Westpark Drive

Share Westpark Drive on Facebook Share Westpark Drive on Twitter Share Westpark Drive on Linkedin Email Westpark Drive link

PROJECT NUMBER N-000815-0001

LOCATION Refer to map

COUNCIL DISTRICT F

BUDGET $22,257,934

TYPE Street

START Fall 2022

COMPLETION Summer 2024

DETAILS Design and construction for concrete paving with storm drainage, curbs, sidewalks, driveways, street lighting, and necessary underground utilities.


MAP

Project Map


General Project Information

What is the purpose of this project?
This project is designed to improve safety and mobility along Westpark Drive.


Have More Questions? Click here for more answers.

PROJECT NUMBER N-000815-0001

LOCATION Refer to map

COUNCIL DISTRICT F

BUDGET $22,257,934

TYPE Street

START Fall 2022

COMPLETION Summer 2024

DETAILS Design and construction for concrete paving with storm drainage, curbs, sidewalks, driveways, street lighting, and necessary underground utilities.


MAP

Project Map


General Project Information

What is the purpose of this project?
This project is designed to improve safety and mobility along Westpark Drive.


Have More Questions? Click here for more answers.

Frequently Asked Questions

GENERAL PROJECT INFORMATION

Q What is the purpose of this project?
A The purpose of the project is to eliminate two transitions from 2-lanes to 4-lanes and complete the drive as planned to a 4-lane boulevard with divided median with mix of shared path and on-street bike path in the existing right-of-way. Traffic signal replacements are proposed. The project also improves street conveyance and sheet flow by providing in-line detention, as needed, for mitigation.


Q What is going to be replaced/installed in this project?
A The scope of this project is for construction of Westpark Drive Paving and Drainage Improvements from Wilcrest to Dairy Ashford and includes the installation of new storm sewer, storm sewer leads, storm manholes, junction boxes, inlets and related appurtenances within City right-of-way throughout the project limits as identified in the Contract Drawings. This project also includes replacing and constructing street pavement, driveways, curbs, sidewalks, shared use path, wheelchair ramps, permanent signs, pavement marking, streetlights, traffic signal, water lines and services, and related appurtenances throughout the project limits


Q How long is this project going to take to complete?
A 20 months (630 calendar days). Work is scheduled to begin in Fall 2022 and anticipated to be completed in Summer 2024. The project schedule will depend on weather conditions.


SIDEWALKS, TREES & LIGHTING

Q Will there be Street Light Poles installed?
A Yes.


Q What trees are being removed?
A The Tree Protection Plan identifies the trees to be removed, which includes the removal of diseased or dying trees. The City of Houston identifies trees that can be preserved on a case-by-case basis.


CONSTRUCTION

Q At some point, will my utilities be affected?
A Yes, you will lose water for a short period of time when the contractor is making waterline reconnections. Contractor will provide notice 72 hours in advance.


Q Will this project cause traffic/mobility issues (lane closures, increase of trucks in the area, etc.)?
A Yes, one lane closure and local access signs will be placed throughout the project site. Flaggers will be present to direct traffic during construction. Attached are the traffic control plans.


Q Are they going to dig up the front area or just the street?
A Both. The project will involve removing and replacing entire pavement and installing new sidewalks at certain locations all inside City of Houston Right of Way. No work is planned on individual (private) property.


CONTACT INFORMATION

NON-EMERGENCY NEEDS
Dial 311 - Mention to the operator the following 3 things along with your issue:
- Project number: N-000815-0001-4
- Westpark Paving and Drainage
- Refer the questions/comments to Capital Projects

EMERGENCY NEEDS
Contact Contractor or the 24-hour contact provided by the contractor.

Contractor
Reytec Construction Resources, Inc.
Daniel Bonilla – Project Manager 915-497-6041

Houston Public Works
Fernando Gallegos – Inspector 713.817.5283
Bashar Khalil – Project Manager 832.395.2241


HELPFUL LINKS

PROJECT SPECIFIC CONCERNS
Buildforward@houstontx.gov

GENERAL CONCERNS
3-1-1 or 713.837.0311
www.houston311.org

You need to be signed in to comment in this Guest Book. Click here to Sign In or Register to get involved
Page last updated: 08 Oct 2024, 02:34 PM