TIRZ 17 Memorial City Area Detention Basin

Share TIRZ 17 Memorial City Area Detention Basin on Facebook Share TIRZ 17 Memorial City Area Detention Basin on Twitter Share TIRZ 17 Memorial City Area Detention Basin on Linkedin Email TIRZ 17 Memorial City Area Detention Basin link
BOONE AND HACKBERRY

Project Overview

Council District: G

Project Number: M-430296-0017

Estimated Budget: $75,000,000

Start: Winter 2027

Completion: Summer 2028





Project Impact Area




Community Feedback

Have questions or feedback about this project? Email us at engage@houstontx.gov or call 311.


Project Overview

Council District: G

Project Number: M-430296-0017

Estimated Budget: $75,000,000

Start: Winter 2027

Completion: Summer 2028





Project Impact Area




Community Feedback

Have questions or feedback about this project? Email us at engage@houstontx.gov or call 311.


What’s your question for the project team?

Email
loader image
Didn't receive confirmation?
Seems like you are already registered, please provide the password. Forgot your password? Create a new one now.
  • Share Hello. What is the updated cost for this project and who is funding? Also, can you please attach rendering/ diagram of basin which has been provided to the City? Where will basin be constructed in relation to residential property lines/ Attingham Drive/ SBMSA fields? Thank you! on Facebook Share Hello. What is the updated cost for this project and who is funding? Also, can you please attach rendering/ diagram of basin which has been provided to the City? Where will basin be constructed in relation to residential property lines/ Attingham Drive/ SBMSA fields? Thank you! on Twitter Share Hello. What is the updated cost for this project and who is funding? Also, can you please attach rendering/ diagram of basin which has been provided to the City? Where will basin be constructed in relation to residential property lines/ Attingham Drive/ SBMSA fields? Thank you! on Linkedin Email Hello. What is the updated cost for this project and who is funding? Also, can you please attach rendering/ diagram of basin which has been provided to the City? Where will basin be constructed in relation to residential property lines/ Attingham Drive/ SBMSA fields? Thank you! link

    Hello. What is the updated cost for this project and who is funding? Also, can you please attach rendering/ diagram of basin which has been provided to the City? Where will basin be constructed in relation to residential property lines/ Attingham Drive/ SBMSA fields? Thank you!

    Amej asked 13 days ago

    Ready...Set...ENGAGE!


    Thank you for reaching out with your questions regarding the project.

    Project cost and funding information can be found in the public meeting presentation available on the project Engage Houston webpage:

    TIRZ 17 Memorial Area Detention Basin Project Page

    (Located on the right side of the webpage under “Documents & Downloads.”)

    The project is funded through a grant from the Federal Emergency Management Agency (FEMA), along with local sponsors including TIRZ 17 Memorial City Redevelopment Authority and the Harris County Flood Control District (HCFCD). Harris County Precinct 3 has also been supportive of the project, including HCFCD funding participation.

    The underground detention basin will be constructed on the Memorial Middle School property, east of Attingham Drive, in the northern portion of the property beneath the current location of the SBMSA baseball fields.

    Additionally, a project location map and basin drawing/rendering are included in the public meeting presentation available on the Engage Houston project webpage linked above.


    Regards,

    The Engage Houston Team

  • Share Hello, can you please provide exact plans about widening streets in the memorial meadows areas. The plans and rendering do not show exact impact on the street. I would like to see exact plans on which streets will be widened and which parts of the streets. Can you specifically share for Kingsride, benignus, vindon? on Facebook Share Hello, can you please provide exact plans about widening streets in the memorial meadows areas. The plans and rendering do not show exact impact on the street. I would like to see exact plans on which streets will be widened and which parts of the streets. Can you specifically share for Kingsride, benignus, vindon? on Twitter Share Hello, can you please provide exact plans about widening streets in the memorial meadows areas. The plans and rendering do not show exact impact on the street. I would like to see exact plans on which streets will be widened and which parts of the streets. Can you specifically share for Kingsride, benignus, vindon? on Linkedin Email Hello, can you please provide exact plans about widening streets in the memorial meadows areas. The plans and rendering do not show exact impact on the street. I would like to see exact plans on which streets will be widened and which parts of the streets. Can you specifically share for Kingsride, benignus, vindon? link

    Hello, can you please provide exact plans about widening streets in the memorial meadows areas. The plans and rendering do not show exact impact on the street. I would like to see exact plans on which streets will be widened and which parts of the streets. Can you specifically share for Kingsride, benignus, vindon?

    Stephane asked 17 days ago

    Ready...Set...ENGAGE!


    The project will reconstruct the following streets as described:  full width of Barryknoll Lane from west of Betina to Gessner Road; only the far east side of the northbound lane on Gessner Road from Barryknoll Lane to Kingsride Lane and a roughly 60' full width of Gessner in line with the eastbound lanes of Kingsride Lane; full width of Kingsride Lane from Gessner Road west to the dead end at Memorial Middle School.  Then, in regards to street widening (roadway pavement):  Barryknoll Lane two west bound lanes will be widened from 10 ft to 11 ft each while the two eastbound lanes remain the same 10 ft width; Gessner Road lanes will not be widened; Kingsride Lane will not be widened.  Also, the project will have limited work (typically outside of the curb line) along Vindon Drive from the Memorial Middle School to Hallie Drive.

