Houston Heights, John Brashear and Memorial Heights Paving and Drainage

Share Houston Heights, John Brashear and Memorial Heights Paving and Drainage on Facebook Share Houston Heights, John Brashear and Memorial Heights Paving and Drainage on Twitter Share Houston Heights, John Brashear and Memorial Heights Paving and Drainage on Linkedin Email Houston Heights, John Brashear and Memorial Heights Paving and Drainage link

PROJECT NUMBER N-210001-0001

LOCATION Refer to map

COUNCIL DISTRICT C & H

BUDGET $14,567,455

TYPE Paving and Drainage

START Winter 2022

COMPLETION Spring 2024

DETAILS Construction of concrete paving with storm drainage, curbs, sidewalks, driveways, street lighting, and necessary underground utilities.


MAPProject Map


General Project Information

What is the purpose of this project?
This project is designed to improve safety and mobility in the area.


How long is this project going to take to complete?
20 months (605 calendar days). Work began in Winter 2022 and is anticipated to be completed in Spring 2024. The project schedule depends upon weather conditions
.

Have More Questions? Click here for more answers

PROJECT NUMBER N-210001-0001

LOCATION Refer to map

COUNCIL DISTRICT C & H

BUDGET $14,567,455

TYPE Paving and Drainage

START Winter 2022

COMPLETION Spring 2024

DETAILS Construction of concrete paving with storm drainage, curbs, sidewalks, driveways, street lighting, and necessary underground utilities.


MAPProject Map


General Project Information

What is the purpose of this project?
This project is designed to improve safety and mobility in the area.


How long is this project going to take to complete?
20 months (605 calendar days). Work began in Winter 2022 and is anticipated to be completed in Spring 2024. The project schedule depends upon weather conditions
.

Have More Questions? Click here for more answers

Is there anything you want us to know?

You need to be signed in to add your question.

  • Share Hello, Are there any plans to put street lighting and most important trash cans on the completed street? The amount of trash has reached a concerning level due to high traffic of people and construction workers littering. There not 1 trash can for the members of the community in the entire area. Thank you for your feedback on Facebook Share Hello, Are there any plans to put street lighting and most important trash cans on the completed street? The amount of trash has reached a concerning level due to high traffic of people and construction workers littering. There not 1 trash can for the members of the community in the entire area. Thank you for your feedback on Twitter Share Hello, Are there any plans to put street lighting and most important trash cans on the completed street? The amount of trash has reached a concerning level due to high traffic of people and construction workers littering. There not 1 trash can for the members of the community in the entire area. Thank you for your feedback on Linkedin Email Hello, Are there any plans to put street lighting and most important trash cans on the completed street? The amount of trash has reached a concerning level due to high traffic of people and construction workers littering. There not 1 trash can for the members of the community in the entire area. Thank you for your feedback link

    Hello, Are there any plans to put street lighting and most important trash cans on the completed street? The amount of trash has reached a concerning level due to high traffic of people and construction workers littering. There not 1 trash can for the members of the community in the entire area. Thank you for your feedback

    besparano asked about 1 year ago

    Thank You for contacting Engage Houston. The project does not propose the installation of new street lights or installation of trash receptacles. We have notified the project team to have the construction crews clean up behind themselves. Thank you!

  • Share Hello, Are there any plans to slow down the car traffic on Center Street? Even with the ongoing construction, drivers are considering this street a race track. Thank you. on Facebook Share Hello, Are there any plans to slow down the car traffic on Center Street? Even with the ongoing construction, drivers are considering this street a race track. Thank you. on Twitter Share Hello, Are there any plans to slow down the car traffic on Center Street? Even with the ongoing construction, drivers are considering this street a race track. Thank you. on Linkedin Email Hello, Are there any plans to slow down the car traffic on Center Street? Even with the ongoing construction, drivers are considering this street a race track. Thank you. link

    Hello, Are there any plans to slow down the car traffic on Center Street? Even with the ongoing construction, drivers are considering this street a race track. Thank you.

    stefan.sievers asked about 1 year ago

    Howdy Neighbor! Thank you for your question! Please look into the Neighborhood Traffic Management Program (NTMP), the purpose is to improve the neighborhood quality of life by implementing “Traffic Calming” measures to reduce excessive vehicular speeds and cut-through traffic on neighborhood street https://www.houstonpublicworks.org/multi-modal-safety-and-design.

  • Share Any updates on when the construction on Center street between South Heights blvd and Studemont will be complete and final? on Facebook Share Any updates on when the construction on Center street between South Heights blvd and Studemont will be complete and final? on Twitter Share Any updates on when the construction on Center street between South Heights blvd and Studemont will be complete and final? on Linkedin Email Any updates on when the construction on Center street between South Heights blvd and Studemont will be complete and final? link

    Any updates on when the construction on Center street between South Heights blvd and Studemont will be complete and final?

    linbed asked about 1 year ago

    Howdy Neighbor! Thank you for your question! The Houston Heights, John Brashear and Memorial Heights Paving and Drainage project is scheduled for completion Fall 2023. The project schedule depends upon weather conditions and any unforeseen circumstances. For a reference guide on the project seasons please visit www.engagehouston.org/seasons-months.


