Easthaven to Southeast Wastewater Treatment Plant - Package 1

Share Easthaven to Southeast Wastewater Treatment Plant - Package 1 on Facebook Share Easthaven to Southeast Wastewater Treatment Plant - Package 1 on Twitter Share Easthaven to Southeast Wastewater Treatment Plant - Package 1 on Linkedin Email Easthaven to Southeast Wastewater Treatment Plant - Package 1 link

Project Overview

Council District: D

Project Number: R-000536-0034

Estimated Budget: $33,740,000

Start: Fall 2024

Completion: Summer 2026



Project Impact Area


Community Feedback

Have questions or feedback about this project? Email us at engage@houstontx.gov or call 311.

Project Overview

Council District: D

Project Number: R-000536-0034

Estimated Budget: $33,740,000

Start: Fall 2024

Completion: Summer 2026



Project Impact Area


Community Feedback

Have questions or feedback about this project? Email us at engage@houstontx.gov or call 311.

  • Latest News

    Share Latest News on Facebook Share Latest News on Twitter Share Latest News on Linkedin Email Latest News link

    The project is progressing well! Contractors are continuing tunnel construction and advancing work on the wastewater tunnel along Fuqua Street between Tower Bridge Street and Aldis Street. We’re pleased to share that the project remains on schedule for completion by Summer 2026.


  • Latest News

    Share Latest News on Facebook Share Latest News on Twitter Share Latest News on Linkedin Email Latest News link

    The project is progressing well! Contractors are actively working on tunnel construction and installing wastewater lines. We’re pleased to share that the project remains on schedule for completion by Summer 2026.


  • Latest News

    Share Latest News on Facebook Share Latest News on Twitter Share Latest News on Linkedin Email Latest News link

    The project is progressing well! Contractors are continuing work on the remaining tunneling activities, marking steady progress toward completion. We’re pleased to report that the project remains on schedule for completion by Summer 2026.


  • Latest News

    Share Latest News on Facebook Share Latest News on Twitter Share Latest News on Linkedin Email Latest News link

    The project is advancing well. Contractors are actively working on tunneling, an important step in moving the project forward. The project remains on schedule for completion in Summer 2026.


  • Latest News

    Share Latest News on Facebook Share Latest News on Twitter Share Latest News on Linkedin Email Latest News link

    The project continues to make steady progress. Crews are preparing for the next phase of tunneling work, with excavation and equipment installation underway at multiple locations. We’re pleased to report that the project remains on schedule for completion by Summer 2026.


  • Latest News

    Share Latest News on Facebook Share Latest News on Twitter Share Latest News on Linkedin Email Latest News link

    The project continues to move forward smoothly. The next phase of work will involve contractors beginning tunneling work soon. We’re pleased to report that the project remains on schedule for completion by Summer 2026. Thank you for your continued support as progress continues!