    The Engage Houston Team

  • Share Has a subsurface detention project of this size been completed in Houston? If so, can you please detail where? on Facebook Share Has a subsurface detention project of this size been completed in Houston? If so, can you please detail where? on Twitter Share Has a subsurface detention project of this size been completed in Houston? If so, can you please detail where? on Linkedin Email Has a subsurface detention project of this size been completed in Houston? If so, can you please detail where? link

    Has a subsurface detention project of this size been completed in Houston? If so, can you please detail where?

    AMej asked 21 days ago

    Ready...Set...ENGAGE!

    Thank you for your question.

    Subsurface detention basins have been constructed in Houston and throughout the surrounding region; however, we are not currently aware of any projects of this size that have been completed by Houston Public Works.

    There is a similar, though smaller, reinforced concrete subsurface detention basin that was privately developed near Allen Parkway, east of Montrose Boulevard. While it differs in scale, it reflects the type of approach being used for this project.

    We appreciate your interest and are happy to provide additional information as it becomes available.

    The Engage Houston Team

  • Share What is the surface area in acres and what is the average height. of the detention pond. on Facebook Share What is the surface area in acres and what is the average height. of the detention pond. on Twitter Share What is the surface area in acres and what is the average height. of the detention pond. on Linkedin Email What is the surface area in acres and what is the average height. of the detention pond. link

    What is the surface area in acres and what is the average height. of the detention pond.

    villiewe asked about 2 months ago

    Ready...Set...ENGAGE!

    Thank you for engaging with us regarding the TIRZ 17 Memorial City Area Detention Basin Project.

    Based on the current 90% design plans, the subsurface detention basin is estimated to have a surface area of approximately 9.25 acres and an average height of 10.26 feet, resulting in a total detention volume of about 94.9 acre-feet.

    We hope this information is helpful. Please feel free to reach out if you have any additional questions.

    Sincerely,
    The Engage Houston Team

  • Share Retention ponds have traditional issues from algae which forms long thick arms which combined with sediment reduces flow through pipes Plus all things structural or mechanical break This puts Fonn villas and memorial meadows at new risk for flooding We do not want this at all No one wants this here No one even heard about it until recently. on Facebook Share Retention ponds have traditional issues from algae which forms long thick arms which combined with sediment reduces flow through pipes Plus all things structural or mechanical break This puts Fonn villas and memorial meadows at new risk for flooding We do not want this at all No one wants this here No one even heard about it until recently. on Twitter Share Retention ponds have traditional issues from algae which forms long thick arms which combined with sediment reduces flow through pipes Plus all things structural or mechanical break This puts Fonn villas and memorial meadows at new risk for flooding We do not want this at all No one wants this here No one even heard about it until recently. on Linkedin Email Retention ponds have traditional issues from algae which forms long thick arms which combined with sediment reduces flow through pipes Plus all things structural or mechanical break This puts Fonn villas and memorial meadows at new risk for flooding We do not want this at all No one wants this here No one even heard about it until recently. link

    Retention ponds have traditional issues from algae which forms long thick arms which combined with sediment reduces flow through pipes Plus all things structural or mechanical break This puts Fonn villas and memorial meadows at new risk for flooding We do not want this at all No one wants this here No one even heard about it until recently.

    Donna asked 3 months ago

    Ready...Set...ENGAGE!

    Thank you for sharing your concerns regarding the TIRZ 17 Memorial City Area Detention Basin Project. Protecting surrounding neighborhoods, including Fonn Villas and Memorial Meadows, is a top priority, and this project is specifically designed to help reduce flood risk in the area.

    The proposed detention basin will be located underground and includes several features to help prevent sediment buildup and maintenance issues. A pretreatment chamber will capture and trap dirt and debris before stormwater enters the main storage area, helping the system operate efficiently. The facility will also include an access lid so maintenance crews and equipment can safely perform routine inspections and cleanout.

    The City of Houston will conduct regular maintenance at appropriate intervals, including the use of vacuum trucks to remove accumulated sediment and ensure the system continues to function as designed.

    The basin is engineered to temporarily store stormwater runoff and release it gradually, reducing peak flows during heavy rainfall events and lowering the risk of flooding for nearby communities.

    We appreciate community feedback and remain committed to keeping residents informed as the project progresses.

  • Share Please change this to under mms as this would severely disrupt our neighborhood and widening of Vinson st would help the neighborhood rather than widening a dead end st Kingsride on Facebook Share Please change this to under mms as this would severely disrupt our neighborhood and widening of Vinson st would help the neighborhood rather than widening a dead end st Kingsride on Twitter Share Please change this to under mms as this would severely disrupt our neighborhood and widening of Vinson st would help the neighborhood rather than widening a dead end st Kingsride on Linkedin Email Please change this to under mms as this would severely disrupt our neighborhood and widening of Vinson st would help the neighborhood rather than widening a dead end st Kingsride link

    Please change this to under mms as this would severely disrupt our neighborhood and widening of Vinson st would help the neighborhood rather than widening a dead end st Kingsride

    Donna W asked 4 months ago

    Ready…Set…ENGAGE!


