Tree Lane Bridge Rehabilitation

Share Tree Lane Bridge Rehabilitation on Facebook Share Tree Lane Bridge Rehabilitation on Twitter Share Tree Lane Bridge Rehabilitation on Linkedin Email Tree Lane Bridge Rehabilitation link

PROJECT NUMBER N-320445-0008

LOCATION Refer to Map

COUNCIL DISTRICT E

BUDGET $909,000

TYPE Street

START Spring 2024

COMPLETION Summer 2024

DETAILS Due to rip rap failures under the bridge, the channels and columns have been exposed to severe scour/erosion, and repairs are needed. This can lead to access, safety, health, and the well-being of the citizens. The channel condition of this bridge is a major contributor to the flooding of Ben’s Branch natural stream. This bridge rehabilitation is an immediate improvement for flood prevention and protection of the citizens in the Kingwood area.


MAP


General Project Information

What is the purpose of this project?
The purpose is to rehab a critical City of Houston infrastructure asset to protect the health and safety of residents.

How long is the project going to take?
(150 calendar days). Work is scheduled to begin in
Spring 2024 and is anticipated to be completed in Summer 2024. The project schedule depends upon weather conditions.


Have More Questions? Click here for more answers.

PROJECT NUMBER N-320445-0008

LOCATION Refer to Map

COUNCIL DISTRICT E

BUDGET $909,000

TYPE Street

START Spring 2024

COMPLETION Summer 2024

DETAILS Due to rip rap failures under the bridge, the channels and columns have been exposed to severe scour/erosion, and repairs are needed. This can lead to access, safety, health, and the well-being of the citizens. The channel condition of this bridge is a major contributor to the flooding of Ben’s Branch natural stream. This bridge rehabilitation is an immediate improvement for flood prevention and protection of the citizens in the Kingwood area.


MAP


General Project Information

What is the purpose of this project?
The purpose is to rehab a critical City of Houston infrastructure asset to protect the health and safety of residents.

How long is the project going to take?
(150 calendar days). Work is scheduled to begin in
Spring 2024 and is anticipated to be completed in Summer 2024. The project schedule depends upon weather conditions.


Have More Questions? Click here for more answers.

Is there anything you want us to know?

You need to be signed in to add your question.

  • Share Why has the Tree Lane Bridge Rehab project been delayed and when do you expect construction to start? on Facebook Share Why has the Tree Lane Bridge Rehab project been delayed and when do you expect construction to start? on Twitter Share Why has the Tree Lane Bridge Rehab project been delayed and when do you expect construction to start? on Linkedin Email Why has the Tree Lane Bridge Rehab project been delayed and when do you expect construction to start? link

    Why has the Tree Lane Bridge Rehab project been delayed and when do you expect construction to start?

    ReduceFlooding.com asked about 2 months ago

    Ready...Set...ENGAGE!

    We appreciate your interest in the Tree Lane Bridge project. Prior to beginning, the Project required additional coordination and discussions with the construction company, local community representatives, and Council Member Fred Flickinger’s office to maximize project efficiency, minimize community impact, and confirm material availability. Therefore, the original start date of Winter 2024 was adjusted to Spring 2024.