Westpark Paving and Drainage

Share on Facebook Share on Twitter Share on Linkedin Email this link

PROJECT NUMBER N-000815-0001

LOCATION From Wilcrest Drive to South Dairy Ashford

COUNCIL DISTRICT F

BUDGET $22,257,934

TYPE Paving and Drainage

START Fall 2022

COMPLETION Summer 2024

DETAILS Design and construction for concrete paving with storm drainage, curbs, sidewalks, driveways, street lighting, and necessary underground utilities.



MAP

Project Map



What is the purpose of this project?
This project is designed to improve safety and mobility along Westpark Drive.
How long is the project going to take?
20 months (630 calendar days). Work is scheduled to begin in Fall 2022 and is anticipated to be completed in Summer 2024. The project schedule depends upon weather conditions.

Have More Questions? Click here for more answers

PROJECT NUMBER N-000815-0001

LOCATION From Wilcrest Drive to South Dairy Ashford

COUNCIL DISTRICT F

BUDGET $22,257,934

TYPE Paving and Drainage

START Fall 2022

COMPLETION Summer 2024

DETAILS Design and construction for concrete paving with storm drainage, curbs, sidewalks, driveways, street lighting, and necessary underground utilities.



MAP

Project Map



What is the purpose of this project?
This project is designed to improve safety and mobility along Westpark Drive.
How long is the project going to take?
20 months (630 calendar days). Work is scheduled to begin in Fall 2022 and is anticipated to be completed in Summer 2024. The project schedule depends upon weather conditions.

Have More Questions? Click here for more answers

Is there anything you want us to know?

You need to be signed in to add your question.

  • Share on Facebook Share on Twitter Share on Linkedin Email this link

    Is there a step by step timeline for the completion of this project, specifying how long each phase is going to take to be completed?

    nirav.mandhani asked about 1 month ago

    Thank you for your question. For more information regarding the project phases please refer to the construction phasing maps located in the construction folder under the documents section of the project webpage.

  • Share on Facebook Share on Twitter Share on Linkedin Email this link

    Will the south side of Westpark between Kirkwood and Wilcrest have trees planted similar to the north side of Westpark?

    Jofayc asked 4 months ago

    Howdy Neighbor! Trees will be mostly re-planted in the median section inside the project limits. City of Houston Forestry group will be the last people to make the final decision on where to plant the new trees. As of current, there is no trees shown on the plans on the south side of the Westpark between Kirckwood and Wilcrest. 


  • Share on Facebook Share on Twitter Share on Linkedin Email this link

    What impact will there be on the Westpark cross streets for Dairy Ashford and West Houston Blvd. The traffic patterns indicate reducing to 2 lanes at Westpark crossing. Is this correct

    adkeller asked 5 months ago

    Howdy Neighbor! Dairy Ashford and Wilcrest will be reduced to 2 lanes for the duration of the intersection reconstruction, not the duration of the project. It is expected that the reduction in the number of lanes will last 2-4 months, depending on the contractor’s schedule.


    "

  • Share on Facebook Share on Twitter Share on Linkedin Email this link

    Will the existing Westpark street concrete be replaced between West Houston Center and Dairyashford?

    Hoasam asked 6 months ago

    Yes, The Westpark Street. concrete pavement will be replaced in its entirety between Dairy Ashford Road and West Houston Center Boulevard.

  • Share on Facebook Share on Twitter Share on Linkedin Email this link

    Can you post a replay of the Westpark virtual meeting on your website

    adkeller asked 7 months ago

    Hello, the recording from the meeting has been uploaded to the project page and can also be found on YouTube. Here is the link: https://youtu.be/p335ASFpaVY

  • Share on Facebook Share on Twitter Share on Linkedin Email this link

    Will you please add a traffic light at Shadowbriar and Westpark. It has become a busy intersection because of school busses and parents cards, turning into Shadowbriar to serve the Outley Elementary School. Westpark Drive is also a major artery for people going east or west to get to Westpark tollway through W. Houston and to Beltway 8

    TheoinTX asked 8 months ago

    Thank you for your question. The Transportation and Drainage operation will re-evaluate the need for signal at Shadowbriar after the completion of the construction of Westpark.

  • Share on Facebook Share on Twitter Share on Linkedin Email this link

    These is a one time opportunity to remove the electrical poles and bury those ugly cables. Over 90% of any digging would be on unimproved raw land. What needs to be done to get this done? .

    Hoasam asked 8 months ago
    These overhead power poles have discussed with CenterPoint Energy during utilities coordination meetings and to bury these overhead lines into underground will cost tremendously to CenterPoint Energy. Currently, they have no plans to bury them. They will remain overhead. Any additional questions regarding these power poles and overhead lines need to be referred to CenterPoint Energy.
  • Share on Facebook Share on Twitter Share on Linkedin Email this link

    So it's now late June, 2022. Any update?

    joeleaza1 asked 8 months ago

    Hello, Thank you for your question. The contractor is expected to mobilize to the area June 29, 2022. We are also hosting a virtual community meeting on June 28, 2022 at 5:30 PM. Please join us to get more information about the project, meet the project team and get your questions answered by the experts. The meeting link is located on the project page. Hope you can join us. Thank you.

  • Share on Facebook Share on Twitter Share on Linkedin Email this link

    Is there a more specific date when construction will start

    adkeller asked 10 months ago

    Thank you for your question. We are trying our best to get the project awarded to a contractor by end of May 2022. If it is awarded by that date then construction will begin Summer (July-Sept.) of 2022.

Page last updated: 02 Feb 2023, 12:22 PM