    Thank you for staying engaged regarding the TIRZ 17 Memorial City Area Detention Basin project. Residents have requested that work impacting Kingsride be reconsidered. Widening Bidin or Vinson Street would provide greater benefit to neighborhood traffic flow than widening a dead-end street such as Kingsride.


    - The Engage Houston Team

  • Share We have 3 heritage trees on Kingsride that should not be disturbed Kingsride should not be widened as it is a dead end and is not subject to high traffic flow on Facebook Share We have 3 heritage trees on Kingsride that should not be disturbed Kingsride should not be widened as it is a dead end and is not subject to high traffic flow on Twitter Share We have 3 heritage trees on Kingsride that should not be disturbed Kingsride should not be widened as it is a dead end and is not subject to high traffic flow on Linkedin Email We have 3 heritage trees on Kingsride that should not be disturbed Kingsride should not be widened as it is a dead end and is not subject to high traffic flow link

    We have 3 heritage trees on Kingsride that should not be disturbed Kingsride should not be widened as it is a dead end and is not subject to high traffic flow

    Donna W asked 4 months ago

    Ready…Set…ENGAGE!


    Thank you for staying engaged regarding the TIRZ 17 Memorial City Area Detention Basin project. The project is seeking to limit impacts to trees within the work limits, and the current design does not include tree removal on Kingsride, except near the dead-end side by the school.


    - The Engage Houston Team

  • Share Will the city of houston be responsible for ongoing maintenance and repair as everything mechanical structural eventually breaks on Facebook Share Will the city of houston be responsible for ongoing maintenance and repair as everything mechanical structural eventually breaks on Twitter Share Will the city of houston be responsible for ongoing maintenance and repair as everything mechanical structural eventually breaks on Linkedin Email Will the city of houston be responsible for ongoing maintenance and repair as everything mechanical structural eventually breaks link

    Will the city of houston be responsible for ongoing maintenance and repair as everything mechanical structural eventually breaks

    Donna W asked 4 months ago

    Ready…Set…ENGAGE!

    Thank you for your question regarding the TIRZ 17 Memorial City Area Detention Basin project. The proposed underground detention basin will be maintained by the City of Houston.


    - The Engage Houston Team

  • Share I would like to know if there is ongoing coordination with MetroNational as their mall rebuild will be going on at the same time and traffic will be severely impacted by both of these projects. on Facebook Share I would like to know if there is ongoing coordination with MetroNational as their mall rebuild will be going on at the same time and traffic will be severely impacted by both of these projects. on Twitter Share I would like to know if there is ongoing coordination with MetroNational as their mall rebuild will be going on at the same time and traffic will be severely impacted by both of these projects. on Linkedin Email I would like to know if there is ongoing coordination with MetroNational as their mall rebuild will be going on at the same time and traffic will be severely impacted by both of these projects. link

    I would like to know if there is ongoing coordination with MetroNational as their mall rebuild will be going on at the same time and traffic will be severely impacted by both of these projects.

    4 months ago

    Ready...Set...ENGAGE!

    The City has had contact with MetroNational for this project.  The City’s designer will consider nearby construction projects for their design including any temporary traffic control detours.

    - Engage Houston Team

  • Share If we're going to suffer torn up streets, business access disrupted for whoever knows how long, we need to know the area will be better than we found it. We should improve walking and biking after the road has been resurfaced. I would like to see shared use paths instead of bare minimum sidewalks. on Facebook Share If we're going to suffer torn up streets, business access disrupted for whoever knows how long, we need to know the area will be better than we found it. We should improve walking and biking after the road has been resurfaced. I would like to see shared use paths instead of bare minimum sidewalks. on Twitter Share If we're going to suffer torn up streets, business access disrupted for whoever knows how long, we need to know the area will be better than we found it. We should improve walking and biking after the road has been resurfaced. I would like to see shared use paths instead of bare minimum sidewalks. on Linkedin Email If we're going to suffer torn up streets, business access disrupted for whoever knows how long, we need to know the area will be better than we found it. We should improve walking and biking after the road has been resurfaced. I would like to see shared use paths instead of bare minimum sidewalks. link

    If we're going to suffer torn up streets, business access disrupted for whoever knows how long, we need to know the area will be better than we found it. We should improve walking and biking after the road has been resurfaced. I would like to see shared use paths instead of bare minimum sidewalks.

    4 months ago

    Ready...Set...ENGAGE!

    Roadway reconstruction has been designed to maximize the safety and comfort for sidewalk users. This is being accomplished by offsetting the sidewalk from the roadway curb line per the City’s safety buffer requirements and includes replacement tree plantings, audible pedestrian signals and wheel chair ramps to current standards.

    - Engage Houston Team

Page last updated: 27 Jan 2026, 09:29 AM