Richmond Plaza (South) Drainage and Paving Improvements

Share Richmond Plaza (South) Drainage and Paving Improvements on Facebook Share Richmond Plaza (South) Drainage and Paving Improvements on Twitter Share Richmond Plaza (South) Drainage and Paving Improvements on Linkedin Email Richmond Plaza (South) Drainage and Paving Improvements link

PROJECT NUMBER M-410023-0001

LOCATION Refer to Project Map

COUNCIL DISTRICT J

BUDGET $18,953,794

TYPE Drainage and Paving

START Winter 2023

COMPLETION Fall 2024

DETAILS Design and construction of stormwater drainage and paving improvements, and necessary utility upgrades.


MAP

Project Map


General Project Information

What is the purpose of this project?
The purpose of the project is to construct storm drainage improvements that address and reduce the risk of structural flooding in the area by improving street conveyance and sheet flow and providing detention, as needed, for mitigation.


How long is this project going to take to complete?

21 months (637 calendar days). Work is scheduled to begin Winter 2023 and anticipated to be completed on Fall 2024. The project schedule depends upon weather conditions.



Have More Questions? Click here for more answers

PROJECT NUMBER M-410023-0001

LOCATION Refer to Project Map

COUNCIL DISTRICT J

BUDGET $18,953,794

TYPE Drainage and Paving

START Winter 2023

COMPLETION Fall 2024

DETAILS Design and construction of stormwater drainage and paving improvements, and necessary utility upgrades.


MAP

Project Map


General Project Information

What is the purpose of this project?
The purpose of the project is to construct storm drainage improvements that address and reduce the risk of structural flooding in the area by improving street conveyance and sheet flow and providing detention, as needed, for mitigation.


How long is this project going to take to complete?

21 months (637 calendar days). Work is scheduled to begin Winter 2023 and anticipated to be completed on Fall 2024. The project schedule depends upon weather conditions.



Have More Questions? Click here for more answers

  • August 2023 Update

    Share August 2023 Update on Facebook Share August 2023 Update on Twitter Share August 2023 Update on Linkedin Email August 2023 Update link

    The project has been partially completed and is facing a delay of around three weeks due to utility conflicts on Evergreen Street. This road is crucial for this project as all the side streets rely on it. The contractor is presently focusing on storm improvements along Evergreen Street from Alder Dr to Chimney Rock Rd. They have already completed the sanitary and water improvements. Once this section is completed, the next phase of work will begin on Alder Drive. from Evergreen Street. to Bissonnet Road. We are confident there will be no issues in completing the project on time.


  • April 2023 Update

    Share April 2023 Update on Facebook Share April 2023 Update on Twitter Share April 2023 Update on Linkedin Email April 2023 Update link

    The project is approximately 5% completed in place. Construction activities currently include the installation of wastewater and water lines on Evergreen between Alder and Chimney Rock.