Latest News

  • The City of Houston's Final Design is in progress (began on July 7, 2023). The topographic survey will be followed by geotechnical borings, environmental sampling, and archeological investigation.
  • Design refinement is ongoing for the Yale-Heights area channel widening, including coordination with overlapping TxDOT and METRO design projects.
  • Design refinement is ongoing for the North Canal area, with an evaluation of the ability to shift a portion of the channel to avoid building structure impacts.
  • Design coordination with TxDOT is ongoing for the North Houston Highway Improvement Project at the South Canal area.
  • Design coordination with METRO is ongoing for North Canal channel impacts to their existing Buffalo Bayou Facility and the planned replacement property.
  • Design coordination and advancement of required Union Pacific Railroad components have begun.
  • Coordination with key stakeholders has begun and will be an ongoing activity throughout the design.


Share Latest News on Facebook Share Latest News on Twitter Share Latest News on Linkedin Email Latest News link