GENERAL PROJECT INFORMATION
Q: What is the purpose of this project?
A: The benefits of the project include upgraded sanitary sewers and force mains.
Q: What is going to be replaced/installed in this project?
A: Work of tThe project primarily consists of installation of approximately 5500-linear feet of force main.
Q: How long is this project going to take to complete?
A: (597 calendar days). Work is scheduled to begin in Spring 2024 and anticipated to be completed in Winter 2026. The project schedule will depend on weather conditions.
SIDEWALKS, TREES & LIGHTING
Q: Will there be Street Light Poles installed?
A: No, street light poles will not be installed.
Q: What trees are being removed?
A: No.
CONSTRUCTION
Q: At some point, will my utilities be affected?
A: No utilities should be impacted, but unforeseen issues may arise due to the nature of underground work.
Q: Will this project cause traffic/mobility issues (lane closures, increase of trucks in the area, etc.)?
A: Yes. Partial lane closures along the construction path as provided in the exhibits.
Q: Are they going to dig up the front area or just the street?A: Roadsides and certain driveways along the construction route will be dug.
Q: When will my services be transferred to the new line?
A: Upon substantial completion of the work.
CONTACT INFORMATION
NON-EMERGENCY NEEDS
Dial 311 - Mention to the operator the following 3 things along with your issue:
- Project number: R-000035-0025
- Force Main Renewal/Replacement of Hempstead No.1 (WCID #28) Lift Stations
- Refer the questions/comments to Capital Projects
EMERGENCY NEEDS
Contact Contractor or the 24-hour contact provided by the contractor.
Contractor
Resicom Inc.
Michelle Turner – 713.666.0775
Houston Public Works
Mack Nosrat – Inspector 832.395.5852
Jack Cortez – Project Manager 713.299.7072
HELPFUL LINKS
PROJECT SPECIFIC CONCERNS
Engage@houstontx.gov
GENERAL CONCERNS
3-1-1 or 713.837.0311
www.houston311.org