North Corridor Consolidation Package 1
PROJECT NUMBER R-000536-0008
LOCATION Along Greens Rd. to Northgate Treatment Plant
COUNCIL DISTRICT B
BUDGET $31,096,430
TYPE Wastewater
START Fall 2020
COMPLETION Spring 2024
DETAILS The project provides for the implementation of a plan for the phased consolidation facilities.
MAP
What is the purpose of this project? This project will construct a new lift station and force main to divert flow to the Intercontinental Airport Wastewater Treatment Plant (WWTP) and decommission the Northgate WWTP. | |
PROJECT NUMBER R-000536-0008
LOCATION Along Greens Rd. to Northgate Treatment Plant
COUNCIL DISTRICT B
BUDGET $31,096,430
TYPE Wastewater
START Fall 2020
COMPLETION Spring 2024
DETAILS The project provides for the implementation of a plan for the phased consolidation facilities.
MAP
What is the purpose of this project? This project will construct a new lift station and force main to divert flow to the Intercontinental Airport Wastewater Treatment Plant (WWTP) and decommission the Northgate WWTP. | |
Is there anything you want us to know?
-
Share At the intersection of Greens Rd and Imperial Valley, the construction has progressed to this area. This has traffic flowing on both directions on the eastbound lanes at this intersection. We at METRO has buses that need to navigate the turn for Imperial Valley N/B to Greens Rd. E/B. This is difficult most of the time as the stop line is not recessed enough distance from the intersection and there is no sign indicating that the vehicles traveling Greens rd. W/B to "STOP HERE". We have asked the contractor to make the adjustment with no success. Could you please assist us with this concern. We would like to continue to service the bus stops in this area to service the community. on Facebook Share At the intersection of Greens Rd and Imperial Valley, the construction has progressed to this area. This has traffic flowing on both directions on the eastbound lanes at this intersection. We at METRO has buses that need to navigate the turn for Imperial Valley N/B to Greens Rd. E/B. This is difficult most of the time as the stop line is not recessed enough distance from the intersection and there is no sign indicating that the vehicles traveling Greens rd. W/B to "STOP HERE". We have asked the contractor to make the adjustment with no success. Could you please assist us with this concern. We would like to continue to service the bus stops in this area to service the community. on Twitter Share At the intersection of Greens Rd and Imperial Valley, the construction has progressed to this area. This has traffic flowing on both directions on the eastbound lanes at this intersection. We at METRO has buses that need to navigate the turn for Imperial Valley N/B to Greens Rd. E/B. This is difficult most of the time as the stop line is not recessed enough distance from the intersection and there is no sign indicating that the vehicles traveling Greens rd. W/B to "STOP HERE". We have asked the contractor to make the adjustment with no success. Could you please assist us with this concern. We would like to continue to service the bus stops in this area to service the community. on Linkedin Email At the intersection of Greens Rd and Imperial Valley, the construction has progressed to this area. This has traffic flowing on both directions on the eastbound lanes at this intersection. We at METRO has buses that need to navigate the turn for Imperial Valley N/B to Greens Rd. E/B. This is difficult most of the time as the stop line is not recessed enough distance from the intersection and there is no sign indicating that the vehicles traveling Greens rd. W/B to "STOP HERE". We have asked the contractor to make the adjustment with no success. Could you please assist us with this concern. We would like to continue to service the bus stops in this area to service the community. link
At the intersection of Greens Rd and Imperial Valley, the construction has progressed to this area. This has traffic flowing on both directions on the eastbound lanes at this intersection. We at METRO has buses that need to navigate the turn for Imperial Valley N/B to Greens Rd. E/B. This is difficult most of the time as the stop line is not recessed enough distance from the intersection and there is no sign indicating that the vehicles traveling Greens rd. W/B to "STOP HERE". We have asked the contractor to make the adjustment with no success. Could you please assist us with this concern. We would like to continue to service the bus stops in this area to service the community.
CarlTaylor asked over 1 year agoHowdy neighbor! Thank you for your comments and for sharing your concern. Per the project team, the contractor will make the adjustment to the traffic flow immediately to ensure safety and better traffic flow.
-
Share Is this project on schedule? By looking at the plans, it would seem that it is behind by about a year. The force main installation and consequent paving seems to stalled right in front of my apartment complex at 855 Greens Road. Thanks. on Facebook Share Is this project on schedule? By looking at the plans, it would seem that it is behind by about a year. The force main installation and consequent paving seems to stalled right in front of my apartment complex at 855 Greens Road. Thanks. on Twitter Share Is this project on schedule? By looking at the plans, it would seem that it is behind by about a year. The force main installation and consequent paving seems to stalled right in front of my apartment complex at 855 Greens Road. Thanks. on Linkedin Email Is this project on schedule? By looking at the plans, it would seem that it is behind by about a year. The force main installation and consequent paving seems to stalled right in front of my apartment complex at 855 Greens Road. Thanks. link
Is this project on schedule? By looking at the plans, it would seem that it is behind by about a year. The force main installation and consequent paving seems to stalled right in front of my apartment complex at 855 Greens Road. Thanks.
Dwcww855 asked over 1 year agoHowdy Neighbor, Thank you for your comment and sharing your concern. This project has been delayed due to the global material shortage. The project has been extended to ensure the contractor can procure all components needed to continue with construction. Thank you for your time and patience.
Follow Project
Project Phases
Documents
Who's Listening?
Public Engagement Team
Email Us: | Engage@houstontx.gov |