • Latest News

    Share Latest News on Facebook Share Latest News on Twitter Share Latest News on Linkedin Email Latest News link

    Park Row Area:

    Pavement restoration has been completed around Shaft 5 to Shaft 7 at Stations 20+64 and 29+78.

    The hand tunnel between Shaft 12 at Station 51+44 and the existing shaft across Park Row is ongoing.

    Work on Shaft 6 at Station 25+03 has been completed.

    Installation at Shaft 1 at Station 2+05 near the wastewater treatment plant is currently underway.

    The only remaining shaft installation along Park Row will be Shaft 12 at Station 51+44.

    North Eldridge Area:

    The shaft at the intersection of Memorial Drive and North Eldridge Parkway has been completed, and the traffic control measures remain unchanged.

    Shaft 12 has been completed. The tunneling subcontractor is mobilizing for tunnel preparation between Shaft 12 and Shaft 18.

    Park Row Area:

    Pavement restoration has been completed around Shaft 5 to Shaft 7 at Stations 20+64 and 29+78.

    The hand tunnel between Shaft 12 at Station 51+44 and the existing shaft across Park Row is ongoing.

    Work on Shaft 6 at Station 25+03 has been completed.

    Installation at Shaft 1 at Station 2+05 near the wastewater treatment plant is currently underway.

    The only remaining shaft installation along Park Row will be Shaft 12 at Station 51+44.

    North Eldridge Area:

    The shaft at the intersection of Memorial Drive and North Eldridge Parkway has been completed, and the traffic control measures remain unchanged.

    Shaft 12 has been completed. The tunneling subcontractor is mobilizing for tunnel preparation between Shaft 12 and Shaft 18.