August 2023 Update

The project has been partially completed and is facing a delay of around three weeks due to utility conflicts on Evergreen Street. This road is crucial for this project as all the side streets rely on it. The contractor is presently focusing on storm improvements along Evergreen Street from Alder Dr to Chimney Rock Rd. They have already completed the sanitary and water improvements. Once this section is completed, the next phase of work will begin on Alder Drive. from Evergreen Street. to Bissonnet Road. We are confident there will be no issues in completing the project on time.