Facilities Improvements Package 2
Share Facilities Improvements Package 2 on Facebook
Share Facilities Improvements Package 2 on Twitter
Share Facilities Improvements Package 2 on Linkedin
Email Facilities Improvements Package 2 link
PROJECT NUMBER S-001000-0045-4
LOCATION Refer to project map
BUDGET $8,537,700.00
TYPE Water
START Summer 2022
COMPLETION Summer 2024
DETAILS Improvements at 18 well sites and re-pump stations throughout the City of Houston
MAP
What is the purpose of this project? This program provides for the renewal of pump stations. Improvements include renovations, individual pump installation, replacement of electrical switchgear, generators, valves, meters, motors, pumps, lead abatement, site demolition, and roadway | |
How long is this project going to take to complete? 23 months (784 calendar days). Work is scheduled to begin in Summer 2022 and is anticipated to be completed in Summer 2024. The project schedule depends upon weather conditions. Please see the phasing map for details. |