Share Pine Forest Wastewater Improvements on FacebookShare Pine Forest Wastewater Improvements on TwitterShare Pine Forest Wastewater Improvements on LinkedinEmail Pine Forest Wastewater Improvements link
DETAILS This project includes the construction of 1,800 linear feet of wastewater lines and associated wastewater connections. This project also includes concrete and paving improvements.
MAP
General Project Information
What is the purpose of this project?
By replacing the backlot wastewater with new wastewater in the public right of way, this project will address complaints about frequent wastewater backing up from the existing wastewater main.
How long is this project going to take to complete? 13 months (400 calendar days). Work is scheduled to begin in Spring 2024 and is anticipated to be completed in Summer 2025. The project schedule depends upon weather conditions. Please see the phasing map for details.
DETAILS This project includes the construction of 1,800 linear feet of wastewater lines and associated wastewater connections. This project also includes concrete and paving improvements.
MAP
General Project Information
What is the purpose of this project?
By replacing the backlot wastewater with new wastewater in the public right of way, this project will address complaints about frequent wastewater backing up from the existing wastewater main.
How long is this project going to take to complete? 13 months (400 calendar days). Work is scheduled to begin in Spring 2024 and is anticipated to be completed in Summer 2025. The project schedule depends upon weather conditions. Please see the phasing map for details.