Water Line Replacement in Midtown Area and Winlow Place, Dearborn Place, Montlew Place, and Lancaster Subdivisions

Share Water Line Replacement in Midtown Area and Winlow Place, Dearborn Place, Montlew Place, and Lancaster Subdivisions on Facebook Share Water Line Replacement in Midtown Area and Winlow Place, Dearborn Place, Montlew Place, and Lancaster Subdivisions on Twitter Share Water Line Replacement in Midtown Area and Winlow Place, Dearborn Place, Montlew Place, and Lancaster Subdivisions on Linkedin Email Water Line Replacement in Midtown Area and Winlow Place, Dearborn Place, Montlew Place, and Lancaster Subdivisions link

Project Overview

Council District: C

Project Number:S-000035-0269

Estimated Budget: $48,000,000

Start: Winter 2025

Completion: Summer 2026



Project Impact Area

Project Map


Community Feedback

Have questions or feedback about this project? Email us at engage@houstontx.gov or call 311.

Project Overview

Council District: C

Project Number:S-000035-0269

Estimated Budget: $48,000,000

Start: Winter 2025

Completion: Summer 2026



Project Impact Area

Project Map


Community Feedback

Have questions or feedback about this project? Email us at engage@houstontx.gov or call 311.

  • Latest News

    Share Latest News on Facebook Share Latest News on Twitter Share Latest News on Linkedin Email Latest News link

    The project is progressing well! Restoration work is underway along Westheimer, West Alabama, South Shepherd, and Dunlavy, with additional work beginning in the Midtown area bounded by McGowen, Winbern, Albany, and Main. The project remains on schedule for completion by Summer 2026.

  • Latest News

    Share Latest News on Facebook Share Latest News on Twitter Share Latest News on Linkedin Email Latest News link

    The project is progressing well! Contractors are actively restoring Westheimer, West Alabama, South Shepherd, and Dunlavy, including replacing street pavement and repairing curbs. Once this work is completed, crews will begin landscaping. We’re pleased to report that the project remains on schedule for completion by Summer 2026.

Page last updated: 30 Mar 2026, 09:12 AM