Westpark Paving and Drainage
PROJECT NUMBER N-000815-0001
LOCATION From Wilcrest Drive to South Dairy Ashford
COUNCIL DISTRICT F
BUDGET $22,257,934
TYPE Paving and Drainage
START Fall 2022
COMPLETION Summer 2024
DETAILS Design and construction for concrete paving with storm drainage, curbs, sidewalks, driveways, street lighting, and necessary underground utilities.
MAP
What is the purpose of this project? This project is designed to improve safety and mobility along Westpark Drive. | |
How long is the project going to take? 20 months (630 calendar days). Work is scheduled to begin in Fall 2022 and is anticipated to be completed in Summer 2024. The project schedule depends upon weather conditions. |
Have More Questions? Click here for more answers
PROJECT NUMBER N-000815-0001
LOCATION From Wilcrest Drive to South Dairy Ashford
COUNCIL DISTRICT F
BUDGET $22,257,934
TYPE Paving and Drainage
START Fall 2022
COMPLETION Summer 2024
DETAILS Design and construction for concrete paving with storm drainage, curbs, sidewalks, driveways, street lighting, and necessary underground utilities.
MAP
What is the purpose of this project? This project is designed to improve safety and mobility along Westpark Drive. | |
How long is the project going to take? 20 months (630 calendar days). Work is scheduled to begin in Fall 2022 and is anticipated to be completed in Summer 2024. The project schedule depends upon weather conditions. |
Have More Questions? Click here for more answers
-
Latest News
Share on Facebook Share on Twitter Share on Linkedin Email this linkThis project is approximately 83% complete. The waterline and storm water system are 99% complete. Just a few touch ups to the storm system to reach 100% completion. All the eastbound pavement has been completed. Westbound pavement rehab and widening is approximately 70% complete. Total sidewalk and shared-use path are approximately 80% complete. Traffic signal installations are 80% complete. Possible delay in street light completion but still on schedule for project completion.
-
Latest News
Share on Facebook Share on Twitter Share on Linkedin Email this linkThe project is approximately 67% complete. The waterline and storm sewer are 99% complete, and all the concrete pavement on the new eastbound has been completed. Total sidewalk and shared-use path at 50% complete. Traffic switches were supposed to be done last month, but an unforeseen storm sewer pipe conflict delayed the completion of the Wilcrest Dr Intersection. Traffic will be switched to the new pavement on the south (eastbound) part of the road, and the Contractor will begin working on the north part (westbound) of Westpark starting the second week of October. On this side of the project, only the existing pavement from S Dairy Ashford to W Houston Center will be completely replaced, and only pavement rehabilitation will be done for the rest of the project near Gallant Bend. We are expecting a faster construction to this portion of the project for it is not as complex as the south portion, which involved water line and storm sewer installation. No change to the targeted completion date.
-
Latest News
Share on Facebook Share on Twitter Share on Linkedin Email this linkThe project is approximately 60% complete. The water line and storm sewer are at 95% complete, and all concrete has been poured for the new east bound pavement. Anticipate traffic switch to the new pavement in the next two weeks. The contractor will start working on the north part of Westpark Dr. (West Bound). This portion of the project will only involve pavement rehabilitation and not complete road replacement. No change to the targeted completion date.
-
Latest News
Share on Facebook Share on Twitter Share on Linkedin Email this linkProject is approximately 35% completed in place. Contractor working to complete installing water lines and continuing the installing of storm water lines and paving work.
-
Latest News
Share on Facebook Share on Twitter Share on Linkedin Email this linkThis upcoming Monday, 3/20/2023 we are going to be crossing Shadow Place Drive to install the drainage boxes at the median. This is anticipated to take two days, depending on weather conditions and any unforeseen circumstances. We are going to first shut down the southwest entrance on the first day, and on the second day the southeast corner based on Contractor’s plan.
Follow Project
Project Phase
Documents
- Meeting Materials
-
Construction Materials
- Construction Phasing Map 1 of 2 (1.65 MB) (pdf)
- Construction Phasing Map 2 of 2 (1.26 MB) (pdf)
- Proposed Improvements 1 of 2 (35.6 MB) (pdf)
- Proposed Improvements 2 of 2 (28.7 MB) (pdf)
- Required Design Features Exhibit 1 of 2 (75.7 MB) (pdf)
- Required Design Features Exhibit 2 of 2 (55.1 MB) (pdf)
- Tree Removal and Replacement Exhibit 1 of 2 (75.8 MB) (pdf)
- Tree Removal and Replacement Exhibit 2 of 2 (57.1 MB) (pdf)
- Typical Sections (2.33 MB) (pdf)
- Plans
- Exhibits
-
Reports
- Archeological Backgound Study (31.5 MB) (pdf)
- Biology Tier 1 Analysis (260 KB) (pdf)
- Community Impacts Assessment (5.61 MB) (pdf)
- Hazardous Materials Initial Site Assessment (78.9 MB) (pdf)
- Historical Resources (193 KB) (pdf)
- Noise Analysis Technical Report (9.65 MB) (pdf)
- Species Analysis (7.48 MB) (pdf)
- Surface Water Analysis (494 KB) (pdf)
- Waters of the U.S. Delineation Report (53.6 MB) (pdf)
-
Design Materials
- Handout - English (729 KB) (pdf)
- Handout - Spanish (736 KB) (pdf)
- Notice of Virtual Public Hearing March 23, 2021 (157 KB) (pdf)
- Notice of Virtual Public Hearing - Spanish March 23, 2021 (158 KB) (pdf)
- Powerpoint Presentation - English (8.32 MB) (pdf)
- Powerpoint Presentation - Spanish (8.45 MB) (pdf)
- Westpark Comment Form (273 KB) (pdf)
Who's Listening?
Public Engagement Team
Email Us: | Engage@houstontx.gov |