Westpark Drive

Share Westpark Drive on Facebook Share Westpark Drive on Twitter Share Westpark Drive on Linkedin Email Westpark Drive link

PROJECT NUMBER N-000815-0001

LOCATION Refer to map

COUNCIL DISTRICT F

BUDGET $22,257,934

TYPE Street

START Fall 2022

COMPLETION Summer 2024

DETAILS Design and construction for concrete paving with storm drainage, curbs, sidewalks, driveways, street lighting, and necessary underground utilities.


MAP

Project Map


General Project Information

What is the purpose of this project?
This project is designed to improve safety and mobility along Westpark Drive.


Have More Questions? Click here for more answers.

PROJECT NUMBER N-000815-0001

LOCATION Refer to map

COUNCIL DISTRICT F

BUDGET $22,257,934

TYPE Street

START Fall 2022

COMPLETION Summer 2024

DETAILS Design and construction for concrete paving with storm drainage, curbs, sidewalks, driveways, street lighting, and necessary underground utilities.


MAP

Project Map


General Project Information

What is the purpose of this project?
This project is designed to improve safety and mobility along Westpark Drive.


Have More Questions? Click here for more answers.

  • Latest News

    Share Latest News on Facebook Share Latest News on Twitter Share Latest News on Linkedin Email Latest News link

    The project team is diligently working to ensure timely completion! We're excited to announce that in collaboration with CenterPoint Energy, we'll be installing new streetlights next month, July 2024. Be the first to know all the latest updates by subscribing to our project page and receiving email notifications. Stay tuned for more exciting news!

  • Latest News

    Share Latest News on Facebook Share Latest News on Twitter Share Latest News on Linkedin Email Latest News link

    Completed work

    • All Paving, sidewalks, curbs, ramps, driveways, and retaining walls are complete.
    • All underground utility installations, including waterlines, fire hydrants, and stormwater, are complete.


    Minor items remaining

    • Cycle lane separators.
    • Streetlights.
    • Traffic Signals.
    • Pavement striping.
    • Tree planting.
    • Hydro mulch (once trees are completed, hydro-mulch will take place)
    • Continue general cleanup & restoration.
  • Latest News

    Share Latest News on Facebook Share Latest News on Twitter Share Latest News on Linkedin Email Latest News link

    This project is approximately 83% complete. The waterline and storm water system are 99% complete. Just a few touch ups to the storm system to reach 100% completion. All the eastbound pavement has been completed. Westbound pavement rehab and widening is approximately 70% complete. Total sidewalk and shared-use path are approximately 80% complete. Traffic signal installations are 80% complete. Possible delay in street light completion but still on schedule for project completion.

  • Latest News

    Share Latest News on Facebook Share Latest News on Twitter Share Latest News on Linkedin Email Latest News link

    The project is approximately 67% complete. The waterline and storm sewer are 99% complete, and all the concrete pavement on the new eastbound has been completed. Total sidewalk and shared-use path at 50% complete. Traffic switches were supposed to be done last month, but an unforeseen storm sewer pipe conflict delayed the completion of the Wilcrest Dr Intersection. Traffic will be switched to the new pavement on the south (eastbound) part of the road, and the Contractor will begin working on the north part (westbound) of Westpark starting the second week of October. On this side of the project, only the existing pavement from S Dairy Ashford to W Houston Center will be completely replaced, and only pavement rehabilitation will be done for the rest of the project near Gallant Bend. We are expecting a faster construction to this portion of the project for it is not as complex as the south portion, which involved water line and storm sewer installation. No change to the targeted completion date.

  • Latest News

    Share Latest News on Facebook Share Latest News on Twitter Share Latest News on Linkedin Email Latest News link

    The project is approximately 60% complete. The water line and storm sewer are at 95% complete, and all concrete has been poured for the new east bound pavement. Anticipate traffic switch to the new pavement in the next two weeks. The contractor will start working on the north part of Westpark Dr. (West Bound). This portion of the project will only involve pavement rehabilitation and not complete road replacement. No change to the targeted completion date.

  • Latest News

    Share Latest News on Facebook Share Latest News on Twitter Share Latest News on Linkedin Email Latest News link

    Project is approximately 35% completed in place. Contractor working to complete installing water lines and continuing the installing of storm water lines and paving work.

  • Latest News

    Share Latest News on Facebook Share Latest News on Twitter Share Latest News on Linkedin Email Latest News link

    This upcoming Monday, 3/20/2023 we are going to be crossing Shadow Place Drive to install the drainage boxes at the median. This is anticipated to take two days, depending on weather conditions and any unforeseen circumstances. We are going to first shut down the southwest entrance on the first day, and on the second day the southeast corner based on Contractor’s plan.