Westpark Paving and Drainage

Share on Facebook Share on Twitter Share on Linkedin Email this link

PROJECT NUMBER N-000815-0001

LOCATION From Wilcrest Drive to South Dairy Ashford

COUNCIL DISTRICT F

BUDGET $22,257,934

TYPE Paving and Drainage

START Fall 2022

COMPLETION Summer 2024

DETAILS Design and construction for concrete paving with storm drainage, curbs, sidewalks, driveways, street lighting, and necessary underground utilities.


MAP

Project Map


What is the purpose of this project?
This project is designed to improve safety and mobility along Westpark Drive.

How long is the project going to take?
20 months (630 calendar days). Work is scheduled to begin in Fall 2022 and is anticipated to be completed in Summer 2024. The project schedule depends upon weather conditions.

Have More Questions? Click here for more answers

PROJECT NUMBER N-000815-0001

LOCATION From Wilcrest Drive to South Dairy Ashford

COUNCIL DISTRICT F

BUDGET $22,257,934

TYPE Paving and Drainage

START Fall 2022

COMPLETION Summer 2024

DETAILS Design and construction for concrete paving with storm drainage, curbs, sidewalks, driveways, street lighting, and necessary underground utilities.


MAP

Project Map


What is the purpose of this project?
This project is designed to improve safety and mobility along Westpark Drive.

How long is the project going to take?
20 months (630 calendar days). Work is scheduled to begin in Fall 2022 and is anticipated to be completed in Summer 2024. The project schedule depends upon weather conditions.

Have More Questions? Click here for more answers

  • August 2023 Update

    Share on Facebook Share on Twitter Share on Linkedin Email this link

    The project is approximately 60% complete. The water line and storm sewer are at 95% complete, and all concrete has been poured for the new east bound pavement. Anticipate traffic switch to the new pavement in the next two weeks. The contractor will start working on the north part of Westpark Dr. (West Bound). This portion of the project will only involve pavement rehabilitation and not complete road replacement. No change to the targeted completion date.

  • April 2023 Update

    Share on Facebook Share on Twitter Share on Linkedin Email this link

    Project is approximately 35% completed in place. Contractor working to complete installing water lines and continuing the installing of storm water lines and paving work.

  • March 2023 Update

    Share on Facebook Share on Twitter Share on Linkedin Email this link

    This upcoming Monday, 3/20/2023 we are going to be crossing Shadow Place Drive to install the drainage boxes at the median. This is anticipated to take two days, depending on weather conditions and any unforeseen circumstances. We are going to first shut down the southwest entrance on the first day, and on the second day the southeast corner based on Contractor’s plan.

  • January 2023 Update

    Share on Facebook Share on Twitter Share on Linkedin Email this link

    Residents of the Shadow Lake Estates, installation of the 6’x4’ Reinforced Concrete Boxes (new drainage trunk line) in the vicinity of the Shadow Place Drive and Westpark Drive intersection will start the week of 1/9/23. The Construction will include the area located between W Houston Center Blvd on the east and Harris County Flood Control Ditch on the west side of the project, which includes the subdivision entrance. Construction will be approaching Shadow Lake Estate entrance toward the end of the week of 1/9/23.

Page last updated: 20 Sep 2023, 01:27 PM