DETAILS This project consists of the construction of the Alief Village and Bell Park #2 Lift Station Diversions. The Alief Village Lift Station Diversion includes the demolition and abandonment of the lift station, construction of 10-inch, 12-inch, 15-inch, and 24-inch gravity wastewater lines by open-cut and micro tunnel construction. The Diversion also includes removal and replacement of approximately 5,400 square yards of concrete pavement. The Belle Park #2 Lift Station diversion includes the demolition and abandonment of the lift station, construction of 18-inch gravity wastewater lines by micro tunnel construction, and concrete pavement replacement.
MAP
General Project Information
What is the purpose of this project? The project is for the construction of the Alief Village and Belle Park #2 Lift Station Diversions.
How long is this project going to take to complete? 20 months (600 calendar days). Work is scheduled to begin in Winter 2023 and anticipated to be completed in Fall 2024. The project schedule will depend on weather conditions. Please see the phasing map for details.
DETAILS This project consists of the construction of the Alief Village and Bell Park #2 Lift Station Diversions. The Alief Village Lift Station Diversion includes the demolition and abandonment of the lift station, construction of 10-inch, 12-inch, 15-inch, and 24-inch gravity wastewater lines by open-cut and micro tunnel construction. The Diversion also includes removal and replacement of approximately 5,400 square yards of concrete pavement. The Belle Park #2 Lift Station diversion includes the demolition and abandonment of the lift station, construction of 18-inch gravity wastewater lines by micro tunnel construction, and concrete pavement replacement.
MAP
General Project Information
What is the purpose of this project? The project is for the construction of the Alief Village and Belle Park #2 Lift Station Diversions.
How long is this project going to take to complete? 20 months (600 calendar days). Work is scheduled to begin in Winter 2023 and anticipated to be completed in Fall 2024. The project schedule will depend on weather conditions. Please see the phasing map for details.