Tree Lane Bridge Rehabilitation

Share Tree Lane Bridge Rehabilitation on Facebook Share Tree Lane Bridge Rehabilitation on Twitter Share Tree Lane Bridge Rehabilitation on Linkedin Email Tree Lane Bridge Rehabilitation link

PROJECT NUMBER N-320445-0008

LOCATION Refer to map

COUNCIL DISTRICT E

BUDGET $909,000

TYPE Street

START Spring 2024

COMPLETION Fall 2024

DETAILS Due to rip rap failures under the bridge, the channels and columns have been exposed to severe scour/erosion, and repairs are needed. This can lead to access, safety, health, and the well-being of the citizens. The channel condition of this bridge is a major contributor to the flooding of Ben’s Branch natural stream. This bridge rehabilitation is an immediate improvement for flood prevention and protection of the citizens in the Kingwood area.


MAPProject Map


General Project Information

What is the purpose of this project?
The purpose is to rehab a critical City of Houston infrastructure asset to protect the health and safety of residents.


Have More Questions? Click here for more answers.

PROJECT NUMBER N-320445-0008

LOCATION Refer to map

COUNCIL DISTRICT E

BUDGET $909,000

TYPE Street

START Spring 2024

COMPLETION Fall 2024

DETAILS Due to rip rap failures under the bridge, the channels and columns have been exposed to severe scour/erosion, and repairs are needed. This can lead to access, safety, health, and the well-being of the citizens. The channel condition of this bridge is a major contributor to the flooding of Ben’s Branch natural stream. This bridge rehabilitation is an immediate improvement for flood prevention and protection of the citizens in the Kingwood area.


MAPProject Map


General Project Information

What is the purpose of this project?
The purpose is to rehab a critical City of Houston infrastructure asset to protect the health and safety of residents.


Have More Questions? Click here for more answers.

  • Latest News

    Share Latest News on Facebook Share Latest News on Twitter Share Latest News on Linkedin Email Latest News link

    Due to some unforeseen circumstances, the project completion has changed to Fall 2024. Please note that bridge traffic flow will remain unblocked from 7AM-9AM and 3PM-6PM Monday thru Friday to minimize disruption.

  • Latest News

    Share Latest News on Facebook Share Latest News on Twitter Share Latest News on Linkedin Email Latest News link

    The Tree Lane Bridge Rehabilitation project will begin in the Spring 2024 and is anticipated to be completed in the Summer 2024.

  • Latest News

    Share Latest News on Facebook Share Latest News on Twitter Share Latest News on Linkedin Email Latest News link

    Project update regarding upcoming bridge construction:

    • Adjacent land area will be closed off with a construction fence.
    • One lane of traffic near the bridge may be closed intermittently, with the bridge remaining fully open during peak hours.
    • Detailed logistics and safety plans are being developed with the contractor.
    • Construction is anticipated to start in March or early April, subject to various factors such as material procurement.
    • The adjacent sidewalk may also be closed, pending finalization of safety measures with the contractor.

    Additionally:

    • Design phase is completed.
    • Construction is scheduled to start in Winter 2024, aiming for completion by Summer 2024.
    • Anticipate minimal traffic delays during construction.

    Remember to subscribe to this page to receive the latest and greatest updates as they become available!

  • Latest News

    Share Latest News on Facebook Share Latest News on Twitter Share Latest News on Linkedin Email Latest News link

    The design phase is complete. The expected construction start date is Winter 2024, with completion in Summer 2024. One lane of traffic is expected to be closed on an as-needed basis near the bridge. Minimal delays can be expected. Please subscribe to this page to receive project updates as they become available.