The project is approximately 60% complete. The water line and storm sewer are at 95% complete, and all concrete has been poured for the new east bound pavement. Anticipate traffic switch to the new pavement in the next two weeks. The contractor will start working on the north part of Westpark Dr. (West Bound). This portion of the project will only involve pavement rehabilitation and not complete road replacement. No change to the targeted completion date.