East Water Purification Plant Improvements Package 2

Share East Water Purification Plant Improvements Package 2 on Facebook Share East Water Purification Plant Improvements Package 2 on Twitter Share East Water Purification Plant Improvements Package 2 on Linkedin Email East Water Purification Plant Improvements Package 2 link

PROJECT NUMBER S-000056-080B

LOCATION Refer to project map

COUNCIL DISTRICT E

BUDGET $23,068,100

TYPE Water

START Spring 2022

COMPLETION Spring 2024

DETAILS This project upgrades and optimizes the East Water Plant, and increases the capacity and reliability to meet immediate and future needs of the City and its customers.



MAPProject Map




What is the purpose of this project?
This project is necessary to meet water demand, Safe Drinking Water Act, TCEQ and Harris-Galveston Subsidence District requirements.
How long is this project going to take to complete?
22 months. Work begins June 27, 2022 and the completion date is projected for April 29, 2024. These dates are estimates. the project schedule depends upon weather conditions and the contractor's production rate.

Have More Questions? Click here for more answers


PROJECT NUMBER S-000056-080B

LOCATION Refer to project map

COUNCIL DISTRICT E

BUDGET $23,068,100

TYPE Water

START Spring 2022

COMPLETION Spring 2024

DETAILS This project upgrades and optimizes the East Water Plant, and increases the capacity and reliability to meet immediate and future needs of the City and its customers.



MAPProject Map




What is the purpose of this project?
This project is necessary to meet water demand, Safe Drinking Water Act, TCEQ and Harris-Galveston Subsidence District requirements.
How long is this project going to take to complete?
22 months. Work begins June 27, 2022 and the completion date is projected for April 29, 2024. These dates are estimates. the project schedule depends upon weather conditions and the contractor's production rate.

Have More Questions? Click here for more answers


  • April 2023 Update

    Share April 2023 Update on Facebook Share April 2023 Update on Twitter Share April 2023 Update on Linkedin Email April 2023 Update link

    Project is currently 30% complete in place. Major construction activities include equipment and piping demolition plus the removal of chlorine cylinders from the Ton Cylinder Building.