Kirkwood Road - Subproject 2
PROJECT NUMBER N-100029-0002
LOCATION Refer to map
COUNCIL DISTRICT G
BUDGET $25,410,000
TYPE Street
START Summer 2023
COMPLETION Fall 2025
DETAILS The work includes new concrete and asphalt pavement, curbs, wheelchair ramps, sidewalks, streetlights, and reconstruction of median openings. The existing drainage system will be upgraded with the installation of new storm sewers, inlets, manholes, and inline detention. The existing water main will be replaced to include new fire hydrants and valves.
MAP
General Project Information
What is the purpose of this project? This project is a part of the Street and Traffic Capital Improvement project and is necessary to improve roadway and traffic mobility and to meet City of Houston Design Standards. |
PROJECT NUMBER N-100029-0002
LOCATION Refer to map
COUNCIL DISTRICT G
BUDGET $25,410,000
TYPE Street
START Summer 2023
COMPLETION Fall 2025
DETAILS The work includes new concrete and asphalt pavement, curbs, wheelchair ramps, sidewalks, streetlights, and reconstruction of median openings. The existing drainage system will be upgraded with the installation of new storm sewers, inlets, manholes, and inline detention. The existing water main will be replaced to include new fire hydrants and valves.
MAP
General Project Information
What is the purpose of this project? This project is a part of the Street and Traffic Capital Improvement project and is necessary to improve roadway and traffic mobility and to meet City of Houston Design Standards. |
-
Water Outage Reminder
Share Water Outage Reminder on Facebook Share Water Outage Reminder on Twitter Share Water Outage Reminder on Linkedin Email Water Outage Reminder linkAll businesses and homeowners who are projected to be out of water was notified by the Contractor on June 24th.
WHAT
Water Disruption
WHERE
Kirkwood from Westheimer to Southlake and along Westheimer (north side) from Grey Falls to Kirkwood. Small portion of the subdivision between Southlake and Waldemar.
WHEN
June 27th @ 6:30PM for 8-10 hours
WHY
To preform wet connections to the water line.
WHO TO CONTACT
Houston 311 reference Project # N-100029-0002
-
Water Service Outage
Share Water Service Outage on Facebook Share Water Service Outage on Twitter Share Water Service Outage on Linkedin Email Water Service Outage linkAn emergency repair is planned for this evening along Kirkwood between Overbrook and Southlake. It will likely shut off water in the area between these streets for at least 6-8 hours.
WHAT
Water Line Break
WHERE
Along Kirkwood
WHEN
June 25th
WHY
A break in the existing 16-inch water line
WHO TO CONTACT
Houston 311 reference Project # N-100029-0002
-
Traffic Update
Share Traffic Update on Facebook Share Traffic Update on Twitter Share Traffic Update on Linkedin Email Traffic Update linkWe are performing construction near Waldemar and Kirkwood crossing, our contractor has ensured that during peak hours, morning and afternoon, flaggers will be available to help get pedestrian traffic safely across. The flaggers will again be implemented by the contractor during the paving operations at this intersection. In addition, contractors will have additional barrels and traffic control devices in place during this construction.
-
Water Service Outage
Share Water Service Outage on Facebook Share Water Service Outage on Twitter Share Water Service Outage on Linkedin Email Water Service Outage linkResidents affected along Kirkwood from just south of Briar Forest to just north of Southlake Dr. and those residents along Waldemar from Cherry Bend to Kirkwood.
WHAT
Water Service Outage
WHEN
Friday March 1st from 7AM to 3PM
WHY
To tie in the new waterline
WHO TO CONTACT
Houston 311 reference project number N-100029-0002
-
Latest News
Share Latest News on Facebook Share Latest News on Twitter Share Latest News on Linkedin Email Latest News linkThe waterline has been repaired and all services have been restored,
-
Latest News
Share Latest News on Facebook Share Latest News on Twitter Share Latest News on Linkedin Email Latest News linkA water main break was reported on February 8th. The contractor is currently addressing the issue with urgency and diligence. Further updates will be provided as soon as they are available. Thank you for your patience and understanding.
-
Traffic Closure
Share Traffic Closure on Facebook Share Traffic Closure on Twitter Share Traffic Closure on Linkedin Email Traffic Closure linkWHAT
Traffic Closure at Overbrook Lane and Kirkwood
WHEN
February 9th to February 26th
WHY
To construct Water and Wastewater Lines
WHO TO CONTACT
Houston 311 reference Project Number N-100029-0002
-
Latest News
Share Latest News on Facebook Share Latest News on Twitter Share Latest News on Linkedin Email Latest News linkCompleted to Date:
- Contractor has completed the wastewater system improvements. Contractor continues to install the proposed wastewater system along the project alignment.
- Contractor has commenced the installation of the 16-inch water line proposed along Kirkwood. Approximately 300 linear feet of the 3500 linear feet has been installed to date.
Planned Work (Next 30 Days)
- Continue installation of wastewater system.
- Continue installation of 16-inch water line. Start testing the water line.
- Contractor anticipates the water and wastewater work will be completed in April.
-
Trees
Share Trees on Facebook Share Trees on Twitter Share Trees on Linkedin Email Trees linkThe City understands the value and beauty of our trees and is committed to make sure we evaluate and preserve all trees within the project area when possible. However, due to the drainage, safety and mobility improvements planned for this project, some of the trees along Kirkwood Drive will be impacted and require removal. The good news is that no trees along Briar Forest will be impacted by this project.
The City does have a tree ordinance that governs the removal, mitigation and care of trees within the City’s right-of-way for construction projects. At the conclusion of this project, the Contractor will be installing new trees along the project alignment to mitigate for the removal of the existing trees per the Ordinance. The tree protection plan for this project is posted here on the project page. Please subscribe to this page to receive the latest updates as they become available.
-
Traffic Switch
Share Traffic Switch on Facebook Share Traffic Switch on Twitter Share Traffic Switch on Linkedin Email Traffic Switch linkWHAT
Traffic Switch
WHEN
Wednesday, January 10th at 1PM-Wednesday, February 14th at 7PM
WHY
To construct Water and Wastewater lines
WHO TO CONTACT
Houston 311 reference Project Number N-100029-0002