Force Main Renewal for Plum Creek, Tanya Circle, and Old Stone Trail

Share on Facebook Share on Twitter Share on Linkedin Email this link

PROJECT NUMBER R-000035-011B

LOCATION Tanya Circle and Old Stone Trail: Refer to project map

COUNCIL DISTRICT G, I

BUDGET $1,002,769

TYPE Sanitary Sewer Replacement

START Fall 2020

COMPLETION Fall 2022

DETAILS The project will include replacement of sanitary force mains from Plum Creek, Old Stone Trail, and Tanya Circle Lift Stations (Old Stone Trail and Tanya Circle location).


MAP

Project Map




What is the purpose of this project?
This project will include the replacement of sanitary force mains from Plum Creek, Old Stone Trail, and Tanya Circle Lift Stations.


How long is this project going to take to complete?
4 Months (121 calendar days). Work is scheduled to begin on Monday, July 12, 2021 and anticipated to be completed by Spring 2022
.


Have More Questions? Click here for more answers

PROJECT NUMBER R-000035-011B

LOCATION Tanya Circle and Old Stone Trail: Refer to project map

COUNCIL DISTRICT G, I

BUDGET $1,002,769

TYPE Sanitary Sewer Replacement

START Fall 2020

COMPLETION Fall 2022

DETAILS The project will include replacement of sanitary force mains from Plum Creek, Old Stone Trail, and Tanya Circle Lift Stations (Old Stone Trail and Tanya Circle location).


MAP

Project Map




What is the purpose of this project?
This project will include the replacement of sanitary force mains from Plum Creek, Old Stone Trail, and Tanya Circle Lift Stations.


How long is this project going to take to complete?
4 Months (121 calendar days). Work is scheduled to begin on Monday, July 12, 2021 and anticipated to be completed by Spring 2022
.


Have More Questions? Click here for more answers

  • Bridge Demolition Activity

    Share on Facebook Share on Twitter Share on Linkedin Email this link

    Bridge Demo Activity

    • Install TCP/Pre Con Pictures
    • Trimming Shrubs/Vegetation
    • Begin Removing FM Pipe
    • Haul Away Abandoned Pipe
    • Mat Set-Up for Cranes
    • Mobilization for Crane & Set Up 11/8/2022
    • Beam Removal
    • Bridge Columns/Cut-Off & Removal
    • Beams Hauled Off
    • Bridge Columns/Cut-Off & Removal
    • Crane Disassembly & Demo
    • Haul-Away Pile Foundation from Bayou
    • Clean-Up Bayou Debris
    • Restoration
    • VACA Demo






  • Updated Phasing Map

    Share on Facebook Share on Twitter Share on Linkedin Email this link

    Please see project documents to view the latest construction phasing map or click here.

  • Manhole Delivery Today

    Share on Facebook Share on Twitter Share on Linkedin Email this link

    Contractor will be delivering a manhole on Tanya Circle. This delivery should only take a few hours this morning.

  • Dec. 8, 2021 On-site meeting

    Share on Facebook Share on Twitter Share on Linkedin Email this link

    Contractor Route Option Map


    On December 8, 2021 at 10:00 AM, a meeting was held at the Old Stone Trail Lift Station (LS) (WBS R-000035-011B-4) with the City of Houston project team, the Deputy Chief of Staff for Houston City Council District G, and an Old Stone Trail HOA representative to discuss the possible routes to access the proposed manhole construction location inside of the LS. One possible route (Route 1) was the LS entrance gate; however, it is too narrow for the excavator that needs to access. Another option was to use City of Houston easement (Route 2) on the west side of the LS; however, the route is too narrow with a tree blocking that path. The last option (Route 3) was to use the open area further west of the LS, and Route 3 is the most practical option available. The contractor agreed to restore any construction related damages to its original condition once complete.

    Also, the dirt piled up on the south side of the LS will be removed by the Contractor by Friday, December 10, 2021.

Page last updated: 07 Nov 2023, 03:19 PM