Sherwood Lane

Share Sherwood Lane on Facebook Share Sherwood Lane on Twitter Share Sherwood Lane on Linkedin Email Sherwood Lane link

PROJECT NUMBER N-321040-0053

LOCATION Refer to map

COUNCIL DISTRICT A

BUDGET $5,703,466

TYPE Street

START Fall 2023

COMPLETION Summer 2024

DETAILS This project is part of the Roadway Pavement Replacement Program and provides for the reconstruction and rehabilitation of the street along with the repair and improvements to sidewalks, curbs, and curb ramps.


MAP

Project Map


General Project Information


What is the purpose of this project?
This project is part of the Capital Improvement Plan, which replaces the pavement of thoroughfares and collector streets that have deteriorated beyond economical repair and maintenance. This program will improve the quality and safety of pedestrians as well as vehicular mobility.


Have More Questions? Click here for more answers.

PROJECT NUMBER N-321040-0053

LOCATION Refer to map

COUNCIL DISTRICT A

BUDGET $5,703,466

TYPE Street

START Fall 2023

COMPLETION Summer 2024

DETAILS This project is part of the Roadway Pavement Replacement Program and provides for the reconstruction and rehabilitation of the street along with the repair and improvements to sidewalks, curbs, and curb ramps.


MAP

Project Map


General Project Information


What is the purpose of this project?
This project is part of the Capital Improvement Plan, which replaces the pavement of thoroughfares and collector streets that have deteriorated beyond economical repair and maintenance. This program will improve the quality and safety of pedestrians as well as vehicular mobility.


Have More Questions? Click here for more answers.

Frequently Asked Questions

GENERAL PROJECT INFORMATION

Q What is the purpose of this project?
A The purpose is to reconstruct the roadway and sidewalk, regrade the ditches, and replace roadside culverts.


Q What is going to be replaced/installed in this project?
A Work Work in the Sherwood Lane area includes removing existing asphalt pavement and installing new reinforced concrete pavement with slotted curbs. This project does not include any proposed utility work. Current drainage on Sherwood Lane is conveyed via roadside ditches. These roadside ditches will be regraded where necessary to allow for flow through ditch. This project also involves removing and replacing damaged concrete sidewalks. Asphalt and concrete driveways will be replaced with concrete driveways to the right-of-way. Saw cutting and dowels for driveways is incidental to the driveway line item. Bus pads are to be constructed per the location and dimension of the plan and profile sheets with 9” concrete pavement, 4” chairs for reinforcing, expansion joints between 4 1/2” and 9” pavement and require METRO approval before placement of concrete. Mailboxes impacted by construction will be replaced with approval of COH. 


Q How long is this project going to take to complete?
A (270 calendar days). Work is scheduled to begin in Fall 2023 and anticipated to be completed in Fall 2024. The project schedule will depend on weather conditions.


SIDEWALKS, TREES & LIGHTING

Q Will there be Street Light Poles installed?
A Lights will be added to existing wood poles in some circumstances as part of the project



What are my options if I do not want to construct a sidewalk with my project?
A Existing sidewalk will be replaced as part of the project.



Q What trees are being removed?
A No.


CONSTRUCTION

Q At some point, will my utilities be affected?
A No


Q Will this project cause traffic/mobility issues (lane closures, increase of trucks in the area, etc.)?
A Yes, there will be a traffic control plan implemented for closures.




Q Are they going to dig up the front area or just the street?
A Just the Street.




CONTACT INFORMATION

NON-EMERGENCY NEEDS
Dial 311 - Mention to the operator the following 3 things along with your issue:
- Project number: N-321040-0053-4
- Sherwood Lane
- Refer the questions/comments to Capital Projects

EMERGENCY NEEDS
Contact Contractor or the 24-hour contact provided by the contractor.

Contractor
JFT Construction, Inc.
Ismael Hernandez – Superintendent 832.274.1726                                                                                                                                                                                             Pierre Chamoun – Project Manager 832.512.2062

Houston Public Works

Claudius Anyalebechi – Inspector 832.395.6632
Ahmed Siddiqui – Project Manager 832.395.2216


HELPFUL LINKS

PROJECT SPECIFIC CONCERNS
Engage@houstontx.gov

GENERAL CONCERNS
3-1-1 or 713.837.0311
www.houston311.org

You need to be signed in to comment in this Guest Book. Click here to Sign In or Register to get involved
Page last updated: 14 Oct 2024, 11:00 AM