Almeda Sims Wastewater Treatment Plant Improvements

Share Almeda Sims Wastewater Treatment Plant Improvements on Facebook Share Almeda Sims Wastewater Treatment Plant Improvements on Twitter Share Almeda Sims Wastewater Treatment Plant Improvements on Linkedin Email Almeda Sims Wastewater Treatment Plant Improvements link

PROJECT NUMBER R-000298-0014

LOCATION Refer to Project Map

COUNCIL DISTRICT D

BUDGET $21,210,192

TYPE Wastewater

START Winter 2022

COMPLETION Winter 2024

DETAILS This project consists of the construction and the replacement of electrical, mechanical, structure, process, and piping components in the facility.


MAPProject Map



General Project Information

What is the purpose of this project?

This project is part of the City’s ongoing program to improve inefficient components of the existing wastewater treatment plant facilities.

How long is this project going to take to complete?
23 months (700 calendar days). Work is scheduled to begin in Winter 2022 and is anticipated to be completed in Winter 2024. The project schedule depends upon weather conditions.


Have More Questions? Click here for more answers

PROJECT NUMBER R-000298-0014

LOCATION Refer to Project Map

COUNCIL DISTRICT D

BUDGET $21,210,192

TYPE Wastewater

START Winter 2022

COMPLETION Winter 2024

DETAILS This project consists of the construction and the replacement of electrical, mechanical, structure, process, and piping components in the facility.


MAPProject Map



General Project Information

What is the purpose of this project?

This project is part of the City’s ongoing program to improve inefficient components of the existing wastewater treatment plant facilities.

How long is this project going to take to complete?
23 months (700 calendar days). Work is scheduled to begin in Winter 2022 and is anticipated to be completed in Winter 2024. The project schedule depends upon weather conditions.


Have More Questions? Click here for more answers

  • Latest News

    Share Latest News on Facebook Share Latest News on Twitter Share Latest News on Linkedin Email Latest News link

    The completion percentage is 70%, and the anticipated completion date is Summer 2024.

  • Latest News

    Share Latest News on Facebook Share Latest News on Twitter Share Latest News on Linkedin Email Latest News link

    The project is currently 40% completed in place, which includes the installation of storm drains. Current construction activities include the installation of the Electrical duct bank and Acoustical panels in the blower building.

  • Latest News

    Share Latest News on Facebook Share Latest News on Twitter Share Latest News on Linkedin Email Latest News link

    Contractor is on site installing the 36-inch storm sewer manhole.

Page last updated: 02 Apr 2024, 01:00 PM