  • Share The intersection of East 2nd St and Height Blvd was left with a poor road transition where now there is a big unleveled pavement on it. Is there a plan to fix this? Thank you! on Facebook Share The intersection of East 2nd St and Height Blvd was left with a poor road transition where now there is a big unleveled pavement on it. Is there a plan to fix this? Thank you! on Twitter Share The intersection of East 2nd St and Height Blvd was left with a poor road transition where now there is a big unleveled pavement on it. Is there a plan to fix this? Thank you! on Linkedin Email The intersection of East 2nd St and Height Blvd was left with a poor road transition where now there is a big unleveled pavement on it. Is there a plan to fix this? Thank you! link

    The intersection of East 2nd St and Height Blvd was left with a poor road transition where now there is a big unleveled pavement on it. Is there a plan to fix this? Thank you!

    besparano asked about 1 year ago

    Howdy Neighbor! This will be overlaid with Type D asphalt surface course. There are multiple transitions on this project and will be done in groups. East 2nd street is included in the first group. We anticipate paving the first group in the next few weeks. Thanks

  • Share Since construction started after the meeting was held and phase 2 started before phase 1, when will Wagner street (phase 1) start and be completed? Thank you? on Facebook Share Since construction started after the meeting was held and phase 2 started before phase 1, when will Wagner street (phase 1) start and be completed? Thank you? on Twitter Share Since construction started after the meeting was held and phase 2 started before phase 1, when will Wagner street (phase 1) start and be completed? Thank you? on Linkedin Email Since construction started after the meeting was held and phase 2 started before phase 1, when will Wagner street (phase 1) start and be completed? Thank you? link

    Since construction started after the meeting was held and phase 2 started before phase 1, when will Wagner street (phase 1) start and be completed? Thank you?

    ConcernedNeighbor asked almost 2 years ago

    Thank you for your question. The current construction schedule indicates that work along Wagner will be completed close to the end of November 2022.

  • Share Myself and many of my neighbors on Center Street and Wager were wondering why the trees were cut down so early in the project when the timeline/schedule indicates the work would not start until next year. Will the street remain treeless until late 2023 or is the project being run at a different timeline than that on the documentation provided? on Facebook Share Myself and many of my neighbors on Center Street and Wager were wondering why the trees were cut down so early in the project when the timeline/schedule indicates the work would not start until next year. Will the street remain treeless until late 2023 or is the project being run at a different timeline than that on the documentation provided? on Twitter Share Myself and many of my neighbors on Center Street and Wager were wondering why the trees were cut down so early in the project when the timeline/schedule indicates the work would not start until next year. Will the street remain treeless until late 2023 or is the project being run at a different timeline than that on the documentation provided? on Linkedin Email Myself and many of my neighbors on Center Street and Wager were wondering why the trees were cut down so early in the project when the timeline/schedule indicates the work would not start until next year. Will the street remain treeless until late 2023 or is the project being run at a different timeline than that on the documentation provided? link

    Myself and many of my neighbors on Center Street and Wager were wondering why the trees were cut down so early in the project when the timeline/schedule indicates the work would not start until next year. Will the street remain treeless until late 2023 or is the project being run at a different timeline than that on the documentation provided?

    linbed asked about 2 years ago

    The project drawings for this project designate trees for removal within the project limits. Contractor elected to remove all trees designated for removal at the beginning of the project. The project is currently on schedule. Contractor will install all proposed trees towards the end of the project.

  • Share Will there be improvements done to the roads between Studemont and Sawyer? They need to be repaved, lines drawn for safety. Old rails removed. Will Union Pacific improve the crossings affected in this improvement project? on Facebook Share Will there be improvements done to the roads between Studemont and Sawyer? They need to be repaved, lines drawn for safety. Old rails removed. Will Union Pacific improve the crossings affected in this improvement project? on Twitter Share Will there be improvements done to the roads between Studemont and Sawyer? They need to be repaved, lines drawn for safety. Old rails removed. Will Union Pacific improve the crossings affected in this improvement project? on Linkedin Email Will there be improvements done to the roads between Studemont and Sawyer? They need to be repaved, lines drawn for safety. Old rails removed. Will Union Pacific improve the crossings affected in this improvement project? link

    Will there be improvements done to the roads between Studemont and Sawyer? They need to be repaved, lines drawn for safety. Old rails removed. Will Union Pacific improve the crossings affected in this improvement project?

    IDelgado72 asked about 2 years ago

    The Houston Heights, John Brashear, and Memorial Heights Paving and Drainage Improvements Project (N-210001-0001) does not include improvements to areas east of Studemont at this time.

  • Share Do l have to move my plants that are in the way of the new side walk on Facebook Share Do l have to move my plants that are in the way of the new side walk on Twitter Share Do l have to move my plants that are in the way of the new side walk on Linkedin Email Do l have to move my plants that are in the way of the new side walk link

    Do l have to move my plants that are in the way of the new side walk

    Jesus S Cervantes asked about 2 years ago

    If you have specific landscaping that you would like to be saved, we suggest that property owners relocate such plant materials now. Grass will be restored in areas upon completion of all construction.

Page last updated: 06 May 2024, 03:52 PM