Share When will the Inwood Forrest flood control project be completed and grass planted? on Facebook Share When will the Inwood Forrest flood control project be completed and grass planted? on X (formerly Twitter) Share When will the Inwood Forrest flood control project be completed and grass planted? on Linkedin Email When will the Inwood Forrest flood control project be completed and grass planted? link
When will the Inwood Forrest flood control project be completed and grass planted?
Sanscott asked about 1 month agoReady...Set...ENGAGE!
Dear Sanscott,
Thank you for your question. The flood control work in the Inwood Forest area is a Harris County Flood Control District (HCFCD) initiative rather than a City of Houston project. According to HCFCD, the White Oak Bayou Federal Flood Damage Reduction Project was completed as of Q1 2026. For questions regarding grass installation or site restoration related to that work, we encourage you to contact HCFCD directly.
The City of Houston's Inwood Forest Area Drainage and Paving Project is a separate initiative, currently scheduled to begin construction in Winter 2028 with an anticipated completion date of Winter 2031. We appreciate your patience and your engagement with the project.
- Engage Houston Team
-
Share What's the latest on the Roseland Project, N-210005-0001? Still scheduled to start next month? on Facebook Share What's the latest on the Roseland Project, N-210005-0001? Still scheduled to start next month? on X (formerly Twitter) Share What's the latest on the Roseland Project, N-210005-0001? Still scheduled to start next month? on Linkedin Email What's the latest on the Roseland Project, N-210005-0001? Still scheduled to start next month? link
What's the latest on the Roseland Project, N-210005-0001? Still scheduled to start next month?
traviscpeiffer asked 4 months agoReady...Set...ENGAGE!
The project is now anticipated to begin in Spring 2026. A Virtual Community Meeting will be scheduled closer to the start of construction to share important details and answer questions. Thank you for your continued interest and support. We’ll keep you informed as the schedule is finalized and the project moves forward—stay tuned for more updates!
- The Engage Houston Team -
Share What is the status of the final stages regarding Garden Oaks and Shepherd Park drainage around Garden Oaks Elementary? When will this part of the project be started? on Facebook Share What is the status of the final stages regarding Garden Oaks and Shepherd Park drainage around Garden Oaks Elementary? When will this part of the project be started? on X (formerly Twitter) Share What is the status of the final stages regarding Garden Oaks and Shepherd Park drainage around Garden Oaks Elementary? When will this part of the project be started? on Linkedin Email What is the status of the final stages regarding Garden Oaks and Shepherd Park drainage around Garden Oaks Elementary? When will this part of the project be started? link
What is the status of the final stages regarding Garden Oaks and Shepherd Park drainage around Garden Oaks Elementary? When will this part of the project be started?
jeremiah_wheeler asked 5 months agoReady…Set…ENGAGE!
Thank you for reaching out and for your interest in the Garden Oaks and Shepherd Park (East) Drainage Improvements Project near Garden Oaks Elementary.
The project is currently in the planning and review phase. During this time, our team is evaluating community feedback, technical considerations, and overall priorities to help refine the design and ensure the best path forward.
We will be hosting a virtual community meeting to share updates and next steps, and we encourage you to stay tuned to EngageHouston.org for the latest information and meeting announcements.
We appreciate your patience and continued engagement as we work to improve drainage in the area.
– The Engage Houston Team
-
Share What is the status of the Gray and Taft Drainage and Paving Improvements Project? How can I access the video of the Virtual Design Update Meeting? on Facebook Share What is the status of the Gray and Taft Drainage and Paving Improvements Project? How can I access the video of the Virtual Design Update Meeting? on X (formerly Twitter) Share What is the status of the Gray and Taft Drainage and Paving Improvements Project? How can I access the video of the Virtual Design Update Meeting? on Linkedin Email What is the status of the Gray and Taft Drainage and Paving Improvements Project? How can I access the video of the Virtual Design Update Meeting? link
What is the status of the Gray and Taft Drainage and Paving Improvements Project? How can I access the video of the Virtual Design Update Meeting?
gardnersavage asked 5 months agoReady…Set…ENGAGE!
Thank you for your inquiry regarding the Gray and Taft Drainage and Paving Improvements Project. The project is currently in the planning phase, and a virtual community meeting will be scheduled once it is ready for public review. Please stay tuned for updates on EngageHouston.org.
- The Engage Houston Team