Kirkwood Paving and Drainage - Subproject 2

Share Kirkwood Paving and Drainage - Subproject 2 on Facebook Share Kirkwood Paving and Drainage - Subproject 2 on Twitter Share Kirkwood Paving and Drainage - Subproject 2 on Linkedin Email Kirkwood Paving and Drainage - Subproject 2 link

PROJECT NUMBER N-100029-0002

LOCATION Refer to map

COUNCIL DISTRICT G

BUDGET $25,410,000

TYPE Street

START Summer 2023

COMPLETION Spring 2025

DETAILS The work includes new concrete and asphalt pavement, curbs, wheelchair ramps, sidewalks, streetlights, and reconstruction of median openings. The existing drainage system will be upgraded with the installation of new storm sewers, inlets, manholes, and inline detention. The existing water main will be replaced to include new fire hydrants and valves.


MAP

Project Map


General Project Information

What is the purpose of this project?

This project is a part of the Street and Traffic Capital Improvement project and is necessary to improve roadway and traffic mobility and to meet City of Houston Design Standards.


How long is the project going to take?
Work began in Summer 2023 and is anticipated to be completed in Spring 2025. The project schedule depends upon weather conditions.


Have More Questions? Click here for more answers

PROJECT NUMBER N-100029-0002

LOCATION Refer to map

COUNCIL DISTRICT G

BUDGET $25,410,000

TYPE Street

START Summer 2023

COMPLETION Spring 2025

DETAILS The work includes new concrete and asphalt pavement, curbs, wheelchair ramps, sidewalks, streetlights, and reconstruction of median openings. The existing drainage system will be upgraded with the installation of new storm sewers, inlets, manholes, and inline detention. The existing water main will be replaced to include new fire hydrants and valves.


MAP

Project Map


General Project Information

What is the purpose of this project?

This project is a part of the Street and Traffic Capital Improvement project and is necessary to improve roadway and traffic mobility and to meet City of Houston Design Standards.


How long is the project going to take?
Work began in Summer 2023 and is anticipated to be completed in Spring 2025. The project schedule depends upon weather conditions.


Have More Questions? Click here for more answers

  • Traffic Update

    Share Traffic Update on Facebook Share Traffic Update on Twitter Share Traffic Update on Linkedin Email Traffic Update link

    We are performing construction near Waldemar and Kirkwood crossing, our contractor has ensured that during peak hours, morning and afternoon, flaggers will be available to help get pedestrian traffic safely across. The flaggers will again be implemented by the contractor during the paving operations at this intersection. In addition, contractors will have additional barrels and traffic control devices in place during this construction.

  • Water Service Outage

    Share Water Service Outage on Facebook Share Water Service Outage on Twitter Share Water Service Outage on Linkedin Email Water Service Outage link

    Residents affected along Kirkwood from just south of Briar Forest to just north of Southlake Dr. and those residents along Waldemar from Cherry Bend to Kirkwood.


    WHAT

    Water Service Outage

    WHEN

    Friday March 1st from 7AM to 3PM

    WHY

    To tie in the new waterline

    WHO TO CONTACT

    Houston 311 reference project number N-100029-0002

  • Latest News

    Share Latest News on Facebook Share Latest News on Twitter Share Latest News on Linkedin Email Latest News link

    The waterline has been repaired and all services have been restored,

  • Latest News

    Share Latest News on Facebook Share Latest News on Twitter Share Latest News on Linkedin Email Latest News link

    A water main break was reported on February 8th. The contractor is currently addressing the issue with urgency and diligence. Further updates will be provided as soon as they are available. Thank you for your patience and understanding.

  • Traffic Closure

    Share Traffic Closure on Facebook Share Traffic Closure on Twitter Share Traffic Closure on Linkedin Email Traffic Closure link

    WHAT

    Traffic Closure at Overbrook Lane and Kirkwood

    WHEN

    February 9th to February 26th

    WHY

    To construct Water and Wastewater Lines

    WHO TO CONTACT

    Houston 311 reference Project Number N-100029-0002

  • Latest News

    Share Latest News on Facebook Share Latest News on Twitter Share Latest News on Linkedin Email Latest News link

    Completed to Date:

    • Contractor has completed the wastewater system improvements. Contractor continues to install the proposed wastewater system along the project alignment.
    • Contractor has commenced the installation of the 16-inch water line proposed along Kirkwood. Approximately 300 linear feet of the 3500 linear feet has been installed to date.

    Planned Work (Next 30 Days)

    • Continue installation of wastewater system.
    • Continue installation of 16-inch water line. Start testing the water line.
    • Contractor anticipates the water and wastewater work will be completed in April.
  • Trees

    Share Trees on Facebook Share Trees on Twitter Share Trees on Linkedin Email Trees link

    The City understands the value and beauty of our trees and is committed to make sure we evaluate and preserve all trees within the project area when possible. However, due to the drainage, safety and mobility improvements planned for this project, some of the trees along Kirkwood Drive will be impacted and require removal. The good news is that no trees along Briar Forest will be impacted by this project.

    The City does have a tree ordinance that governs the removal, mitigation and care of trees within the City’s right-of-way for construction projects. At the conclusion of this project, the Contractor will be installing new trees along the project alignment to mitigate for the removal of the existing trees per the Ordinance. The tree protection plan for this project is posted here on the project page. Please subscribe to this page to receive the latest updates as they become available.

  • Traffic Switch

    Share Traffic Switch on Facebook Share Traffic Switch on Twitter Share Traffic Switch on Linkedin Email Traffic Switch link

    WHAT

    Traffic Switch

    WHEN

    Wednesday, January 10th at 1PM-Wednesday, February 14th at 7PM

    WHY

    To construct Water and Wastewater lines

    WHO TO CONTACT

    Houston 311 reference Project Number N-100029-0002

  • Latest News

    Share Latest News on Facebook Share Latest News on Twitter Share Latest News on Linkedin Email Latest News link
    • Contractor has installed tree protection measures (including fencing) throughout the project area.
    • Contractor has commenced pruning of the trees that are adjacent to the construction areas.
    • The contractor has started removing trees designated for removal in the project plans.
    • The water and sanitary sewer improvements will commence this month.
    • There will be moving lane closures to accommodate the water and sewer work.
Page last updated: 06 May 2024, 04:13 PM