Water Line Replacement Along Telephone Road from Bellfort to Convair

Share Water Line Replacement Along Telephone Road from Bellfort to Convair on Facebook Share Water Line Replacement Along Telephone Road from Bellfort to Convair on Twitter Share Water Line Replacement Along Telephone Road from Bellfort to Convair on Linkedin Email Water Line Replacement Along Telephone Road from Bellfort to Convair link

PROJECT NUMBER S-000700-A044

LOCATION See project map

COUNCIL DISTRICT I

BUDGET $5,107,617

TYPE Water

START Summer 2023

COMPLETION Spring 2024

DETAILS This program provides for the construction of water main extension projects to improve circulation and fire protection.


MAPProject Map




General Project Information

What is the purpose of this project? This project is necessary to is to provide quality water services, fire protection, and improve system reliability.

How long is this project going to take to complete? 8 months (220 calendar days). Work is scheduled to begin in Summer 2023 and anticipated to be completed in Winter 2024. The project schedule depends upon weather conditions.

Have More Questions? Click here for more answers

PROJECT NUMBER S-000700-A044

LOCATION See project map

COUNCIL DISTRICT I

BUDGET $5,107,617

TYPE Water

START Summer 2023

COMPLETION Spring 2024

DETAILS This program provides for the construction of water main extension projects to improve circulation and fire protection.


MAPProject Map




General Project Information

What is the purpose of this project? This project is necessary to is to provide quality water services, fire protection, and improve system reliability.

How long is this project going to take to complete? 8 months (220 calendar days). Work is scheduled to begin in Summer 2023 and anticipated to be completed in Winter 2024. The project schedule depends upon weather conditions.

Have More Questions? Click here for more answers

  • Latest News

    Share Latest News on Facebook Share Latest News on Twitter Share Latest News on Linkedin Email Latest News link

    The project is at 90% completion. The Project is scheduled to be completed by Spring 2024. The remaining work will include waterline connections and restoration. The contractor will notify the customer if there are any impacts on services.

  • Latest News

    Share Latest News on Facebook Share Latest News on Twitter Share Latest News on Linkedin Email Latest News link

    The 20-inch line is currently underutilized (60% to 40%), the unused water recirculates into the waterline and repumped into the system, which impacts the water quality. Reduction of the waterline to 16-inch will prevent the recirculation.

  • Latest News

    Share Latest News on Facebook Share Latest News on Twitter Share Latest News on Linkedin Email Latest News link

    Construction will commence this month starting on the South side of Convair Street. Please subscribe to this project page to receive updates as they become available.

Page last updated: 22 Mar 2024, 12:02 PM