This project is approximately 83% complete. The waterline and storm water system are 99% complete. Just a few touch ups to the storm system to reach 100% completion. All the eastbound pavement has been completed. Westbound pavement rehab and widening is approximately 70% complete. Total sidewalk and shared-use path are approximately 80% complete. Traffic signal installations are 80% complete. Possible delay in street light completion but still on schedule for project completion.