PROJECT NUMBER N-100029-0002

LOCATION Refer to map

COUNCIL DISTRICT G

BUDGET $25,410,000

TYPE Street

START Summer 2023

COMPLETION Fall 2025

DETAILS The work includes new concrete and asphalt pavement, curbs, wheelchair ramps, sidewalks, streetlights, and reconstruction of median openings. The existing drainage system will be upgraded with the installation of new stormwater, inlets, manholes, and inline detention. The existing water main will be replaced to include new fire hydrants and valves.


MAP

Project Map


General Project Information

What is the purpose of this project?

This project is a part of the Street and Traffic Capital Improvement project and is necessary to improve roadway and traffic mobility and to meet City of Houston Design Standards.


Have More Questions? Click here for more answers.

PROJECT NUMBER N-100029-0002

LOCATION Refer to map

COUNCIL DISTRICT G

BUDGET $25,410,000

TYPE Street

START Summer 2023

COMPLETION Fall 2025

DETAILS The work includes new concrete and asphalt pavement, curbs, wheelchair ramps, sidewalks, streetlights, and reconstruction of median openings. The existing drainage system will be upgraded with the installation of new stormwater, inlets, manholes, and inline detention. The existing water main will be replaced to include new fire hydrants and valves.


MAP

Project Map


General Project Information

What is the purpose of this project?

This project is a part of the Street and Traffic Capital Improvement project and is necessary to improve roadway and traffic mobility and to meet City of Houston Design Standards.


Have More Questions? Click here for more answers.

  • Traffic Closure

    Share Traffic Closure on Facebook Share Traffic Closure on Twitter Share Traffic Closure on Linkedin Email Traffic Closure link

    WHAT

    Traffic Closure at Overbrook Lane and Kirkwood

    WHEN

    February 9th to February 26th

    WHY

    To construct Water and Wastewater Lines

    WHO TO CONTACT

    Houston 311 reference Project Number N-100029-0002

  • Latest News

    Share Latest News on Facebook Share Latest News on Twitter Share Latest News on Linkedin Email Latest News link

    Completed to Date:

    • The contractor has completed the wastewater system improvements and continues to install the proposed wastewater system along the project alignment.
    • The contractor has commenced the installation of the 16-inch water line proposed along Kirkwood. Approximately 300 linear feet of the 3500 linear feet have been installed.

    Planned Work (Next 30 Days)

    • Continue installation of the wastewater system.
    • Continue installation of 16-inch water line. Start testing the water line.
    • The contractor anticipates the water and wastewater work will be completed in April.


  • Trees

    Share Trees on Facebook Share Trees on Twitter Share Trees on Linkedin Email Trees link

    The City understands the value and beauty of our trees and is committed to make sure we evaluate and preserve all trees within the project area when possible. However, due to the drainage, safety and mobility improvements planned for this project, some of the trees along Kirkwood Drive will be impacted and require removal. The good news is that no trees along Briar Forest will be impacted by this project.

    The City does have a tree ordinance that governs the removal, mitigation and care of trees within the City’s right-of-way for construction projects. At the conclusion of this project, the Contractor will be installing new trees along the project alignment to mitigate for the removal of the existing trees per the Ordinance. The tree protection plan for this project is posted here on the project page. Please subscribe to this page to receive the latest updates as they become available.

  • Traffic Switch

    Share Traffic Switch on Facebook Share Traffic Switch on Twitter Share Traffic Switch on Linkedin Email Traffic Switch link

    WHAT

    Traffic Switch

    WHEN

    Wednesday, January 10th at 1PM-Wednesday, February 14th at 7PM

    WHY

    To construct Water and Wastewater lines

    WHO TO CONTACT

    Houston 311 reference Project Number N-100029-0002


  • Latest News

    Share Latest News on Facebook Share Latest News on Twitter Share Latest News on Linkedin Email Latest News link
    • The contractor has installed tree protection measures (including fencing) throughout the project area.
    • The contractor has commenced pruning of the trees that are adjacent to the construction areas.
    • The contractor has started removing trees designated for removal in the project plans.
    • The water and sanitary sewer improvements will commence this month.
    • There will be moving lane closures to accommodate the water and sewer work.
Page last updated: 14 Nov 2024, 12:57 PM